Supplemental Agreement for work within scope
A00069 · Modification for weather time extension JAN 26 - MAR 26 to contract for kansas citys, MO and KS, flood risk management project; argentine, armourdale and…
$0
Supplemental Agreement for work within scope
A00068
$473,060
Supplemental Agreement for work within scope
P00020 · Modification for arm clin 40 hpiles to contract for kansas citys, MO and KS, flood risk management project; argentine, armourdale and central industrial…
$1,234,958
Supplemental Agreement for work within scope
P00019 · Modification to descope full replacement of inland drive to contract for kansas citys, MO & KS, flood risk management project argentine, armourdale, and central…
-$2,716,241
Supplemental Agreement for work within scope
P00018 · Modification for ARG clin 39 hpiles to contract for kansas citys, MO & KS, flood risk management project argentine, armourdale and central industrial district…
$1,522,348
Supplemental Agreement for work within scope
A00065 · Modification for ARG RIP RAP STA 131+00 to contract for kansas citys, MO & KS, flood risk management project argentine, armourdale and central industrial…
$99,512
Supplemental Agreement for work within scope
A00064 · Modification for ARG & arm fence and hpile restrike to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
-$238,636
Supplemental Agreement for work within scope
A00063 · Modification for arm 12TH street PS fence, shawnee PS access ramps, and hpile restrike to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas…
$140,439
Supplemental Agreement for work within scope
A00062 · Modification for CID monolith ME5 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$142,935
Supplemental Agreement for work within scope
P00017 · Modification for CID monolith ME3 and ME4 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$876,542
Supplemental Agreement for work within scope
A00061 · Modification for ARG handrail for gatewells to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$53,274
Supplemental Agreement for work within scope
A00060 · Modification for CID hpiles M117 - M119 and M121 - M126 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$499,839
Supplemental Agreement for work within scope
A00059 · Modification for ARG widening levee STA 150+00 - 152+00 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$66,508
Supplemental Agreement for work within scope
A00058 · Modification for ARG concrete STA 63+00 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$76,676
Supplemental Agreement for work within scope
A00057 · Modification for ARG PS retaining wall to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$300,783
Supplemental Agreement for work within scope
A00056 · Modification for CID markone grate inlets to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$115,317
Supplemental Agreement for work within scope
P00016 · Modification for bnsf flagging pilaster to pilaster to contract for KCL arm/ARG/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$2,406,410
Supplemental Agreement for work within scope
A00055 · Modification for jump span mockup to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$100,000
Supplemental Agreement for work within scope
A00054 · Modification for ARG PS header pipe tie in to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$21,584
Supplemental Agreement for work within scope
A00053 · Modification for arm subsurface retaining wall STA 109+00 to contract for KCL ARG/arm CID levee/floodwall at kansas city, kansas and kansas city, missouri
$28,131
Supplemental Agreement for work within scope
A00052 · Modification for weather time extension JAN 24 - MAR 24 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$0
Supplemental Agreement for work within scope
A00051 · Modification for arm STA 282+00 redesign to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
-$209,121
Supplemental Agreement for work within scope
A00050 · Modification for CID bnsf pedestal and caisson to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$50,453
Supplemental Agreement for work within scope
A00047 · Modification for arm sawcut gatewell STA 75+40 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$80,612
Supplemental Agreement for work within scope
A00049 · Modification for ARG contaminated water relief well 42 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$34,448
Supplemental Agreement for work within scope
A00048 · Modification for arm unsuitable material STA. 246 to 252 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$111,056
Supplemental Agreement for work within scope
A00046 · Modification for tension pile plates, ARG buried collector, and arm piezometer STA 249 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas…
$21,147
Supplemental Agreement for work within scope
P00015 · Modification for rock island bridge abutment to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$553,938
Supplemental Agreement for work within scope
A00045 · Modification for weather time extension JUL 23 - SEP 23 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$0
Supplemental Agreement for work within scope
A00042 · Modification for railroad training to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$50,000
Supplemental Agreement for work within scope
A00044 · Modification for CID 36INCH pipe removal and CID update bnsf isometric to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city,…
$39,092
Supplemental Agreement for work within scope
A00043 · Modification for add work for stoplog demonstration to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$100,000
Funding Only Action
P00014 · Arm floodwall improvements final rate adjustment MOD for clin 0040 and 0043
$27,639
Supplemental Agreement for work within scope
A00041 · Modification for CID proof test holes to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$115,983
Supplemental Agreement for work within scope
A00040 · Modification for arm relief well bollards to contract for KCL ARG/arm/CID levee/floodwall at kansas city, missouri and kansas city, kansas.
$94,712
Supplemental Agreement for work within scope
A00039 · Modification for CID concrete slab and water utilities and CID brick box and pipe to contract for KCL ARG/arm/CID levees/floodwall at kansas city, missouri…
$79,613
Supplemental Agreement for work within scope
A00038 · Modification for additional hesco flood barriers for TFP to contract for KCL ARG/arm/CID levee/floodwall at kansas city, missouri and kansas city, kansas/
$258,285
Supplemental Agreement for work within scope
A00037 · Modification for arm BPU tower asbestos, arm UG trail, and arm CLM-0166 to contract for ARG/arm/CID levee/floodwall at kansas city, missouri and kansas city,…
$132,537
Supplemental Agreement for work within scope
A00036 · Modification for arm and ARG fence realignment to contract for ARG/arm/CID levee/floodwall at kansas city, MO and kansas city, KS
$89,337
Supplemental Agreement for work within scope
A00035 · Modification for arm-fiber-04 and erosion under EM5 footing to contract for ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri
$4,599
Supplemental Agreement for work within scope
A00034 · Modification for monofill 10 fence to contract for KCL ARG/arm/CID levee/floodwall at kansas city, missouri and kansas city, kansas.
$113,669
Supplemental Agreement for work within scope
A00033 · Modification for CID gatewell light pole to contract for KCL ARG/arm/CID levee/floodwall at kansas city, KS and kansas city, MO
$5,087
Supplemental Agreement for work within scope
P00013 · Modification for CID ARG bnsf flagger to contract for kansas citys, MO & KS, flood risk management project argentine, armourdale and central industrial district…
$1,561,086
Supplemental Agreement for work within scope
A00032 · Modification for unsuitable material and relief well subbase to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$80,950
Change Order
A00029 · Modification for weather time extension JAN 23 - MAR 23 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$0
Other Administrative Action
A00031 · Modification for partnering adjustments to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas and kansas city, missouri.
$0
Supplemental Agreement for work within scope
A00030 · Modification for arm SV055 and SV059 to contract for KCL ARG/arm/CID levee/floodwall at kansas city, kansas.
$32,336
Supplemental Agreement for work within scope
A00028 · Modification for ARG demo 152+60 to 157+6 to contract for kansas citys, MO & KS, flood risk management project argentine, armourdale and central industrial…
$7,781
Supplemental Agreement for work within scope
A00027 · Modification for arm caissons rebar to contract for kansas citys, MO & KS, flood risk management project argentine, armourdale and central industrial district…
$324,862
Exercise an Option
P00012 · Exercise BPU tower demo option
The U.S. Army Corps of Engineers Kansas City District awarded a $281.7 million definitive contract to The Lane Construction Corporation for levee and floodwall raises in Kansas City, Kansas and Kansas City, Missouri on May 17, 2021. This award reflects a modification extending the weather time extension period from January 26 through March 26, 2026, on the underlying Kansas City Flood Risk Management Project covering the Argentine, Armourdale, and Central Industrial District units.
The solicitation was issued as a two-step sealed bid for firm fixed-price construction work to raise approximately 90,000 feet of levee and floodwall an estimated four to five feet using various construction methods. No small business set-aside was applied. Place of performance is Kansas City, Kansas. Ultimate completion is August 25, 2026. NAICS code 237990 (other heavy and civil engineering construction) applies. Bidders were required to be SAM-registered and capable of bonding $300 million in construction work.
Quick answers
Who was awarded contract W912DQ21C1027?
W912DQ21C1027 was awarded to The Lane Construction Corporation by ENDIST Kansas City (US Army Corps of Engineers) on May 17, 2021.
How much is contract W912DQ21C1027 worth?
The government has obligated $279,043,870 on W912DQ21C1027. Its current value, with exercised options, is $279,618,021. Its potential value, with all options, is $281,746,021.
Was contract W912DQ21C1027 competed?
The extent of competition for W912DQ21C1027 was full and open competition. The government received 5 offers.