Port monmouth contract 5, new jersey

Ended Definitive Contract Awarded Last action

Contract number
W912DS22C0017
Awardee
Awarding agency
Obligated
$47,854,730

Award facts

Contract value 100% obligated
$48,079,729.65 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 15 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Maplewood, NJ 07040, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00018 $11,500
Change Order A00017 · Port monmouth hurricane and storm damage reduction project, phase II, contract 5 $74,500
Other Administrative Action P00005 · Administrative modification $0
Supplemental Agreement for work within scope A00016 · Option 3 reference no: A00016, R00020 NS030 pump station security fence, NS033 final H-pile quantity, NS034 sprinkler system repair, NS035 main street paving $341,171
Supplemental Agreement for work within scope A00015 · Option 3 reference no: A00015, R00019 NS032 additional H pile quantity $467,767
Supplemental Agreement for work within scope A00014 · Option 3 reference no: A00014, R00018 NS031 phase 3 - dispose unsat material - OP3 $350,569
Supplemental Agreement for work within scope A00013 · Option 3 reference no: A00013, R00017 NS028 phase 2 dispose unsat material OP3 $432,247
Supplemental Agreement for work within scope A00012 · Option 3 reference no: A00012, R00016 NS026 phase 1 dispose unsat material OP3 $366,759
Supplemental Agreement for work within scope A00011 · Option 3 reference no: A00011, R00015 NS024 additional quantity of herbivory fence $169,620
Supplemental Agreement for work within scope A00010 · Option 3 reference no: A00010, R00014 NS023 seeding area reduced -$5,800
Supplemental Agreement for work within scope A00009 · Option 3 reference no: A00009, R00013, NS022 environmental landscaping (L 101) change. $341,133
Supplemental Agreement for work within scope A00008 · Option 3 reference no: A00008, R00012 NS010 power and comm to overhead. -$11,000
Supplemental Agreement for work within scope A00007 · Option 3 reference no: A00007, R00011 NS018 dispose excess & unsat - OPT 2 $307,972
Supplemental Agreement for work within scope A00006 · Option 3 reference no: A00006, R00010 NS006, NS008, NS009, NS011, NS016, NS017, NS020 $207,260
Supplemental Agreement for work within scope A00005 · Option 3 reference no: A00005, R00009 NS012 port monmouth RD - relocate watermain $495,000
Exercise an Option P00004 · Exercise of optional contract line item numbers (CLIN) for award of options 3 through 5, 8 through 11, & 13 under contract no. W912DS22C0017, port monmouth,… $13,250,700
Exercise an Option P00003 · Exercise of option 2 (clin 0018) $5,990,000
Supplemental Agreement for work within scope A00003 · Reference no. R00005 NS004 dispose excess & unsat swales base & OPT 1 $438,660
Supplemental Agreement for work within scope A00004 · Reference no. R00006 NS005 dispose excess & unsat surcharge & elliptical pipe $185,085
Supplemental Agreement for work within scope A00002 · Reference no. R00004 NS002 dispose excess & unsat levee TOE drain $407,938
Supplemental Agreement for work within scope A00001 · Reference no. R00003 NS007 main ST utility conflict - njng $120,000
Exercise an Option P00002 · Exercise of options 1 and 6 $0
Change Order P00001 · In-situ soil stabilization $2,600,000
Original award $21,313,650
Show all 24

About this award

ENDIST New York, a Defense agency, awarded a $48.08 million firm-fixed-price definitive contract to Anselmi & De Cicco, Inc. on September 7, 2022, for Phase II, Contract 5 of the Port Monmouth Hurricane and Storm Damage Reduction Project in New Jersey, with no set-aside used. Ultimate completion is October 30, 2026.

The originating pre-solicitation, posted by the U.S. Army Corps of Engineers, New York District on December 22, 2021, anticipated an Invitation for Bid for 1,190 linear feet of floodwall, 2,420 linear feet of levee, 261 linear feet of retaining wall, 37,732 cubic yards of embankment fill, and relocation of 1,824 linear feet of underground utilities. Key elements include two 40 cubic-feet-per-second pumps and 28,600 linear feet of piles. Place of performance is recorded as Maplewood, New Jersey, while the solicitation locates the work in Middletown Township, Monmouth County, New Jersey.

The pre-solicitation estimated construction cost at $10 million to $25 million, proposed 570 base calendar days plus three option periods totaling 935 additional calendar days, and assigned NAICS 237990 with a $39.5 million size standard.

Quick answers

Who was awarded contract W912DS22C0017?

W912DS22C0017 was awarded to Anselmi & De Cicco, Inc. by ENDIST New York (US Army Corps of Engineers) on September 7, 2022.

How much is contract W912DS22C0017 worth?

The government has obligated $47,854,730 on W912DS22C0017. Its current value, with exercised options, is $48,079,730.

Was contract W912DS22C0017 competed?

The extent of competition for W912DS22C0017 was full and open competition. The government received 15 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award