Construction of levee unit R471-460

Ended Definitive Contract Awarded Last action

Contract number
W912DQ22C1027
Awardee
Awarding agency
Obligated
$16,579,361

Award facts

Opportunity
Contract value 100% obligated
$16,642,361.43 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Elwood, KS 66024, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00029 · Weather time extension JAN 26 - MAR 26 $0
Supplemental Agreement for work within scope A00028 -$63,000
Change Order A00027 · Additional stockpile atterberg testing $13,288
Supplemental Agreement for work within scope A00026 · Weather time extension OCT 25 - DEC 25 $0
Change Order A00025 · Modification for southern stockpiles delay impact to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $22,726
Supplemental Agreement for work within scope A00024 · Modification for magellan gas line/levee raise to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $137,728
Supplemental Agreement for work within scope A00023 · Modification for weather time extension APR 25 - SEP 25 for contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Supplemental Agreement for work within scope P00007 · Modification for SK027-2 equip adjustment contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $112,197
Supplemental Agreement for work within scope A00022 · Modification for stockpile testing and usage to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $202,397
Supplemental Agreement for work within scope P00006 · Executive order modification. $0
Change Order A00021 · Modification for weather time extension JAN 25 - MAR 25 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Other Administrative Action P00005 · Modification for admin funding correction to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Supplemental Agreement for work within scope A00020 · Modification for gates to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $1,940
Change Order P00004 · Modification for borrow area 9 rock discovery to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $719,786
Supplemental Agreement for work within scope A00019 · Modification for weather time extension OCT 24 - DEC 24 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $0
Supplemental Agreement for work within scope P00003 · Modification for RE-stripping to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $548,649
Change Order P00002 · Modification for borrow area 9 rock discovery to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas $0
Supplemental Agreement for work within scope A00018 · Modification for weather time extension JUL 24 - SEP 24 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Supplemental Agreement for work within scope A00017 · Modification for pervious fill rework STA 287-325 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $63,015
Supplemental Agreement for work within scope A00016 · Modification for 115+60 inline ductbill check valve to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $6,862
Supplemental Agreement for work within scope A00015 · Modification for SK013, SK018, SK019 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $194,358
Supplemental Agreement for work within scope A00014 · Modification for RIP RAP removal & topo survey treece RD contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $158,884
Supplemental Agreement for work within scope A00013 · Modification for weather time extension APR 24 - JUN 24 contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Supplemental Agreement for work within scope A00012 · Modification for rework STA 18+00/replace gate to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $21,451
Supplemental Agreement for work within scope A00011 · Modification for weather time extension JAN 24 - MAR 24 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Change Order A00010 · Modification for weather time extension OCT 23 - DEC 23 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Supplemental Agreement for work within scope A00009 · Modification to borrow area 1 final grade change for contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $114,932
Supplemental Agreement for work within scope A00005 · Modification for native seed changes & descope borrow 4 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $143,274
Supplemental Agreement for work within scope A00004 · Modification for weather time extension JUL 23 - SEP 23 to contract for R471-460 levee raise contract 4 (north of HWY 36) at doniphan county, kansas. $0
Change Order A00003 · Modification for weather time extension april - june 2023 to contract for R471-460 north levee raise at doniphan county, kansas and buchanan county, missouri. $0
Other Administrative Action P00001 · Incorporate mandatory bytedance clause far 52.204-27 $0
Change Order A00002 · Modification for weather time extension OCT 2022 - march 2023 to contract for missouri river levee system R471-460 north of highway 36 levee raise at elwood,… $0
Change Order A00001 · Modification for construction area signs to contract for R471-460 north levee raise at doniphan county, kansas and buchanan county, missouri. $2,371
Original award $14,178,505
Show all 34

About this award

The U.S. Army Corps of Engineers, Kansas City District, awarded a $16.6 million definitive contract to HB Construction Inc. for construction of Levee Unit R471-460 on September 22, 2022, under a total small business set-aside.

The contract covers raising and modifying existing levees, constructing seepage and stability berms, upgrading gatewell structures, extending and abandoning conduits, and adding manhole structures and pipes at the R471-460 Levee Unit in Doniphan County, Kansas (north of Highway 36). Place of performance is Elwood, Kansas. The contract is firm fixed price with an ultimate completion date of December 28, 2025. The originating pre-solicitation, posted April 27, 2022, estimated a performance period of 550 calendar days and anticipated a solicitation release within 30 days of the posting, with bids due approximately 30 days after solicitation release.

Quick answers

Who was awarded contract W912DQ22C1027?

W912DQ22C1027 was awarded to HB Construction Inc. by ENDIST Kansas City (US Army Corps of Engineers) on September 22, 2022.

How much is contract W912DQ22C1027 worth?

The government has obligated $16,579,361 on W912DQ22C1027. Its current value, with exercised options, is $16,642,361.

Was contract W912DQ22C1027 competed?

The extent of competition for W912DQ22C1027 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities