South topeka floodwall modification

Ended Definitive Contract Awarded Last action

Contract number
W912DQ18C1013
Awardee
Awarding agency
Obligated
$13,042,644

Award facts

Opportunity
Contract value 100% obligated
$13,042,644.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
US Army Corps of Engineers Department of the Army, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Topeka, KS 66601, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00005 · Deobligation of funds at subclin 00202 due to accepted but deficient work - south topeka floodwall modification -$6,650
Change Order A00035 · Modification for descope waterworks wall infill to contract for south topeka wall modification at topeka, KS. -$24,195
Change Order A00034 · Modification for misc changes to contract for south topeka wall modification at topeka, KS. -$58,715
Change Order A00033 · Modification for delays in contract performance due to unforeseen weather conditions, namely, unusually severe weather and ground conditions to contract for… $0
Supplemental Agreement for work within scope A00032 · Modification for erosion rock and seeding changes to contract for south topeka wall modification at topeka, KS $20,000
Change Order A00031 · Modification for south berm road stabilization to contract for south topeka wall modification at topeka, KS. $46,954
Supplemental Agreement for work within scope A00028 · Modification for madison PH stairs and mitigation changes to contract for south topeka wall modification at topeka, KS. $35,141
Change Order A00027 · Modification for timber piles #4 to contract for south topeka wall modification at topeka, KS. $22,726
Supplemental Agreement for work within scope A00026 · Modification for M45/M44 protrusion pile cap rebar splice and, timber piles #3 to contract for south topeka wall modification at topeka, KS. $66,659
Supplemental Agreement for work within scope A00025 · Modification for existing foundation at w-28 DE-scope mockup SB pipe flared end and, well conflict P122 to contract for south topeka wall modification at… $20,540
Supplemental Agreement for work within scope A00024 · Modification for hayes demob/remob to contract for south topeka wall modification at topeka, KS. $27,763
Change Order A00023 · Modification for high river delay to contract for south topeka wall modification at topeka, KS. $62,885
Change Order A00022 · Modification for drilled shafts gage criteria to contract for south topeka wall modification at topeka, KS. $0
Change Order A00021 · Modification for high river may-july 2019 delay and associated costs to contract for south topeka wall modification at topeka, KS. $190,901
Change Order A00020 · Modification for SB access road alignment to contract for south topeka wall modification at topeka, KS. $1,007
Change Order A00019 · Modification for remove timber piles-middle section to contract for south topeka wall modification at topeka, KS. $22,613
Change Order A00018 · Modification for delays in contract performance due to unforeseen weather conditions to contract for south topeka wall modification at topeka, KS. $0
Change Order A00017 · Modification for SB access road culvert to contract for south topeka wall modification at topeka, KS. $3,593
Change Order A00016 · Modification for hayes work at P231 to contract for south topeka wall modification at topeka, KS. $17,348
Change Order A00015 · Modification for P231 exploratory excavation and backfill to contract for south topeka wall modification at topeka, KS $1,998
Change Order A00014 · Modification for drilled shaft plumbness test to contract for contract for south topeka wall modification at topeka, KS. $83,630
Change Order A00013 · Modification for additional disposal of contaminated soil to contract for south topeka wall modification at topeka, KS. $244,314
Supplemental Agreement for work within scope P00004 $218,173
Change Order A00012 · Modification for P258 drill through w-24; well conflicts P208, P217, P250, P275; and, well conflicts P088 & P105 to contract for south topeka wall… $249,424
Change Order A00010 · Modification for differing site condition reference 1908 foundation coring to contract for south topeka wall modification at topeka, KS. $36,990
Change Order A00009 · Modification for sequestered slurry to contract for south topeka wall modification at topeka, KS. $5,090
Change Order A00008 · Modification for 15" abandoned sanitary line to contract for south topeka wall modification at topeka, KS. $4,448
Change Order A00007 · Modification for barry ICE sidewalk to contract for south topeka wall modification at topeka, KS. $4,391
Change Order A00006 · Modification for drilled shaft mockup to contract for south topeka wall modification at topeka, KS. $1,797
Exercise an Option P00003 · Exercise option clin 0005 and 0006. $509,465
Change Order A00005 · Modification for revisions for manhole w-29 to contract for south topeka wall modification at topeka, KS. $5,656
Change Order A00004 · Modification for ntop abandon MH VCP to contract for south topeka wall modification at topeka, KS. $5,365
Other Administrative Action P00002 · Correction to clause 217-7 south topeka floodwall modification $0
Change Order A00003 · Modification for hill's security fencing to contract for south topeka wall modification at topeka, KS. $21,014
Change Order A00002 · Modification for creosote construction investigation to contract for south topeka wall modification at topeka, KS. $193,502
Change Order A00001 · Modification for raise inlet to storm drain to contract for south topeka wall modification at topeka, KS. $2,759
Other Administrative Action P00001 · South topeka floodwall modification to not include amendments in actual award document. $0
Original award $11,006,058
Show all 38

About this award

This is a $13,042,644.00 firm fixed price definitive contract awarded by the U.S. Army Corps of Engineers to the Frontier-Arrowhead JVA, a veteran-owned, self-certified HUBZone joint venture company. The contract is for the SOUTH TOPEKA FLOODWALL MODIFICATION project, with a completion date of June 30, 2021. The contract does not have a set-aside designation. This contract supports the U.S. Army Corps of Engineers' efforts to maintain and improve flood control infrastructure.

Quick answers

Who was awarded contract W912DQ18C1013?

W912DQ18C1013 was awarded to Frontier-Arrowhead JVA by ENDIST Kansas City (US Army Corps of Engineers) on February 1, 2018.

How much is contract W912DQ18C1013 worth?

The government has obligated $13,042,644 on W912DQ18C1013.

Which agency awarded contract W912DQ18C1013?

ENDIST Kansas City (US Army Corps of Engineers) awarded W912DQ18C1013, with funding from US Army Corps of Engineers (Department of the Army).

Was contract W912DQ18C1013 competed?

The extent of competition for W912DQ18C1013 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award