Rehabilitate the spillway gate assembly

Ended Definitive Contract Awarded Last action

Contract number
W912DW22C0015
Awardee
Awarding agency
Obligated
$2,651,276

Award facts

Opportunity
Contract value 24% obligated
  • $2,890,830.51 Current, with exercised options
  • $10,965,610.51 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Fixed Price with Economic Price Adjustment
Place of performance
Oldtown, ID 83822, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00003 $620,425
Supplemental Agreement for work within scope A00008 · Contract for albeni falls DAM spillway gate recoating and HSS weld repairs, oldtown, ID. At oldtown, ID. Reference no. R00011 $6,236
Other Administrative Action P00002 $0
Change Order P00001 -$1,355,000
Supplemental Agreement for work within scope A00007 $60,301
Supplemental Agreement for work within scope A00006 $45,681
Supplemental Agreement for work within scope A00005 · Contract for albeni falls DAM spillway gate recoating and HSS weld repairs, oldtown, ID. At oldtown, ID. Reference no. R00007 SP004 weld design change $76,329
Supplemental Agreement for work within scope A00004 · Turned studs torque requirement contract for albeni falls DAM spillway gate recoating and HSS weld repairs, oldtown, ID. At oldtown, ID. Reference no. R00006… $0
Supplemental Agreement for work within scope A00003 $60,823
Supplemental Agreement for work within scope A00002 $1,740
Supplemental Agreement for work within scope A00001 · Contract for albeni falls DAM spillway gate recoating and HSS weld repairs, oldtown, ID. At oldtown, ID. Reference no. R00001 SP001 roller and roller pin… $0
Original award $3,134,741
Show all 12

About this award

The U.S. Army Corps of Engineers Seattle District awarded a $10.97 million definitive contract to Garco Wemco A Joint Venture for recoating and high-strength steel weld repairs to the spillway gate assembly at Albeni Falls Dam on October 15, 2022, under no set-aside.

The contract is fixed price with economic price adjustment. The originating pre-solicitation, posted March 14, 2022, describes maintenance and repairs on the dam's 11 spillway gates, including removal of existing coatings, repair of deficient welds and structural components, replacement of roller chains, seals, and guide springs, reapplication of coatings, and return of gates to the dam. The work is staged because only one gate can be removed at a time without impacting operations; approximately three gates were to be repaired under initial funding with remaining work subject to additional fiscal year 2024 appropriations. Place of performance is Oldtown, ID. The ultimate completion date is February 8, 2026. NAICS code 237990 and PSC code Y1KA apply.

Quick answers

Who was awarded contract W912DW22C0015?

W912DW22C0015 was awarded to Garco Wemco A Joint Venture by ENDIST Seattle (US Army Corps of Engineers) on October 15, 2022.

How much is contract W912DW22C0015 worth?

The government has obligated $2,651,276 on W912DW22C0015. Its current value, with exercised options, is $2,890,831. Its potential value, with all options, is $10,965,611.

Was contract W912DW22C0015 competed?

The extent of competition for W912DW22C0015 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award