Design build construction of facilities fort leonard wood hospital replacement
Ended Definitive Contract Awarded Last action
- Contract number
- W912DQ19C4011
- Awardee
-
J.e. Dunn Construction Company UEI Y9FCAN97NHC9 Part of JE Dunn Construction Group Inc.
- Awarding agency
-
ENDIST Kansas City
US Army Corps of Engineers, Department of Defense
- Obligated
- $319,897,290
Award facts
- Opportunity
-
- Replacement hospital, fort leonard wood, missouri Solicitation · W912DQ18R4018 · Posted Oct 31, 2017
- Replacement hospital, fort leonard wood, missouri Award Notice · Posted Aug 9, 2019
- Contract value 100% obligated
- $320,265,263.88 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 4 offers Two Step
- Pricing
- Firm Fixed Price
- Place of performance
- FT LEONARD WD, MO 65473, USA
- Legislative mandates
-
- Service Contract Act FAR subpart 22.10
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | $295,957 | |
| Supplemental Agreement for work within scope | $218,378 | |
| Supplemental Agreement for work within scope | $199,854 | |
| Supplemental Agreement for work within scope | -$28,499 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $272,359 | |
| Supplemental Agreement for work within scope | $210,449 | |
| Supplemental Agreement for work within scope | $702,362 | |
| Funding Only Action | $4,201,618 | |
| Supplemental Agreement for work within scope | $129,264 | |
| Supplemental Agreement for work within scope | $381,820 | |
| Supplemental Agreement for work within scope | -$185,057 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $361,882 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $1,606,713 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $430,140 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $45,944 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$361,882 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $361,486 | |
| Supplemental Agreement for work within scope | $322,297 | |
| Supplemental Agreement for work within scope | $203,505 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$257,820 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $4,569 | |
| Supplemental Agreement for work within scope | -$186,033 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
The Department of Defense Engineering and Installation Directorate (ENDIST) Kansas City awarded a $320.3 million definitive contract to J.E. Dunn Construction Company for design-build construction of a hospital replacement facility at Fort Leonard Wood, Missouri on August 8, 2019, under a firm fixed-price arrangement with no set-aside. The ultimate completion date is July 13, 2026.
Place of performance is Fort Leonard Wood, Missouri. The originating solicitation, posted October 31, 2017, with a due date of June 8, 2018, called for design-build construction services including stormwater management and contaminated drinking water main modifications to support the consolidated hospital replacement project. The contract incorporates numerous subcontractors performing specialized trades: Bloomsdale Excavating Company (excavation, site preparation, utilities, and site concrete); E & K Of Kansas City (fireproofing, metal stud framing, drywall, and acoustical ceilings); Minnesota Elevator (elevator modernization); Meyer Electric (temporary traffic signals); Flooring Systems (resilient flooring, carpeting, ceramic and quarry tiling); Landesign LLC (landscaping and irrigation); Apex Environmental Consultants (asbestos sampling, abatement oversight, and air monitoring); Abbey-Simons Co (operable partitions); Cohen Architectural Woodworking (millwork and finish carpentry); Apco Graphics (signage); J & R Investments (final cleaning); and Turnkey Cleaner (rubber flooring preparation).
Subawards
| Subcontractor | Amount | Awarded |
|---|---|---|
| Turnkey Cleaner LLC | $49,500 | |
| Turnkey Cleaner LLC | $49,500 | |
| Subcontractor not on record | $1,646,110 | |
| J & R Investments Inc. | $240,692 | |
| Apco Graphics, Inc. | $352,957 | |
| Cohen Architectural Woodworking, LLC | $1,176,130 | |
| Abbey-Simons Co | $50,628 | |
| JE Dunn Construction Group Inc. | $464,005 | |
| Flooring Systems Inc. | $4,120,271 | |
| Landesign LLC | $1,648,479 | |
| Apex Environmental Consultants Inc. | $90,251 | |
| Apex Environmental Consultants Inc. | $90,251 | |
| Minnesota Elevator Inc. | $2,054,814 | |
| Minnesota Elevator Inc. | $2,054,814 | |
| Meyer Electric Company, Inc. | $79,020 | |
| Bloomsdale Excavating Company, Incorporated | $9,902,561 | |
| E & K Of Kansas City, Inc. | $17,355,799 |
Show all 17
Quick answers
Who was awarded contract W912DQ19C4011?
W912DQ19C4011 was awarded to J.e. Dunn Construction Company by ENDIST Kansas City (US Army Corps of Engineers) on August 8, 2019.
How much is contract W912DQ19C4011 worth?
The government has obligated $319,897,290 on W912DQ19C4011. Its current value, with exercised options, is $320,265,264.
Was contract W912DQ19C4011 competed?
The extent of competition for W912DQ19C4011 was full and open competition. The government received 4 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award