MNA-LMA-LGA headgate repair PIT upgrades
Ended Definitive Contract Awarded Last action
- Contract number
- W912EF21C0007
- Awardee
-
Record Steel And Construction, Inc. UEI G47MZHXDUE63
- Awarding agency
-
ENDIST Walla Walla
US Army Corps of Engineers, Department of Defense
- Obligated
- $12,652,222
Award facts
- Opportunity
-
- MNA-LGA-LMA Headgate Rep Pit Upgrades Pre-Solicitation · W912EF21B0007 · Posted Aug 24, 2020
- MNA-LGA-LMA Headgate Rep Pit Upgrades Award Notice · Posted Mar 11, 2021
- MNA-LGA-LMA Headgate Rep Pit Upgrades Solicitation · Posted Nov 6, 2020
- Contract value 100% obligated
- $12,652,221.50 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- Funding agency
- US Army Corps of Engineers Department of the Army, Department of Defense
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z2KA Repair Or Alteration Of Dams
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 4 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Umatilla, OR 97882, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | -$0 | |
| Supplemental Agreement for work within scope | $48,262 | |
| Change Order | $437,645 | |
| Other Administrative Action | $7,124 | |
| Other Administrative Action | $34,507 | |
| Supplemental Agreement for work within scope | $360,811 | |
| Change Order | $94,600 | |
| Change Order | $23,000 | |
| Supplemental Agreement for work within scope | $249,755 | |
| Supplemental Agreement for work within scope | $179,830 | |
| Other Administrative Action | -$11,138 | |
| Other Administrative Action | $47,127 | |
| Other Administrative Action | $368,198 | |
| Other Administrative Action | -$9,470 | |
| Funding Only Action | $227,151 | |
| Other Administrative Action | $23,698 | |
| Supplemental Agreement for work within scope | $74,697 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $60,303 | |
| Supplemental Agreement for work within scope | $19,348 | |
| Supplemental Agreement for work within scope | $24,666 | |
| Supplemental Agreement for work within scope | $4,636 | |
| Supplemental Agreement for work within scope | $6,072 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $117,547 | |
| Supplemental Agreement for work within scope | $44,326 | |
| Supplemental Agreement for work within scope | $8,410 | |
| Supplemental Agreement for work within scope | $31,246 | |
| Supplemental Agreement for work within scope | $23,400 | |
| Supplemental Agreement for work within scope | $95,223 | |
| Supplemental Agreement for work within scope | $25,629 | |
| Supplemental Agreement for work within scope | $30,000 | |
| Supplemental Agreement for work within scope | $1,036 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $9,786 | |
| Supplemental Agreement for work within scope | $53,899 | |
| Supplemental Agreement for work within scope | $38,688 | |
| Supplemental Agreement for work within scope | $12,241 | |
| Supplemental Agreement for work within scope | $19,187 | |
| Supplemental Agreement for work within scope | $26,782 | |
| Funding Only Action | $6,774,849 | |
| Supplemental Agreement for work within scope | $2,151 | |
| Supplemental Agreement for work within scope | $30,000 | |
| Other Administrative Action | $0 | |
| Original award | $3,037,000 |
Show all 45
About this award
This is a firm-fixed price construction contract awarded by the U.S. Army Corps of Engineers to Record Steel and Construction, Inc. (RSCI), a self-certified HUBZone joint venture, for $12,652,221.50. The contract is for upgrades to headgate repair pits at the McNary, Lower Monumental, and Little Goose dams located in Oregon and Washington. The work includes new utilities, drainage, exhaust, painting, lighting, demolition, and ventilation system improvements. There was no set-aside used for this full and open competition contract. The contract has a performance period through December 11, 2024, with anticipated completion of the McNary upgrades by mid-November 2021 and the Lower Monumental and Little Goose upgrades by mid-November 2022.
Quick answers
Who was awarded contract W912EF21C0007?
W912EF21C0007 was awarded to Record Steel And Construction, Inc. by ENDIST Walla Walla (US Army Corps of Engineers) on March 11, 2021.
How much is contract W912EF21C0007 worth?
The government has obligated $12,652,222 on W912EF21C0007.
Which agency awarded contract W912EF21C0007?
ENDIST Walla Walla (US Army Corps of Engineers) awarded W912EF21C0007, with funding from US Army Corps of Engineers (Department of the Army).
Was contract W912EF21C0007 competed?
The extent of competition for W912EF21C0007 was full and open competition. The government received 4 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award