Construct 6 bldgs

Ended Definitive Contract Awarded Last action

Contract number
W912DW08C0008
Awardee
Awarding agency
Obligated
$3,807,289

Award facts

Opportunity
Contract value 100% obligated
  • $3,807,289.00 Current, with exercised options
  • $3,817,589.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Air Force Space Command Air Force, Department of Defense
NAICS code
236115 New Single-Family Housing Construction (except For-Sale Builders)
PSC
Y161 Construct/Family Housing
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Malmstrom AFB, MT 59402, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00019 · Construct 6 bldgs R00020 SP018 vinyl fence post anchorage $0
Change Order A00017 · Construct 6 bldgs R00018 SP017 natural gas leakage $1,690
Change Order A00018 · Construct 6 bldgs R00019 SP016 add retaining walls to bldg #50 and #72 $53,675
Change Order A00016 · Construct 6 bldgs R00017 SP019 garage ceiling access hatches $2,910
Change Order A00015 · Construct 6 bldgs R00016 SP020 weather delays may - august 2009 $0
Change Order A00014 · Construct 6 bldgs R00015 SP015 final QTY clin 0006 "additional piles" -$3,735
Change Order A00013 · Construct 6 bldgs R00014 SP014 raise gas valve boxes at bldg #49 $2,023
Change Order A00012 · Construct 6 bldgs R00013 SP010 raise existing retaining wall elevation $5,849
Change Order A00011 · Construct 6 bldgs R00009 SP013 weather delays january - april 2009 $0
Change Order A00010 · Construct 6 bldgs R00012 SP011 pressure test chestnut ST. Water main $1,219
Change Order A00009 · Construct 6 bldgs R00011 SP008 add sump pumps $15,902
Change Order A00008 · Construct 6 bldgs R00010 SP006 temporary fall protection anchors $1,213
Change Order A00007 · Construct 6 bldgs R00008 SP012 remove and replace sidewalks $4,000
Change Order A00006 · Construct 6 bldgs R00007 SP007 light fixture 'H' -$447
Change Order A00004 · Construct 6 bldgs R00005 SP001 differing site conditions thru 20JAN2009 $7,594
Change Order A00005 · Construct 6 bldgs R00006 SP002 raise sewer line elevation $0
Change Order P00001 · Construct 6 bldgs R00004 SP009 pressure test the water main $1,466
Change Order A00003 · Construct 6 bldgs R00003 SP005 afci breakers $775
Change Order A00002 · Construct 6 bldgs R00002 SP004 bldg 49: groundwater at water connection $2,155
Change Order A00001 · Construct 6 bldgs R00001 SP003 weather delays november - december 2008 $0
Original award $3,711,000
Show all 21

Quick answers

Who was awarded contract W912DW08C0008?

W912DW08C0008 was awarded to Oswood Construction Company by ENDIST Seattle (US Army Corps of Engineers) on September 21, 2008.

How much is contract W912DW08C0008 worth?

The government has obligated $3,807,289 on W912DW08C0008. Its potential value, with all options, is $3,817,589.

Which agency awarded contract W912DW08C0008?

ENDIST Seattle (US Army Corps of Engineers) awarded W912DW08C0008, with funding from Air Force Space Command (Air Force).

Was contract W912DW08C0008 competed?

The extent of competition for W912DW08C0008 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award