All costs in connection with the
Ended Definitive Contract Awarded Last action
- Contract number
- W912DR20C0033
- Awardee
-
CPP Construction Co UEI CRNSWVP4V9D6
- Awarding agency
-
ENDIST Baltimore
US Army Corps of Engineers, Department of Defense
- Obligated
- $10,227,608
Award facts
- Opportunity
-
- W912DR-20-B-0016 | Mcmillan Backwash Discharge to Sewer Pre-Solicitation · W912DR20B0016 · Posted May 8, 2020
- W912DR20B0016 | Mcmillan Backwash Discharge to Sewer Award Notice · Posted Aug 20, 2020
- W912DR20B0016 | Mcmillan Backwash Discharge to Sewer Solicitation · Posted May 22, 2020
- Contract value 100% obligated
- $10,227,608.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Marshall, VA 20116, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $51,694 | |
| Change Order | $49,439 | |
| Change Order | $8,221 | |
| Change Order | $2,215 | |
| Change Order | -$10,698 | |
| Change Order | $12,653 | |
| Change Order | $113,126 | |
| Change Order | $298,002 | |
| Change Order | $1,344 | |
| Change Order | $7,854 | |
| Change Order | $21,191 | |
| Change Order | $13,020 | |
| Change Order | $27,292 | |
| Change Order | $5,255 | |
| Exercise an Option | $180,000 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Original award | $9,447,000 |
Show all 18
About this award
This is a $10,227,608.00 firm-fixed-price construction contract awarded by the U.S. Army Corps of Engineers, Baltimore District (USACE) to CPP Construction Co. for the Mcmillan Backwash Discharge to Sewer project at the Washington Aqueduct in Washington, D.C. The contract was set aside for small businesses and involves the excavation and construction of concrete equalization basins and a pumping station, as well as the installation and testing of equipment to collect and control filter backwash water and the piping system to discharge it directly to the D.C. combined sewer system. The work includes the supply and installation of large pipes, valves, fittings, a chemical addition unit, submersible pumps, electrical switchgear, and flow measurement devices. This contract was awarded on August 17, 2020 and has a completion date of May 31, 2024.
Quick answers
Who was awarded contract W912DR20C0033?
W912DR20C0033 was awarded to CPP Construction Co by ENDIST Baltimore (US Army Corps of Engineers) on August 17, 2020.
How much is contract W912DR20C0033 worth?
The government has obligated $10,227,608 on W912DR20C0033.
Was contract W912DR20C0033 competed?
The extent of competition for W912DR20C0033 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award