Construction of a water treatment plant at lake city army ammunition plant.

Ended Definitive Contract Awarded Last action

Contract number
W912DQ19C4002
Awardee
Awarding agency
Obligated
$35,226,158

Award facts

Opportunity
Contract value 100% obligated
$35,226,158.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Independence, MO 64056, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00019 · Modification for REA settlement associated with bolt isolation in painting clarifiers SB1 and SB2 for the lake city army ammunition plant water treatment plant. $15,000
Supplemental Agreement for work within scope A00018 · Modification for WTP replace clarifier mixing sys/add vfds to contract for lcaap - water treatment plant at lake city army ammunition plant, independence,… $169,300
Change Order P00004 · Modification for WTP add degassing valves/flush taps to contract for lcaap - water treatment plant at lake city army ammunition plant, independence, missouri $7,822
Change Order A00017 · Modification for misc. Piping revisions/remove letters to contract for lcaap - water treatment plant at lake city army ammunition plant, independence, missouri $14,436
Change Order P00003 · Modification to remove heavy highway wage rates $0
Supplemental Agreement for work within scope A00015 · Modification for add air release valves add heat trace & insulation add 4 butterfly isolation valves relocate turbidity meter TAP and, NG support to contract… -$32,438
Supplemental Agreement for work within scope A00016 · Modification for add in-line sample pump and add booster pump to contract for lcaap water treatment plant at lake city army ammunition plant, independence, MO. $43,518
Supplemental Agreement for work within scope A00014 · Modification for add 2 bollards and replace PIV with valve box to contract for lcaap - water treatment plant, independence, missouri $7,953
Supplemental Agreement for work within scope A00013 · Modification for WTP add 8" gate isolation valve to contract for contract for lcaap water treatment plant at lake city army ammunition plant, independence, MO. $8,269
Change Order A00012 · Modification for delays caused by adverse weather in excess of anticipated to contract for lcaap water treatment plant at lake city army ammunition plant,… $0
Supplemental Agreement for work within scope A00011 · Modification for control system cyber security to contract for water treatment plant at lake city army ammunition plant, independence, MO. $326,142
Change Order A00010 · Modification for additional spare parts to contract for lcaap water treatment plant at lake city army ammunition plant, independence, MO. $377,154
Supplemental Agreement for work within scope A00009 · Modification for WTP relocate 6" SBD line to contract for lcaap water treatment plant at lake city army ammunition plant, independence, MO. $2,729
Other Administrative Action P00002 · Adding required fars and dfars clauses 52.204-25 and 252.204-7018. $0
Supplemental Agreement for work within scope A00008 · Modification for WTP install future lime pump conduits to contract for lcaap water treatment plant at lake city army ammunition plant, independence, MO. $1,595
Change Order A00007 · Modification for WTP revise 18" RBI & SBI line elevations and, WTP REA remove concrete slab to contract for lcaap water treatment plant at lake city army… $74,334
Change Order A00006 · Modification for delays caused by adverse weather in excess of anticipated to contract for lcaap water treatment plant at lake city army ammunition plant,… $0
Change Order A00005 · Modification add pump station & catch basin to contract for lcaap water treatment plant at lake city army ammunition plant, independence, MO. $77,944
Change Order A00004 · Modification for delays caused by adverse weather in excess of anticipated contract for contract for lcaap water treatment plant at lake city army ammunition… $0
Change Order A00003 · Modification for WTP REA hydrated lime feed equipment to contract for lcaap - water treatment plant at lake city army ammunition plant, independence, MO $210,000
Supplemental Agreement for work within scope A00002 · MOD for GW test/disposal, reroute non-potable water pipe, roof scupper dimensions & elevations, wall pipes & cleanout, PRV for eye wash stations and pothole for… $22,400
Supplemental Agreement for work within scope A00001 · Modification for delays caused by adverse weather in excess of anticipated to contract for lcaap water treatment plant at lake city army ammunition plant,… $0
Other Administrative Action P00001 $0
Original award $33,900,000
Show all 24

About this award

This is a $35,226,158.00 firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers' Kansas City District to Goodwin Bros. Construction Company for the construction of a water treatment plant at the Lake City Army Ammunition Plant in Sugar Creek, Missouri. The contract has an ultimate completion date of September 5, 2022 and was awarded on February 7, 2019. The contract does not have a set-aside designation.

Quick answers

Who was awarded contract W912DQ19C4002?

W912DQ19C4002 was awarded to Goodwin Bros. Construction CO. by ENDIST Kansas City (US Army Corps of Engineers) on February 7, 2019.

How much is contract W912DQ19C4002 worth?

The government has obligated $35,226,158 on W912DQ19C4002.

Was contract W912DQ19C4002 competed?

The extent of competition for W912DQ19C4002 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award