Hahd emergency closure system rehab

Ended Definitive Contract Awarded Last action

Contract number
W912DW22C0014
Awardee
Awarding agency
Obligated
$6,982,137

Award facts

Opportunity
Contract value 97% obligated
$7,200,870.82 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Ravensdale, WA 98051, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00008 · NW012, QTY VAR clins 0017, 0018 -$218,734
Supplemental Agreement for work within scope A00007 · NW010/NW011 global settlement contract for FY22 howard a. Hanson DAM (HHD) emergency closure system rehabilitation at howard hansen DAM, WA reference no. R00007 $473,000
Supplemental Agreement for work within scope A00006 $45,281
Supplemental Agreement for work within scope A00005 $120,981
Supplemental Agreement for work within scope A00004 $8,682
Supplemental Agreement for work within scope A00003 $50,264
Supplemental Agreement for work within scope A00002 $3,437
Supplemental Agreement for work within scope A00001 · Contract for FY22 howard a. Hanson DAM (HHD) emergency closure system rehabilitation at howard hansen DAM, WA. Reference no. R00001 NW001 hoist drum design… $0
Original award $6,499,225

About this award

The U.S. Army Corps of Engineers Seattle District awarded a $7.2 million definitive contract to BCI Construction USA Inc. for Howard A. Hanson Dam emergency closure system rehabilitation on November 1, 2022, under a total small business set-aside.

BCI Construction USA Inc. is a veteran-owned small business and service-disabled veteran-owned small business. Place of performance is Ravensdale, WA. The originating solicitation called for removal and replacement of the existing emergency gate and hoist, cleaning of trash racks, and handling of a spare stoplog at Howard A. Hanson Dam along the Green River, using barge-mounted cranes. The contract carries a firm fixed price structure with an ultimate completion date of March 31, 2026.

Quick answers

Who was awarded contract W912DW22C0014?

W912DW22C0014 was awarded to BCI Construction Usa, Inc. by ENDIST Seattle (US Army Corps of Engineers) on November 1, 2022.

How much is contract W912DW22C0014 worth?

The government has obligated $6,982,137 on W912DW22C0014. Its current value, with exercised options, is $7,200,871.

Was contract W912DW22C0014 competed?

The extent of competition for W912DW22C0014 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award