Design-build of a `class a waste water treatment plant (wwtp) with nutrient removal, to include redundant process equipment while applying an activated sludge system employing nutrient removal with…

Ended Definitive Contract Awarded Last action

Contract number
W912DW14C0002
Awardee
Awarding agency
Obligated
$82,348,844

Award facts

Opportunity
Contract value 100% obligated
$82,348,844.28 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 12 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Joint Base Lewis-McChord, WA, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00006 $1,712,060
Supplemental Agreement for work within scope A00020 $0
Supplemental Agreement for work within scope A00019 $44,839
Other Administrative Action A00018 $250,000
Supplemental Agreement for work within scope A00017 · Contract for FY13 (PN75165) wastewater treatment PH 1 at joint base lewis-mcchord, WA. Reference no. R00021 FL018 misc. Design changes through RFI-0070 -$20,019
Other Administrative Action P00005 · The purpose of this no-cost, administrative modification is to clarify that the modification executed on 03/25/2016 by the contracting officer, implementing… $0
Supplemental Agreement for work within scope P00004 · The purpose of this modification is to incorporate the negotiated PNM to finalize costs and time. $1,320,147
Supplemental Agreement for work within scope A00016 $50,454
Change Order P00003 $238,500
Supplemental Agreement for work within scope A00015 $349,481
Supplemental Agreement for work within scope A00014 $14,594
Supplemental Agreement for work within scope A00013 -$79,310
Supplemental Agreement for work within scope A00012 -$22,801
Change Order A00011 $0
Supplemental Agreement for work within scope A00010 $0
Supplemental Agreement for work within scope P00002 $472,746
Supplemental Agreement for work within scope A00009 $91,325
Supplemental Agreement for work within scope A00008 · Contract for FY13 (PN75165) wastewater treatment PH 1 at joint base lewis-mcchord, WA. Reference no. R00009 FL007 biosolids storage canopy/tree removal -$144,043
Change Order P00001 · All work to construct wwtp contract for FY13 (PN75165) wastewater treatment PH 1 at joint base lewis-mcchord, WA. Reference no. R00008 FL009-1 UCO - UV… $400,000
Supplemental Agreement for work within scope A00007 $89,333
Supplemental Agreement for work within scope A00006 $57,564
Supplemental Agreement for work within scope A00005 $17,346
Supplemental Agreement for work within scope A00004 -$20,000
Change Order A00003 $20,000
Change Order A00002 $30,000
Supplemental Agreement for work within scope A00001 · Contract for FY13 (PN75165) wastewater treatment PH 1 at joint base lewis-mcchord, WA. Reference no. R00001 FL001 e-submittals/soft copy pay apps see page 2. $0
Original award $77,476,628
Show all 27

Description

Design-build of a `class a waste water treatment plant (wwtp) with nutrient removal, to include redundant process equipment while applying an activated sludge system employing nutrient removal with tertiary membrane filtration, supporting a projected total population of 100,000 people at joint base lewis-mcchord, WA.

Quick answers

Who was awarded contract W912DW14C0002?

W912DW14C0002 was awarded to CDM Constructors Inc. by ENDIST Seattle (US Army Corps of Engineers) on January 16, 2014.

How much is contract W912DW14C0002 worth?

The government has obligated $82,348,844 on W912DW14C0002.

Was contract W912DW14C0002 competed?

The extent of competition for W912DW14C0002 was full and open competition. The government received 12 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award