Building 201, FT. Myers HVAC elec renovation

Ended Definitive Contract Awarded Last action

Contract number
W912DR19C0046
Awardee
Awarding agency
Obligated
$3,815,821

Award facts

Opportunity
  • W912DR19R0026 Solicitation number
Contract value 94% obligated
  • $3,792,077.00 Current, with exercised options
  • $4,060,695.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Fort Myer, Arlington, VA 22211, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00011 · To incorporate change AP - add manual pull station into contract 19C0046 building 201, FT. Myer $18,587
Supplemental Agreement for work within scope A00010 · Clin 0002 building 201, FT. Myer field change AI - REA subcontractor cost increase $23,744
Supplemental Agreement for work within scope A00009 · Clin 0002 building 201, FT. Myer field change AO - fire egress stairs redesign $91,091
Supplemental Agreement for work within scope A00008 · Clin 0002 building 201, FT. Myer field change an - REA - additional mold remediation $10,415
Supplemental Agreement for work within scope A00007 · Field change AL - exterior window repair $31,782
Supplemental Agreement for work within scope A00006 · Clin 0002 building 201, FT. Myer field change am - replace elevator disconnect switch $2,187
Supplemental Agreement for work within scope A00005 · Clin 0002 building 201, FT. Myer field change AG - defective water heater $8,810
Supplemental Agreement for work within scope A00004 · AC - life safety fire egress modification $268,237
Supplemental Agreement for work within scope A00003 · Field change ad - basement mold remediation $273,187
Supplemental Agreement for work within scope A00002 · Change AA - mobilization/contract completion delay $0
Supplemental Agreement for work within scope A00001 · Field change AB - 400 AMP to 600 AMP electric service $47,758
Other Administrative Action P00001 · Extend the period of performance end date to 16 january 2021. $0
Original award $3,040,022
Show all 13

About this award

This is a federal contract award to Huang's Inc., a minority-owned, woman-owned small business, for the Building 201 HVAC and Electrical Renovation project at Fort Myer in Arlington, Virginia. The $4,060,695 firm fixed price contract was awarded on September 23, 2019 by the U.S. Army Corps of Engineers (USACE) Baltimore District as an 8(a) sole source set-aside. The contract has an ultimate completion date of November 23, 2021 and provides for HVAC system and electrical renovations at the Fort Myer facility.

In addition to this contract, Huang's Inc. holds two significant indefinite delivery contracts with the U.S. Navy and the Department of Justice, respectively, for mechanical services and HVAC/UPS/generator maintenance. These contracts were also awarded under the 8(a) program and allow for the issuance of task orders for work at various government facilities.

Quick answers

Who was awarded contract W912DR19C0046?

W912DR19C0046 was awarded to Huang's Inc. by ENDIST Baltimore (US Army Corps of Engineers) on September 23, 2019.

How much is contract W912DR19C0046 worth?

The government has obligated $3,815,821 on W912DR19C0046. Its current value, with exercised options, is $3,792,077. Its potential value, with all options, is $4,060,695.

Was contract W912DR19C0046 competed?

The extent of competition for W912DR19C0046 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award