Award facts
- Opportunity
-
- W912DW06R0016 Solicitation number
-
Contract value
100% obligated
-
$54,065,832.00
Current and potential, with all options
-
Completion date
100% complete
-
Current and potential, with all options
- Set-aside
- No set-aside
- Competition
-
Full and Open Competition · 2 offers
Two Step
- Pricing
- Firm Fixed Price
- Place of performance
- Mountain Home AFB, ID 83648, USA
Award details come from SAM.gov/FPDS.
Transactions
| Action |
Obligated |
Date |
|
Change Order
A00045 · All work for construction of phase VII R00048 MH050 provide storm doors
|
$40,783 |
|
|
Other Administrative Action
P00005 · All work for construction of phase VII
|
$0 |
|
|
Change Order
A00044 · All work for construction of phase VII R00047 MH049 increase rock excavation quantities
|
$64,008 |
|
|
Definitize Change Order
A00043 · All work for construction of phase VII R00046 MH030 definitize MH036 user/landscape changes
|
$33,438 |
|
|
Change Order
A00042 · All work for construction of phase VII R00045 MH046 relocate pacer loop playground
|
$3,034 |
|
|
Change Order
A00041 · All work for construction of phase VII R00044 MH048 fences and boundary landscaping
|
$168,000 |
|
|
Change Order
A00040 · All work for construction of phase VII R00042 MH045 modify northern boundary landscaping
|
-$57,230 |
|
|
Change Order
A00039 · All work for construction of phase VII R00043 MH047 landscaping changes
|
$420,000 |
|
|
Change Order
A00038 · All work for construction of phase VII R00041 MH044 import soils due to rock excavation
|
$28,420 |
|
|
Change Order
A00037 · All work for construction of phase VII R00040 MH043 increase rock excavation quantities
|
$144,900 |
|
|
Change Order
A00036 · All work for construction of phase VII R00039 MH015 delete PCS removal
|
-$21,900 |
|
|
Change Order
A00035 · All work for construction of phase VII R00038 MH038 delete FGO vinyl porch railing
|
-$6,275 |
|
|
Other Administrative Action
A00034 · All work for construction of phase VII R00037 MH042 admin change - correct contract amount
|
$0 |
|
|
Change Order
A00033 · All work for construction of phase VII R00036 MH040 weather delays april - june 2008
|
$0 |
|
|
Change Order
A00032 · All work for construction of phase VII R00035 MH039 import soils due to rock excavation
|
$77,508 |
|
|
Change Order
A00031 · All work for construction of phase VII R00033 MH033 reroute existing well water line
|
$42,263 |
|
|
Change Order
A00030 · All work for construction of phase VII R00034 MH031 modify disposal location for rock waste
|
$0 |
|
|
Change Order
A00029 · All work for construction of phase VII R00032 MH024 modify jogging pathways
|
-$13,067 |
|
|
Change Order
A00028 · All work for construction of phase VII R00031 MH037 increase rock excavation quantities
|
$90,720 |
|
|
Change Order
A00027 · All work for construction of phase VII R00029 MH028 construct water pressure zone tie
|
$58,159 |
|
|
Change Order
A00026 · All work for construction of phase VII R00030 MH036 notice to proceed case MH030
|
$25,000 |
|
|
Change Order
A00024 · All work for construction of phase VII R00027 MH026 modify sinks, unit types i and j
|
$3,712 |
|
|
Change Order
A00025 · All work for construction of phase VII R00028 MH032 change color for switches and covers
|
$5,270 |
|
|
Change Order
A00023 · All work for construction of phase VII R00026 MH034 weather delays january - march 2008
|
$0 |
|
|
Change Order
A00022 · All work for construction of phase VII R00025 MH035 notice to proceed (NTP) for case MH033
|
$37,500 |
|
|
Change Order
A00021 · All work for construction of phase VII R00024 MH025 modify master bath, unit type "n"
|
$1,355 |
|
|
Change Order
A00020 · All work for construction of phase VII R00023 MH029 weather delays october - december 2007
|
$0 |
|
|
Change Order
A00019 · All work for construction of phase VII R00018 MH018 delete common area lighting
|
-$71,507 |
|
|
Change Order
A00018 · All work for construction of phase VII R00021 MH019 relocate duplex CGO unit
|
$6,455 |
|
|
Change Order
A00017 · All work for construction of phase VII R00022 MH008 modify design/build of volcano loop
|
-$26,659 |
|
|
Change Order
A00016 · All work for construction of phase VII R00020 MH017 wood door frames for exterior doors
|
-$7,401 |
|
|
Change Order
A00015 · All work for construction of phase VII R00017 MH016 revise exterior door hinges
|
-$12,062 |
|
|
Change Order
A00014 · All work for construction of phase VII R00019 MH027 miscellaneous hardware changes
|
$0 |
|
|
Change Order
A00013 · All work for construction of phase VII R00016 MH022 modify manhole 43 rim elevation
|
$0 |
|
|
Change Order
A00012 · All work for construction of phase VII R00015 MH023 provide dimensional roof shingles
|
$25,801 |
|
|
Change Order
P00004 · All work for construction of phase VII R00014 MH021 increase rock excavation quantities
|
$549,360 |
|
|
Change Order
A00011 · All work for construction of phase VII R00013 MH020 weather delays july - september 2007
|
$0 |
|
|
Change Order
A00010 · All work for construction of phase VII R00012 MH014 delete photocells; add contract clause
|
-$2,836 |
|
|
Change Order
P00003 · All work for construction of phase VII R00011 MH013 increase rock excavation quantities
|
$1,290,240 |
|
|
Change Order
A00009 · All work for construction of phase VII R00009 MH012 weather delays january - june 2007
|
$0 |
|
|
Change Order
A00008 · All work for construction of phase VII R00008 MH010 increase wall insulation r-value
|
$39,030 |
|
|
Change Order
A00007 · All work for construction of phase VII R00010 MH011 relocate well 6 water line
|
$90,613 |
|
|
Change Order
P00002 · All work for construction of phase 7 R00007 MH009 NTP case MH008
|
$170,000 |
|
|
Change Order
A00006 · All work for construction of phase VII R00006 MH007 repair damaged irrigation supply
|
$4,803 |
|
|
Change Order
A00005 · All work for construction of phase VII R00005 MH006 delete final air clearance sampling
|
-$3,298 |
|
|
Change Order
A00004 · All work for construction of phase VI R00004 MH005 water well elec supply
|
-$3,356 |
|
|
Change Order
A00003 · All work for construction of phase VII R00003 MH002 UG storage tank PCS removal
|
$21,900 |
|
|
Change Order
A00002 · All work for construction of phase VII R00002 MH001 add demolition of building 4640
|
$23,681 |
|
|
Change Order
A00001 · R00001 MH004 onsite office and garage gypboard
|
$0 |
|
|
Other Administrative Action
P00001 · MOD to fix line items by unit price.
|
-$34,000 |
|
Quick answers
Who was awarded contract W912DW06C0023?
W912DW06C0023 was awarded to Hunt Building Company, LTD by ENDIST Seattle (US Army Corps of Engineers) on September 27, 2006.
How much is contract W912DW06C0023 worth?
The government has obligated $54,065,832 on W912DW06C0023.
Which agency awarded contract W912DW06C0023?
ENDIST Seattle (US Army Corps of Engineers) awarded W912DW06C0023, with funding from Air Force Space Command (Air Force).
Was contract W912DW06C0023 competed?
The extent of competition for W912DW06C0023 was full and open competition. The government received 2 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award