TAS:96 3134 511::recovery project #12329 green brook flood damages reduction project, s. Main ST., bound brook, NJ

Ended Definitive Contract Awarded Last action

Contract number
W912DS10C0005
Awardee
Awarding agency
Obligated
$4,555,568

Award facts

Contract value 123% obligated
$3,706,952.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Hillsborough Township, NJ 08844, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00006 · Sanitary sewer: created to capture field MOD. For funding purposes only (FED) $15,359
Change Order A00010 $0
Change Order A00006 · Construction - arra funded $0
Change Order A00010 $16,425
Change Order A00015 · Created to capture field MOD. For funding purposes only (FED $60,793
Change Order A00002 · Construction - arra funded $26,732
Exercise an Option A00011 · Created to capture field MOD. For funding purposes only (FED) $26,425
Change Order A00015 · Construction - arra funded $0
Change Order A00005 · Created to capture field MOD. For funding purposes only (FED) $0
Change Order A00003 · Construction - arra funded $20,658
Change Order A00012 · Created to capture field MOD. For funding purposes only (FED) $49,241
Change Order A00013 $0
Change Order A00012 · Construction - arra funded $0
Change Order A00014 · Created to capture field MOD. For funding purposes only (FED) $12,207
Change Order A00014 $0
Change Order A00009 · Construction - arra funded $0
Exercise an Option A00008 · Created to capture field MOD. For funding purposes only (FED) $126,576
Change Order A00005 $275,000
Change Order A00011 $0
Change Order A00001 $17,259
Change Order A00004 · Construction - arra funded $21,055
Change Order A00003 · Created to capture field MOD. For funding purposes only (FED) $0
Change Order A00008 · Construction - arra funded $0
Change Order A00013 · Created to capture field MOD. For funding purposes only (FED) $16,563
Change Order A00007 · Sanitary sewer: created to capture field MOD. For funding purposes only (FED) $39,228
Change Order A00016 $31,770
Change Order A00004 $0
Change Order A00001 · Created to capture field MOD. For funding purposes only (FED) $0
Change Order A00016 $0
Change Order A00007 · Construction - arra funded $0
Change Order A00009 $22,500
Change Order A00002 · Created to capture field MOD. For funding purposes only (FED) $0
Modification $3,346,248
Original award Green brook flood damage reuction project, s. Main ST., bound brook, NJ $431,529
Show all 34

About this award

This is a $3,706,952.00 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) New York District to Kyle Conti Construction LLC, a small disadvantaged business, for the Green Brook Flood Damages Reduction Project in Bound Brook, New Jersey. The contract is part of the USACE's recovery program and was set aside for small businesses. The work is to be completed by October 31, 2012.

Quick answers

Who was awarded contract W912DS10C0005?

W912DS10C0005 was awarded to Kyle Conti Construction LLC by ENDIST New York (US Army Corps of Engineers) on January 15, 2010.

How much is contract W912DS10C0005 worth?

The government has obligated $4,555,568 on W912DS10C0005. Its current value, with exercised options, is $3,706,952.

Was contract W912DS10C0005 competed?

The extent of competition for W912DS10C0005 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award