ECB4 design & construction

Ended Definitive Contract Awarded Last action

Contract number
W912DR22C0012
Awardee
Awarding agency
Obligated
$702,526,354

Award facts

Contract value 56% obligated
$1,252,339,478.52 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Meade, MD 20755, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00054 $214,438
Supplemental Agreement for work within scope A00053 $180,521
Supplemental Agreement for work within scope A00052 $491,758
Supplemental Agreement for work within scope A00051 $0
Supplemental Agreement for work within scope A00050 -$44,263
Supplemental Agreement for work within scope A00049 -$444,511
Supplemental Agreement for work within scope A00048 $18,190
Supplemental Agreement for work within scope A00047 · Contract for east campus building 4 (ECB4) project, at fort meade, maryland. Reference no. R00065 change AV - traffic and roadway changes, contract amount… $389,859
Funding Only Action P00020 $1,183,794
Change Order A00046 · CY, DA, DC $121,180
Change Order P00019 -$632,136
Change Order A00045 · Change DJ-1 $163,931
Supplemental Agreement for work within scope A00044 · Changes AR, CS, CV $38,327
Change Order P00018 -$1,119,000
Change Order P00017 $36,566
Funding Only Action P00016 $1,225,203
Supplemental Agreement for work within scope A00043 · Changes CU & CZ -$4,384
Change Order A00042 · Change CN $493,818
Change Order A00041 · MOD to cancel A00040 -$49,602
Supplemental Agreement for work within scope A00040 · Change BH $49,602
Supplemental Agreement for work within scope A00039 · Change CP delete ACS desk venona lobby -$44,717
Funding Only Action P00015 $1,692,120
Supplemental Agreement for work within scope A00038 · Change BJ PED storage lockers $42,481
Supplemental Agreement for work within scope A00037 · Change CQ OW separator discharge to storm drain $18,207
Supplemental Agreement for work within scope A00036 · Change CT HVAC repairs $15,054
Supplemental Agreement for work within scope A00035 · Change CH revise famis specifications $67,768
Change Order P00014 -$718,425
Funding Only Action P00013 $277,137,730
Supplemental Agreement for work within scope P00012 $1,424,207
Supplemental Agreement for work within scope A00034 · Change BU $0
Supplemental Agreement for work within scope A00033 · Change CB -$18,281
Supplemental Agreement for work within scope A00032 · Change BV -$90,050
Supplemental Agreement for work within scope A00031 · Changes AJ, AK, & BC $277,549
Supplemental Agreement for work within scope A00030 · Change CK $7,771
Supplemental Agreement for work within scope A00029 · Change CE $403,157
Supplemental Agreement for work within scope A00028 · Change CJ $52,993
Supplemental Agreement for work within scope A00026 · Change AO $223,451
Supplemental Agreement for work within scope A00027 · Change AQ $71,656
Supplemental Agreement for work within scope A00025 · Change CA -$16,651
Change Order P00011 · ECB4 design & construction - change AF $378,350
Supplemental Agreement for work within scope A00024 · Change BF $198,694
Supplemental Agreement for work within scope A00023 · Change an $195,541
Change Order P00010 $0
Supplemental Agreement for work within scope A00021 · Change by $273,792
Supplemental Agreement for work within scope A00022 · Change CG dispose of poly-chlorinated biphenyl waste from building .9827 $190,140
Supplemental Agreement for work within scope A00020 · Change BO $5,415
Supplemental Agreement for work within scope A00019 · Change BP -$22,346
Supplemental Agreement for work within scope A00017 · Change BH $6,326
Supplemental Agreement for work within scope A00018 · Change BM -$11,410
Supplemental Agreement for work within scope A00016 · Change BI -$20,132
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

ENDIST Baltimore awarded a $1.252 billion definitive contract to Balfour Beatty Construction, LLC for design and construction of East Campus Building 4 at Fort Meade, Maryland on May 1, 2022. The award uses firm fixed-price pricing with no set-aside. Ultimate completion is scheduled for May 18, 2026.

The originating solicitation, published as a special notice in October 2019, sought industry feedback on the potential use of a Project Labor Agreement for construction of a new operations facility at Fort George G. Meade with an estimated budget exceeding $25 million. Place of performance is Fort Meade, Maryland. The contract was subsequently amended to increase the contract amount by $214,438.00 with no calendar day time extension.

Quick answers

Who was awarded contract W912DR22C0012?

W912DR22C0012 was awarded to Balfour Beatty Construction, LLC by ENDIST Baltimore (US Army Corps of Engineers) on May 1, 2022.

How much is contract W912DR22C0012 worth?

The government has obligated $702,526,354 on W912DR22C0012. Its current value, with exercised options, is $1,252,339,479.

Was contract W912DR22C0012 competed?

The extent of competition for W912DR22C0012 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award