Port monmouth flood reduction project

Active Definitive Contract Awarded Last action

Contract number
W912DS25C0001
Awardee
Awarding agency
Obligated
$69,773,732

Award facts

Opportunity
Contract value 96% obligated
  • $71,179,474.14 Current, with exercised options
  • $72,634,474.14 Potential, with all options
Completion date 49% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Belford, NJ 07718, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00011 $203,037
Change Order P00004 $1,500,000
Exercise an Option P00003 $400,000
Change Order A00010 · RFP-0019 (NS#023), broadway avenue drainage concrete culvert $35,201
Change Order P00002 $3,600,000
Change Order A00009 · Campbell avenue bridge poles and wire to be removed up until JC2840MDT (RFP0017 PART2) $431,619
Change Order A00008 $246,151
Change Order A00007 · Jcpl materials for primary RE-locations $223,900
Change Order A00006 $61,801
Change Order A00005 · Contract 4B, port monmouth hurricane and storm damage reduction. Construction of floodwalls, retaining walls, earthen levees, interior drainage features… $276,758
Change Order A00004 · NS009 - water sampling to delineate the extents of the contaminated water. $177,673
Change Order A00003 · Change: NS006 title: 38 willow AVE. - shed replacement $285,343
Supplemental Agreement for work within scope A00002 · Floodwall reference no: A00002, R00002 NS002 verizon overhead utility lines NS003 tomsa - hozizontal lines $23,332
Supplemental Agreement for work within scope A00001 · Floodwall reference no: A00001, R00001 NS004 levee subbase - select granular fill $443,791
Other Administrative Action P00001 · Port monmouth contract 4B $0
Original award $61,865,125
Show all 16

About this award

The U.S. Army Corps of Engineers, New York District, awarded a $69.5 million firm fixed-price definitive contract to Anselmi & De Cicco, Inc. for the Port Monmouth Hurricane and Storm Damage Reduction Project, Phase II, Contract 4B on November 21, 2024, under a total small business set-aside.

The scope includes construction of 1,521 linear feet of floodwall, 1,040 linear feet of levee, 3,100 cubic yards of contaminated non-hazardous material removal, 15,510 cubic yards of excess material haul and disposal, 2,405 cubic yards of borrow material placement, two road closure gates, and 119,300 linear feet of steel H-piles, with eleven static load tests for primary and secondary test piles. Work is located in Belford, NJ. The base period of performance spans 1,300 calendar days from notice to proceed. NAICS code 237990 applies.

Quick answers

Who was awarded contract W912DS25C0001?

W912DS25C0001 was awarded to Anselmi & De Cicco, Inc. by ENDIST New York (US Army Corps of Engineers) on November 21, 2024.

How much is contract W912DS25C0001 worth?

The government has obligated $69,773,732 on W912DS25C0001. Its current value, with exercised options, is $71,179,474. Its potential value, with all options, is $72,634,474.

Was contract W912DS25C0001 competed?

The extent of competition for W912DS25C0001 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award