Arra::yes::arra recoveryproject#::107218::RP# B4L1430 FC/MR & t, yazoo river basin, big sunflower river, washington county, mississippi, steele bayou- item 66B channel relocation phase 2.

Ended Definitive Contract Awarded Last action

Contract number
W912EE09C0032
Awardee
Awarding agency
Obligated
$5,723,051

Award facts

Contract value 100% obligated
$5,723,050.70 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Greenville, MS 38701, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00007 · B4L1430 weather MOD time extension item 66B phase 2 $0
Change Order A00006 · Recoveryproject#::107218001490::RP# B4L1420 steele bayou- item 66B channel relocation phase 2 $3,125
Change Order P00001 · Recoveryproject#::107218001490::RP# B4L1430 steele bayou- item 66B channel relocation phase 2 $24,076
Other Administrative Action A00005 $0
Change Order A00004 · B4L1430 channel and ditch excavation $0
Change Order A00003 · B4L1430 item 66B time extension channel and ditch excavation $0
Other Administrative Action A00002 · BL41430 steele bayou-item 66B channel relocation phase 2, time EXT. Due to weather $0
Other Administrative Action A00001 · B4L1430 steele bayou- item 66B channel relocation phase 2, time EXT. $0
Original award $5,695,850

About this award

This is a federal contract award issued by the U.S. Army Corps of Engineers (USACE) Vicksburg District under the American Recovery and Reinvestment Act (ARRA) for the Yazoo River Basin Big Sunflower River project in Washington County, Mississippi. The contract, valued at $5,723,050.70, was awarded to Tri County Contractors Inc., a minority-owned small disadvantaged business. The work involves channel relocation for the Steele Bayou project, Phase 2. The contract is a firm-fixed-price definitive contract and was set aside for competitive 8(a) bidding. The project's ultimate completion date is scheduled for May 31, 2012.

Quick answers

Who was awarded contract W912EE09C0032?

W912EE09C0032 was awarded to Tri County Contractors Inc. by ENDIST Vicksburg (US Army Corps of Engineers) on September 4, 2009.

How much is contract W912EE09C0032 worth?

The government has obligated $5,723,051 on W912EE09C0032.

Was contract W912EE09C0032 competed?

The extent of competition for W912EE09C0032 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award