Rolling closure gates (segments C2 & H)

Active Definitive Contract Awarded Last action

Contract number
W912DS23C0005
Awardee
Awarding agency
Obligated
$61,413,619

Award facts

Opportunity
Contract value 98% obligated
  • $62,603,628.30 Current, with exercised options
  • $62,683,629.30 Potential, with all options
Completion date 77% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 11 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
New York, NY 10278, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00005 $3,584,725
Change Order A00021 · Excess soil disposal quantity adjustments. $156,120
Change Order A00020 $430,000
Supplemental Agreement for work within scope A00019 -$269,437
Other Administrative Action P00004 $0
Change Order A00018 · Modification A00018 - additional fencing $270,000
Supplemental Agreement for work within scope A00017 · Segment H levees and ponds MOD# A00017, NS036, NS037 $31,220
Supplemental Agreement for work within scope A00016 · Segment H levees and ponds modification no. A00016 R00019 - verizon conduit relocation $161,854
Exercise an Option P00003 · Segment H levees and ponds $11,033,112
Supplemental Agreement for work within scope A00015 · Segment C2 levee and BDR2 pond modification no. A00015 R00017 - boro paving & S lincoln fence/sanitary $234,660
Supplemental Agreement for work within scope A00013 · Segment C2 levee and BDR2 pond REF modification no. A00013 R00015 - additional paving NS020/028/029 $411,000
Supplemental Agreement for work within scope A00012 · Segment C2 levee and BDR2 pond reference no: A00012 / R00014 NS030 C2 & H pseg gas installation on S lincoln AVE $196,570
Supplemental Agreement for work within scope A00010 · Segment C2 levee and BDR2 pond reference no: A00010, R00001 NS024 pseg gas sleeve $22,420
Supplemental Agreement for work within scope P00002 $0
Exercise an Option P00001 · Segment C2 levee and BDR2 pond $20,987,136
Supplemental Agreement for work within scope A00009 · Rolling closure gates (segments C2 & H) reference no: A00009, R00009 NS021 american water line stops, NS022 njaw 20" tapping sleeve $127,000
Supplemental Agreement for work within scope A00008 · Rolling closure gates (segments C2 & H) reference no: A00008, R00008 NS011 culvert grading and stone removal. NS013 2024 property maintenance NS017 pipe… $355,010
Supplemental Agreement for work within scope A00007 · Rolling closure gates (segments C2 & H) reference no: A00007, R00007 NS016 20" water line replacement $457,400
Supplemental Agreement for work within scope A00006 · Rolling closure gates (segments C2 & H) reference no: A00006, R00006 NS015 8" water line relocation $321,560
Supplemental Agreement for work within scope A00005 · Rolling closure gates (segments C2 & H) reference no: A00005, R00005 NS014 american water insertion valves. $165,764
Supplemental Agreement for work within scope A00004 · Rolling closure gates (segments C2 & H) reference no: A00004, R00004 NS009 drainage changes - segment H NS010 drainage changes - segment C $82,555
Supplemental Agreement for work within scope A00003 · Rolling closure gates (segments C2 & H) reference no: A00003, R00003 NS008 pseg test pits $17,897
Supplemental Agreement for work within scope A00002 $64,490
Supplemental Agreement for work within scope A00001 · Rolling closure gates (segments C2 & H) reference no: A00001, R00001 NS001 2023 property maintenance $15,727
Original award $22,608,346
Show all 25

About this award

ENDIST New York, a Defense-designated funding agency, awarded a firm-fixed-price definitive contract to Carbro Constructors Corp on March 15, 2023, with a ceiling value of $61.97 million for rolling closure gates and excess soil disposal quantity adjustments on the Green Brook Flood Risk Management Project. No set-aside was used. Ultimate completion is December 31, 2027.

Place of performance is New York, NY 10278. The originating pre-solicitation, posted May 10, 2022 with responses due May 26, 2022, places the Green Brook project in Middlesex, New Jersey, and describes a construction contract with the U.S. Army Corps of Engineers New York District for pump stations, levees, floodwalls, and road closure gates. Segment C2 covers two pump stations, 1,700 feet of levee, 100 feet of floodwall, and one road closure gate. Segment H covers 3,600 feet of levee tied to a railroad embankment, 576 feet of floodwall, and another road closure gate. Work must comply with local, state, and federal law and coordinate any necessary utility relocations. The primary NAICS code is 237990 (other heavy and civil engineering construction), with a size standard of $33.5 million.

Quick answers

Who was awarded contract W912DS23C0005?

W912DS23C0005 was awarded to Carbro Constructors Corp by ENDIST New York (US Army Corps of Engineers) on March 15, 2023.

How much is contract W912DS23C0005 worth?

The government has obligated $61,413,619 on W912DS23C0005. Its current value, with exercised options, is $62,603,628. Its potential value, with all options, is $62,683,629.

Was contract W912DS23C0005 competed?

The extent of competition for W912DS23C0005 was full and open competition. The government received 11 offers.

On GovTribe

See this award's full record