Building 216 renovation, fort myer, VA

Ended Definitive Contract Awarded Last action

Contract number
W912DR16C0035
Awardee
Awarding agency
Obligated
$4,491,821

Award facts

Opportunity
  • W912DR16R0049 Solicitation number
Contract value 100% obligated
$4,491,820.81 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Fort Myer, Arlington, VA 22211, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00007 · Building 216 renovation, fort myer, VA field change am - high moisture levels at basement floor $18,232
Supplemental Agreement for work within scope A00006 · Building 216 renovation, fort myer, VA - change AK HVAC 2 pipe to 4 pipe conversion. $304,901
Supplemental Agreement for work within scope A00005 · Building 216 renovation, fort myer, VA - change AL gas utility proximity to wet TAP $4,376
Supplemental Agreement for work within scope A00004 · Building 216 renovation, fort myer, VA - change AI bldg. 211-216 electrical feed - existing duct. $27,013
Supplemental Agreement for work within scope A00003 · Building 216 renovation, fort myer, VA - change AH sanitary sewer repair $45,118
Supplemental Agreement for work within scope A00002 · Contract for building 216 renovation, fort myer, VA, change AG, $0, 279 days for asbestos remediation $0
Change Order P00002 $41,670
Change Order A00001 · Jbmhh-myer building 216 design build renovation change AA removal of unforeseen asbestos containing materials unidentified within asbestos inspection survey… $293,074
Other Administrative Action P00001 $0
Original award $3,757,437

About this award

This is a $4,491,820.81 firm fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) to Summit Construction & Environmental Services LLC, a minority and veteran-owned small business, for the renovation of Building 216 at Fort Myer in Arlington, Virginia. The contract has an 8(a) sole source set-aside designation. Summit Construction also holds a General Services Administration (GSA) Multiple Award Schedule (MAS) contract to provide additional construction, environmental remediation, engineering, and related services to federal agencies up to a potential value of $3 million through April 2024.

Quick answers

Who was awarded contract W912DR16C0035?

W912DR16C0035 was awarded to Summit Construction & Environmental Services LLC by ENDIST Baltimore (US Army Corps of Engineers) on September 28, 2016.

How much is contract W912DR16C0035 worth?

The government has obligated $4,491,821 on W912DR16C0035.

Was contract W912DR16C0035 competed?

The extent of competition for W912DR16C0035 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award