Renovation of the science center at west point NY usma

Ended Definitive Contract Awarded Last action

Contract number
W912DS11C0023
Awardee
Awarding agency
Obligated
$127,916,854

Award facts

Opportunity
Contract value 100% obligated
$127,916,854.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y119 Construct/Other Admin & Svcs Bldgs
Set-aside
No set-aside
Competition
Full and Open Competition · 12 offers Two Step
Pricing
Firm Fixed Price
Place of performance
West Point, NY 10996, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00089 · All work associated with MOD A00089 R00092 $15,003
Change Order A00088 · MOD A00088 R00091 $46,116
Change Order A00087 · All work associated with MOD A00087 R00090 $37,855
Change Order A00086 · MOD A00086 R00089 $109,701
Change Order A00085 · MOD A00085 R00088 $12,547
Change Order A00084 · All work associated with MOD A00084 R00087 $24,437
Change Order A00083 · All work associated with MOD A00083 R00086 $23,291
Change Order A00082 · All work associated with the renovation A00082 R00085 $20,376
Change Order A00081 · All work associated with the MOD A00081 R00084 $281,761
Change Order A00080 · All work associated with MOD A00080 R00083 $40,349
Change Order A00079 · A00079 R00082 $149,000
Change Order A00078 · All work associated with the MOD A00078 R00081 $0
Change Order A00077 · All work associated with the renovation of 753 MOD A00077 R00080 $8,125
Change Order A00076 · All work associated with the MOD A00076 $85,158
Change Order A00075 · All work associated with change A00075 R00078 $7,949
Supplemental Agreement for work within scope P00004 · Perform all remote chiller plant work included in DOR-prepared and issued bulletin 60R $7,344,163
Change Order A00074 · Summer cooling 2019 $201,587
Change Order A00073 · Heat recovery chiller revisions/condenser water chemical treatment $42,521
Change Order A00072 · Crane claim settlement/FPS corrections $118,489
Change Order A00070 · RCP clean condenser pipe $173,557
Change Order A00071 · UPS battery replacement REA $92,203
Change Order A00069 · R0067 misc mech changes $78,546
Change Order P00003 · All work associated with the renovation $614,558
Change Order A00068 · Multi changes $91,321
Supplemental Agreement for work within scope A00067 · Igff:: phase 2A chairlift revisions RCP: CHW loop DP switches steam tunnel ventilation BMS fan coil unit strainer clean relocate return air sensor $68,492
Supplemental Agreement for work within scope A00066 · Reference no. R00069 WP293 RCP additional REA WP302 RCP condenser water pump install WP308 RCP: june 17 JCI start-up WP309 REA: end cap removal $137,786
Supplemental Agreement for work within scope A00065 · RCP support items REA actuator and tower sensors phase 2B jaces winterization of condenser water piping RCP resized condenser pump purchase $118,130
Supplemental Agreement for work within scope A00063 · Steam tunnel ventilation $250,994
Supplemental Agreement for work within scope A00064 · Multiple changes $124,478
Supplemental Agreement for work within scope A00062 · Bulletin 54R-RCP flow control metere $55,896
Supplemental Agreement for work within scope A00061 · All work associated with the renovation $102,880
Supplemental Agreement for work within scope A00060 · Extended field office overhead $79,130
Supplemental Agreement for work within scope A00059 · Multi changes $99,707
Supplemental Agreement for work within scope A00058 · Provide all labor, equipment and materials to perform the work described in STV-aecom bulletin 45: bulletin #45, as described herein, provides 15" high steel… $130,799
Supplemental Agreement for work within scope A00057 · RCP: condenser loop piping revisions $73,114
Supplemental Agreement for work within scope A00056 · Provide all labor, materials and equipment to install 233 pieces of 3/4" slate window sills in area D between the existing windows and the new blast roof… $96,760
Supplemental Agreement for work within scope A00055 · Based on the response to RFI-456, provide all labor, materials and equipment to switch out the installed 600 AMP electrical panel RDP1C in area C/D room C-106… $95,340
Supplemental Agreement for work within scope A00054 $121,306
Supplemental Agreement for work within scope A00053 · Closing statement in consideration of this modification, the parties hereby agree that the equitable adjustment is fair and reasonable and includes all labor,… $114,071
Supplemental Agreement for work within scope A00052 · Provide all labor, materials and equipment to supply and install additional waterproofing and appurtenances required for areas E, upper and lower roofs for area… $96,455
Supplemental Agreement for work within scope A00051 · Provide all labor, equipment and materials to install heat tracing for the cooling tower piping (condenser water supply, condenser water return, make-up… $88,562
Supplemental Agreement for work within scope A00050 · Due to impacts to the contractor's critical path from the multiplicity of differing site conditions changes, IT is considered warranted to extend the current… $99,596
Supplemental Agreement for work within scope A00049 · Provide all labor, equipment and material as described by STV-aecom bulletin 39. Bulletin #039, as described herein, addresses the provision of steel framing… $132,047
Supplemental Agreement for work within scope A00048 · Based on the response to RFI-423, provide all labor, equipment and materials in order to install an additional 2" thickness of polystyrene foam in the area D… $132,260
Supplemental Agreement for work within scope A00047 $129,329
Supplemental Agreement for work within scope A00046 · Provide all labor, equipment and materials to perform the work described in STV-aecom bulletin 41 bulletin 041, as described herein, addresses the added… $99,506
Supplemental Agreement for work within scope A00045 · A00045, R00046 scope of work WP180: provide misc support steel per RFI-284, 292, 293 and bulletin 28 WP185: mold removal area D from terracotta celing deck.… $130,438
Supplemental Agreement for work within scope A00044 · R00045: 1. WP158 relocate accelerator bulletins 36-36R2 based on bulletins #36-36R2, provide all labor, equipment and materials to relocate the linear… $132,502
Supplemental Agreement for work within scope A00043 · A00043, R0044 scope of work according to STV-URS bulletin #35R, provide all labor, equipment and materials to perform all work described herein: this bulletin… $439,606
Supplemental Agreement for work within scope A00042 · A00042 scope of work WP134 - the existing water main that feeds the science center runs along and against the north face of the existing wall at the BF line.… $165,064
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Quick answers

Who was awarded contract W912DS11C0023?

W912DS11C0023 was awarded to Walsh Construction Company II, LLC by ENDIST New York (US Army Corps of Engineers) on September 30, 2011.

How much is contract W912DS11C0023 worth?

The government has obligated $127,916,854 on W912DS11C0023.

Was contract W912DS11C0023 competed?

The extent of competition for W912DS11C0023 was full and open competition. The government received 12 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award