Remote inspection facility base

Ended Definitive Contract Awarded Last action

Contract number
W912DQ23C7001
Awardee
Awarding agency
Obligated
$19,314,872

Award facts

Opportunity
Contract value 99% obligated
  • $19,371,381.66 Current, with exercised options
  • $19,581,240.48 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
St. Louis, MO 63104, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00021 · RIF/MOB sliding gate height adjustment $6,474
Supplemental Agreement for work within scope A00020 · IT fiber terminations $28,791
Supplemental Agreement for work within scope A00019 · Dryer vent, CO detectors and duct detector $54,943
Supplemental Agreement for work within scope A00018 · UPS lighting, canopy elec, gate pathway $164,066
Supplemental Agreement for work within scope A00017 · Painting descope and AVB conduit add $19,365
Change Order A00016 · ATS, ladder, power, and shelves $68,681
Supplemental Agreement for work within scope A00015 · Modification of elevator emergency phone & TV receptacle to contract for remote inspection facility at ST. Louis, missouri. $130,540
Other Administrative Action P00002 $0
Supplemental Agreement for work within scope A00014 · Modification for inspection canopy bent plate & backfill for remote inspection facility (RIF) contract, ST louis, MO $94,844
Change Order A00013 · Modification for canopy steel tie rods and turnbuckles to contract for remote inspection facility at ST. Louis, missouri. $49,185
Change Order A00012 · Modification of vehicle barrier controls and gate arms to contract for remote inspection facility at ST. Louis, missouri. $333,951
Change Order A00011 · Modification of grading around building sidewalk and DF1 to contract for remote inspection facility at ST. Louis, missouri. $11,892
Change Order A00010 · Modification of weather time extension JAN 25 - MAR 25 to contract for remote inspection facility at ST. Louis, missouri. $0
Supplemental Agreement for work within scope A00009 · Modification of electrical changes due to AVB loads, garbage disposal and HVU-1, and temp rock laying at MOB entrance to contract for remote inspection facility… $288,917
Change Order A00008 · Modification of sliding gate style and structural steel to contract for remote inspection facility at ST. Louis, missouri. $55,012
Change Order A00007 · Modification of drop arm, call box, RPM conduits, cetasm descope, and concrete pad to contract for remote inspection facility at ST. Louis, missouri. -$87,889
Supplemental Agreement for work within scope A00006 · Modification of decontamination tank piping and DF3 manhole break in and grading to contract for remote inspection facility at ST. Louis, missouri. $34,744
Supplemental Agreement for work within scope A00005 · Modification to ameren ductbank conflict with storm line and fire suppression at canopy descope of contract for remote inspection facility at ST. Louis,… $95,516
Supplemental Agreement for work within scope A00004 · Modification of gas meter configuration, sidewalk patrol road and curb ramp to contract for remote inspection facility at ST. Louis, missouri. $8,855
Change Order A00003 · Modification of equipment schedule voltage redesign, add reinforcement retaining wall footing to contract for remote inspection facility at ST. Louis, missouri. $57,311
Supplemental Agreement for work within scope A00002 · Modification of weather time extension JAN 24 - MAR 24 contract for remote inspection facility at ST. Louis, missouri. Reference no. R00003 0007 weather time… $0
Supplemental Agreement for work within scope A00001 · Modification of storm drain conflict, remove stop, LP contract for remote inspection facility at ST. Louis, MO REF. #R00002 0002 lightning protection & remove… $58,813
Exercise an Option P00001 · Exercise option clin 0002 $663,934
Original award $17,176,927
Show all 24

About this award

The Army Corps of Engineers Kansas City District awarded a $19.5 million definitive contract to Nisou LGC JV II LLC for design and construction of a Remote Inspection Facility base and modifications to a RIF/MOB sliding gate height adjustment on July 28, 2023, under a total small business set-aside.

Nisou LGC JV II LLC is a woman-owned small disadvantaged business and economically disadvantaged woman-owned small business. Place of performance is St. Louis, Missouri. The facility supports the National Geospatial-Intelligence Agency's West Facilities Modernization program and includes a mail processing center, K-9 training facility, covered inspection area, and secure areas with scanning and security systems to support inspection and screening of personnel, vehicles, and cargo. The contract is firm fixed price with an ultimate completion date of June 25, 2026.

Quick answers

Who was awarded contract W912DQ23C7001?

W912DQ23C7001 was awarded to Nisou LGC JV II LLC by ENDIST Kansas City (US Army Corps of Engineers) on July 28, 2023.

How much is contract W912DQ23C7001 worth?

The government has obligated $19,314,872 on W912DQ23C7001. Its current value, with exercised options, is $19,371,382. Its potential value, with all options, is $19,581,240.

Was contract W912DQ23C7001 competed?

The extent of competition for W912DQ23C7001 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award