Recoveryproject#::NZAS034001C:RP# NZAS034001C malmstrom repair structural foundations in minuteman village (179 units) this project is for the design and construction effort to correct structural…

Ended Definitive Contract Awarded Last action

Contract number
W912DW09C0028
Awardee
Awarding agency
Obligated
$26,108,661

Award facts

Opportunity
Contract value 100% obligated
$26,108,661.38 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Air Mobility Command Air Force, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Great Falls, MT 59401, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00064 $228,250
Supplemental Agreement for work within scope A00063 $207,936
Change Order A00062 -$333,452
Change Order A00061 $255,000
Change Order A00060 -$228,250
Supplemental Agreement for work within scope A00059 · Contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00048 SP028 PH B/C - added driveway… $159,680
Change Order A00057 $18,820
Change Order A00058 · All demolition contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00035 SP030-1 UCO, PH… $15,000
Supplemental Agreement for work within scope A00056 · Contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00033 SP033-2 definitize case SP033-1… $51,970
Supplemental Agreement for work within scope A00055 · All demolition contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00054 SP044 DEF pavement… $87,478
Supplemental Agreement for work within scope A00054 $36,890
Change Order A00053 $15,000
Supplemental Agreement for work within scope A00052 $19,500
Supplemental Agreement for work within scope A00051 $13,850
Supplemental Agreement for work within scope A00050 $8,330
Supplemental Agreement for work within scope A00049 $55,802
Change Order A00048 $25,000
Supplemental Agreement for work within scope A00047 -$26,185
Supplemental Agreement for work within scope A00046 -$20,690
Supplemental Agreement for work within scope A00045 $20,690
Change Order A00044 $90,000
Supplemental Agreement for work within scope A00043 -$22,400
Supplemental Agreement for work within scope A00041 $8,111
Supplemental Agreement for work within scope A00042 $13,095
Supplemental Agreement for work within scope A00039 $92,423
Supplemental Agreement for work within scope A00040 $18,474
Change Order A00038 $0
Supplemental Agreement for work within scope A00037 -$54,301
Supplemental Agreement for work within scope A00036 $82,506
Change Order A00035 -$110,916
Supplemental Agreement for work within scope A00034 $0
Change Order A00033 · Contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00050 SP047-1 NTP - phase C $0
Change Order A00032 $22,590
Supplemental Agreement for work within scope A00031 · Repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. AF recovery act funds used. Reference no. R00047 SP031-2 DEF PH B -… $8,520
Supplemental Agreement for work within scope A00030 · R38 SP024-2 definitizecase SP-24-1: repair PH a ST. AF recovery act funds used. $50,679
Change Order A00029 $15,000
Change Order A00028 · Contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00031 SP025-2 phase B NTP, DEF. SP025-1 $0
Change Order A00027 · R00030 SP036-1 UCO, PH B - basement subgrade DSC. AF recovery act funds were used. $35,650
Change Order A00026 · R00029 SP042-1 UCO, phase B exploratory work. AF recovery act funds were used. This change order constitutes a notice to proceed and makes $7500.00 available as… $7,500
Other Administrative Action P00005 · All demolition $0
Supplemental Agreement for work within scope A00025 · R00034 SP042-2 phase B exploratory work. AF recovery act funds were used. $11,035
Supplemental Agreement for work within scope A00024 · Reference no. R00028 SP038 inspect PH. B storm sewer all demolition. AF recovery act funds were used. $19,775
Supplemental Agreement for work within scope A00023 · Reference no. R00027 SP023 PH B/C: basement excavations. AF recovery act funds were used. $64,490
Change Order P00004 · Reference no. R00032 SP036-3 UCO II, PH B- basement subgrade DSC all demolition. AF recovery act funds were used. $91,850
Change Order A00022 · Reference no. R00022 SP026 delete units briarwood CT. AF recovery act funds. All demolition -$913,000
Supplemental Agreement for work within scope A00021 · Contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. AF recovery act funds were used. Reference no.… $10,372
Supplemental Agreement for work within scope A00020 $8,122
Supplemental Agreement for work within scope A00019 · All demolition contract for arra -- repair structural foundations minuteman village, malmstrom AFB at malmstrom AFB, MT. Reference no. R00021 SP018-2 definitize… $92,248
Change Order A00018 · R00023 SP024-1 NTP-repair PH. A storm sewer. AF recovery act funds were used. $44,663
Change Order A00017 · R00024 SP033-1 NTP-PH B/C - windows/wells. AF recovery act funds were used. $2,675
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This firm-fixed-price contract was awarded by the Air Mobility Command to Sunstar, LLC for the design and construction effort to correct structural issues in 179 military family housing units at Malmstrom Air Force Base in Great Falls, Montana. The $26,108,661.38 contract does not utilize any set-aside designation and is scheduled for completion by January 23, 2013. The project involves replacing partition walls, window wells, caulking floor slabs, installing a drainage system, and repairing surrounding pavements and utilities that have been damaged. No information is provided about any major subcontractors.

Description

Recoveryproject#::NZAS034001C:RP# NZAS034001C malmstrom repair structural foundations in minuteman village (179 units) this project is for the design and construction effort to correct structural walls and floor slabs in 179 military family housing units. Work includes replacing partition walls, window wells, caulking floor slab perimeter, installing drain system with sump pump under floor slab, topsoil and SOD replacement for surface drainage. Additionally, construction will correct surrounding pavements and utilities that have been damaged and require repair.

Quick answers

Who was awarded contract W912DW09C0028?

W912DW09C0028 was awarded to Sunstar, LLC by ENDIST Seattle (US Army Corps of Engineers) on September 16, 2009.

How much is contract W912DW09C0028 worth?

The government has obligated $26,108,661 on W912DW09C0028.

Which agency awarded contract W912DW09C0028?

ENDIST Seattle (US Army Corps of Engineers) awarded W912DW09C0028, with funding from Air Mobility Command (Air Force).

Was contract W912DW09C0028 competed?

The extent of competition for W912DW09C0028 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award