Renovation of nolan building phase 4 at fort belvoir, virginia

Active Definitive Contract Awarded Last action

Contract number
W912DR23C0015
Awardee
Awarding agency
Obligated
$106,379,526

Award facts

Opportunity
Contract value 98% obligated
$108,546,170.71 Current and potential, with all options
Completion date 86% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Fort Belvoir, VA 22060, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00029 $200,228
Supplemental Agreement for work within scope A00028 $264,228
Supplemental Agreement for work within scope A00027 $378,680
Supplemental Agreement for work within scope A00026 $110,234
Supplemental Agreement for work within scope P00007 $988,971
Supplemental Agreement for work within scope A00024 $349,686
Supplemental Agreement for work within scope A00022 $456,136
Supplemental Agreement for work within scope A00023 $311,408
Supplemental Agreement for work within scope A00021 · The construction of the complete renovation of the existing 235,000 SF nolan building (building 2444). $389,469
Supplemental Agreement for work within scope A00020 · Change CI revised L2 low roof top slab mix and reinforcement $35,318
Supplemental Agreement for work within scope A00019 · Change CF revised L1 top slab mix and reinf $362,929
Supplemental Agreement for work within scope A00018 · To incorporate changes CD and be into inscom phase 4 renovation, fort belvoir, VA $67,874
Supplemental Agreement for work within scope P00006 $575,668
Supplemental Agreement for work within scope P00005 · U.S. Army intelligence and security command nolan building construction $1,106,113
Supplemental Agreement for work within scope A00017 · To incorporate changes BA, BQ and CC into inscom phase 4 renovation, fort belvoir, VA $372,247
Supplemental Agreement for work within scope A00016 · To incorporate change BU (revised roof topping slab mix & reinforcement) into inscom phase 4 renovation, fort belvoir, VA $310,669
Supplemental Agreement for work within scope A00015 · To incorporate change CB (new duct openings in 1ST floor fan rooms) into inscom phase 4 renovation, fort belvoir, VA $151,543
Supplemental Agreement for work within scope A00014 · To incorporate change by into inscom phase 4 renovation, fort belvoir, VA $258,822
Change Order P00004 · Renovation of saof building $559,236
Supplemental Agreement for work within scope A00013 · To incorporate change BZ into inscom phase 4 renovation, fort belvoir, VA $499,343
Supplemental Agreement for work within scope A00012 · To incorporate changes AR, BG, BO and BT into inscom phase 4 renovation, fort belvoir, VA $180,756
Supplemental Agreement for work within scope A00011 · To incorporate changes AV, AW, AY, BD, BR, BV and BW into inscom phase 4 renovation, fort belvoir, VA $202,259
Change Order P00003 · Renovation of saof building $5,779,353
Supplemental Agreement for work within scope A00010 · To incorporate change an (elevator jacks replacement) into inscom phase 4 renovation, fort belvoir, VA $212,215
Supplemental Agreement for work within scope A00009 · To incorporate change as (replace grating support) into inscom phase 4 renovation, fort belvoir, VA $295,015
Other Administrative Action PK0001 · Executive order 14148 and 14173 $0
Supplemental Agreement for work within scope A00008 · To incorporate change am (alternate power to USB risers) into inscom phase 4 renovation, fort belvoir, VA $176,307
Supplemental Agreement for work within scope A00007 · To incorporate changes AO (central plant ETR intake louver damper), at (beulah street fencing changes), and AU (demo concrete platforms). $66,021
Supplemental Agreement for work within scope A00006 · To incorporate change BI (PH-04 chilled water shut off delay) into renovation of inscom phase 4, fort belvoir, VA $405,572
Supplemental Agreement for work within scope A00005 · To incorporate change AK (storm/sanitary/vent piping RE-routing) into renovation of inscom phase 4, fort belvoir, VA $241,369
Supplemental Agreement for work within scope A00004 · To incorporate change AP (L2 topping slab southeast elevation) into renovation of inscom phase 4, fort belvoir, VA $30,896
Supplemental Agreement for work within scope A00003 · To incorporate change AL into renovation of inscom phase IV, fort belvoir, VA $134,593
Supplemental Agreement for work within scope A00002 · To incorporate change AF into renovation of inscom phase IV, fort belvoir, VA $5,568
Supplemental Agreement for work within scope A00001 · To incorporate changes AA - ad & AG - AJ into renovation of inscom phase IV, fort belvoir, VA $292,801
Other Administrative Action P00002 · Renovation of nolan building at fort belvoir, VA. Notice to proceed modification. $0
Other Administrative Action P00001 · Renovation of saof nolan building phase 4 - modification to update accounting information on clins $0
Original award $90,608,000
Show all 37

About this award

ENDIST Baltimore (Defense Counterintelligence and Security Agency) awarded a $106.5 million definitive contract to Grunley Construction Co., Inc. for complete renovation of the 235,000 square-foot Nolan Building at Fort Belvoir, Virginia on September 29, 2023, under firm fixed-price terms with no set-aside.

The contract encompasses comprehensive repair and replacement of roofing, HVAC, electrical, plumbing, fire protection and alarm systems, ceilings, windows, doors, flooring, partitions, and finishes. The originating solicitation specified demonstration of experience constructing secure facilities per Intelligence Community standards, LEED Silver construction, and Building Information Modeling capability. Ultimate completion is scheduled for May 5, 2027.

Place of performance is Fort Belvoir, VA. Subcontractors on the project include D2 LLC for earthwork, Potomac Abatement LLC for CMU wall demolition and hazardous abatement, Aceco LLC for demolition, Pro-Air Inc. for mechanical and plumbing, Atlantic Refinishing & Restoration Inc. for masonry and stone restoration, and Roche Landscaping Services LLC for paving.

Subawards

Subcontractor Amount Awarded
D2 LLC RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA Earthwork $420,000
Potomac Abatement, LLC RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA CMU wall Demolition $291,975
Aceco, L.L.C. RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA Demolition $75,000
Roche Landscaping Services, LLC RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA Unit Paving $59,000
Atlantic Refinishing & Restoration, Inc. RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA Masonry, Stone, and Masonry, Stone, and Tile Restoration $1,500,000
Pro-Air, Inc. RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA Mechanical and Plumbing $18,300,000
Subcontractor not on record RENOVATION OF NOLAN BUILDING PHASE 4 AT FORT BELVOIR, VIRGINIA Acustic Treatment $77,484

Quick answers

Who was awarded contract W912DR23C0015?

W912DR23C0015 was awarded to Grunley Construction Co., Inc. by ENDIST Baltimore (US Army Corps of Engineers) on September 29, 2023.

How much is contract W912DR23C0015 worth?

The government has obligated $106,379,526 on W912DR23C0015. Its current value, with exercised options, is $108,546,171.

Was contract W912DR23C0015 competed?

The extent of competition for W912DR23C0015 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award