Provide new 480V AC switchgear lineups

Ended Definitive Contract Awarded Last action

Contract number
W912EF20C0003
Awardee
Awarding agency
Obligated
$9,946,409

Award facts

Opportunity
Contract value 100% obligated
$9,946,408.85 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
US Army Corps of Engineers Department of the Army, Department of Defense
Set-aside
No set-aside
Competition
4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Pomeroy, WA 99347, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action A00041 · Replacement of inverters $297,330
Other Administrative Action A00040 · Governor oil pump motor couplings $29,087
Supplemental Agreement for work within scope A00039 · Annunciating to CQ05 and CQ04 feeders $15,681
Supplemental Agreement for work within scope A00038 · Welding receptacle added to CQ05 $16,469
Supplemental Agreement for work within scope A00037 $15,891
Supplemental Agreement for work within scope A00036 · Relocate SH annunciation $2,931
Supplemental Agreement for work within scope A00035 · Arms light and switches feeds $7,037
Supplemental Agreement for work within scope A00034 · Enlarge doorway in gallery at elev .640 $5,109
Supplemental Agreement for work within scope A00033 · Sensor plugs and cable upgrades. $52,471
Supplemental Agreement for work within scope A00032 -$530
Supplemental Agreement for work within scope A00031 · Ground wire to CR09 and tailrace wiring. $26,654
Supplemental Agreement for work within scope A00030 · Air dryer/compressor 1 & 2 feeds $9,871
Supplemental Agreement for work within scope A00029 · Control for high pressure thrust pump $10,236
Supplemental Agreement for work within scope A00028 · Convenience outlet sqoc $879
Supplemental Agreement for work within scope A00027 · TGB oil pump controls U1-3 $12,145
Supplemental Agreement for work within scope A00026 · TGB and HCP controls. $21,966
Supplemental Agreement for work within scope A00025 $17,913
Supplemental Agreement for work within scope A00024 · Relocate cable tray in equip. Gallery. $6,613
Supplemental Agreement for work within scope A00023 · Enlarge doorway in gallery at elev. 640 $4,000
Supplemental Agreement for work within scope A00022 · CQ1 main breaker upsize $2,999
Supplemental Agreement for work within scope A00021 · CE panels CE 1-6 changes $5,590
Supplemental Agreement for work within scope A00020 · Additional vertical section to MCC CQ04 $11,181
Supplemental Agreement for work within scope A00019 · FCQ2 panel replacement $21,541
Supplemental Agreement for work within scope A00018 · Redundant DC and preferred AC feed $49,308
Supplemental Agreement for work within scope A00017 · Additional vertical section to MCC CQ04 $0
Supplemental Agreement for work within scope A00016 · Cable and cable length adjustments $240,613
Funding Only Action P00001 · Incremental contract funding. $3,805,932
Supplemental Agreement for work within scope A00015 · Addtiional vertical section to MCC CQ04 $10,000
Supplemental Agreement for work within scope A00014 -$10,484
Supplemental Agreement for work within scope A00013 · Cabinet demo ER room. $2,172
Supplemental Agreement for work within scope A00012 $4,000
Supplemental Agreement for work within scope A00011 · Core drilling descope/cable reroute $27,762
Supplemental Agreement for work within scope A00010 · Governor oil motor changes $27,070
Supplemental Agreement for work within scope A00009 · CE panels CE 1-6 changes $2,000
Supplemental Agreement for work within scope A00008 · Additional 18" ladder tray $3,900
Supplemental Agreement for work within scope A00007 · Control panel SBC relocate. $5,967
Supplemental Agreement for work within scope A00006 · See ATT -$320,486
Supplemental Agreement for work within scope A00005 · Remove and dispose of exist transf 480V AC switchgear SQ0 & SQ1 remove and retain SQ2. -$45,000
Supplemental Agreement for work within scope A00004 · Networking system $24,244
Supplemental Agreement for work within scope A00003 · Outage change and surge protection. $3,688
Supplemental Agreement for work within scope A00002 · Temporary battery AMP-hours (CR005) $92,130
Supplemental Agreement for work within scope A00001 · SS transformers copper windings A00001 $78,838
Original award $5,351,690
Show all 43

About this award

The US Army Corps of Engineers awarded a $9.95 million definitive contract to Pick Electric, Inc. for provision of new 480V AC switchgear lineups and replacement of inverters on November 19, 2019, under no set-aside.

Place of performance is Pomeroy, WA. The contract was firm fixed price with an ultimate completion date of August 1, 2023. The solicitation was posted on May 20, 2019.

Quick answers

Who was awarded contract W912EF20C0003?

W912EF20C0003 was awarded to Pick Electric, Inc. by ENDIST Walla Walla (US Army Corps of Engineers) on November 19, 2019.

How much is contract W912EF20C0003 worth?

The government has obligated $9,946,409 on W912EF20C0003.

Which agency awarded contract W912EF20C0003?

ENDIST Walla Walla (US Army Corps of Engineers) awarded W912EF20C0003, with funding from US Army Corps of Engineers (Department of the Army).

Was contract W912EF20C0003 competed?

The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award