Historical building renovation located at FT. Leavenworth, kansas.

Ended Definitive Contract Awarded Last action

Contract number
W912DQ14C4026
Awardee
Awarding agency
Obligated
$25,374,203

Award facts

Opportunity
Contract value 63% obligated
  • $25,374,202.82 Current, with exercised options
  • $40,192,002.82 Potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1AA Construction Of Office Buildings
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 8 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Fort Leavenworth, KS, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00015 · Modification for settlement of reas to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $0
Supplemental Agreement for work within scope A00014 · Modification for B468-B487 REA-018 link bldg unsuit soil to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $1,463
Supplemental Agreement for work within scope A00013 · Modification for replace basement floor drain to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $5,860
Supplemental Agreement for work within scope A00012 · Modification for blast windows-paint color; and, repair fire sprinkler riser to contract for multiple building repairs, fort leavenworth, KS at fort… $9,605
Supplemental Agreement for work within scope A00011 · Modification for building 468 and building 487 replace storm drain and sewer line obstructions to contract for multiple building repairs, fort leavenworth, KS… $30,782
Supplemental Agreement for work within scope A00010 · Modification for swing space closure to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. -$83,298
Supplemental Agreement for work within scope A00009 · Modification for tunnel credit; link-concrete obstruction; credit for foundation underpinning; link- 2ND concrete obstruction; expose floor concrete; and,… -$37,952
Change Order A00008 · Modification for weather time extension for delays caused by adverse weather in excess of anticipated for contract for multiple building repairs, fort… $0
Change Order A00007 · Modification for building 468/487 AV/IT change to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $0
Supplemental Agreement for work within scope A00006 · Modification for cupola repair to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $18,591
Supplemental Agreement for work within scope A00005 · Change for B196 door and frame replacement for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $8,172
Supplemental Agreement for work within scope A00004 · Modification for alarmed carrier credit; roof credit; and, dock repair to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth,… $6,825
Supplemental Agreement for work within scope A00003 · Modification for building 196 to replace 2ND floor fire escape door to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $5,105
Change Order A00002 · Modification for building 196 eifs north basement entryway to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $4,289
Supplemental Agreement for work within scope A00001 · Modification to add tile to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $32,541
Change Order P00050 · Modification for building 245 loading dock repair to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $11,277
Change Order P00049 · Modification for double-wall insulated duct to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $25,616
Supplemental Agreement for work within scope P00048 · Modification for swing space - site clean-up/closure; additional structural repairs-floors; and, porch and ceiling repairs to contract for multiple building… $67,077
Supplemental Agreement for work within scope P00047 · Modification building 468-building 487 changes to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $58,358
Supplemental Agreement for work within scope P00046 · Modification for building 53 space usage changes including doors and sipr drops to contract for multiple building repairs, fort leavenworth, KS at fort… $58,754
Supplemental Agreement for work within scope P00045 · Modification for building 468 foundation stabilization and unforeseen voids-sinkhole/tunnel to contract for multiple building repairs, fort leavenworth, KS at… $429,828
Supplemental Agreement for work within scope P00044 · Modification for exterior stairwell drainage to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $9,424
Supplemental Agreement for work within scope P00042 · Modification for building 196 mold survey and removal to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $2,754
Supplemental Agreement for work within scope P00043 · Modification for B468-487 user requested add-ONS; and, B468-B487 final user requested changes to contract for multiple building repairs, fort leavenworth, KS at… $57,397
Supplemental Agreement for work within scope P00041 · Modification for gas line curb stop value for the contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $4,533
Supplemental Agreement for work within scope P00040 · Modification for basement floor finish; and, interior door locks to contract for multiple building repairs, fort leavenworth, KS $5,070
Supplemental Agreement for work within scope P00039 · Modification for building 487 asbestos removal to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $1,867
Supplemental Agreement for work within scope P00038 · Modification for building 196 mold removal to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $10,932
Supplemental Agreement for work within scope P00037 · Modification to building 468 foundation stabilization to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $166,957
Supplemental Agreement for work within scope P00036 · Modification for building 468 unforeseen voids-sinkhole/tunnel to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $168,121
Supplemental Agreement for work within scope P00035 · Modification for unforeseen voids-sinkhole/tunnel to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $53,036
Supplemental Agreement for work within scope P00034 · Modification for mold removal to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $3,820
Supplemental Agreement for work within scope P00033 · Modification for multiple design changes; addl TV-data-electrical connections; and, energy monitoring - recirculation pump to contract for multiple building… $100,525
Supplemental Agreement for work within scope P00032 · Modification for building 53 arms vault walls; beam replacement - unforeseen; and, mold remediation to contract for multiple building repairs, fort leavenworth,… $60,356
Supplemental Agreement for work within scope P00031 · Modification for building 245 main distribution panel replacement to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $42,825
Supplemental Agreement for work within scope P00030 · Modification for buildings 468-487 change to FF & e layout & specs to contract for $30,264
Supplemental Agreement for work within scope P00029 · Modification for building 487 additional structural repairs under dock slab to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth,… $3,626
Supplemental Agreement for work within scope P00028 · Modification for building 245 asbestos abatement-NW cooler door; and, building 245 truss removal-unforeseen structure to contract for multiple building repairs,… $15,031
Supplemental Agreement for work within scope P00027 · Modification for swing space unforeseen site conditions to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $125,755
Supplemental Agreement for work within scope P00026 · Modification for B468-487 OSP comm cable 50PR to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $7,037
Supplemental Agreement for work within scope P00025 · Modification for building 53 lead repair & abatement to contract for multiple building repairs, fort leavenworth, KS at fort leavenworth, kansas. $9,362
Supplemental Agreement for work within scope P00024 · Modification for B53 additional structural repairs to contract for multiple building repairs, fort leavenworth, KS $40,400
Supplemental Agreement for work within scope P00023 · Modification for building 53 access control credit/locks to contract for multiple building repairs, fort leavenworth, KS $15,988
Supplemental Agreement for work within scope P00022 · Modification for building 245 ADA ramp to contract for multiple building repairs, fort leavenworth, KS $79,597
Supplemental Agreement for work within scope P00021 · Modification for building 53 additional structural repairs to contract for multiple building repairs, fort leavenworth, KS $64,984
Supplemental Agreement for work within scope P00020 · Modification for building 196 structural repairs to contract for multiple building repairs, fort leavenworth, KS $362,788
Supplemental Agreement for work within scope P00019 · Modification for additional sipr requirements; copper requirements; and, building 245 structural repairs to contract for multiple building repairs, fort… $34,035
Supplemental Agreement for work within scope P00018 · Modification for building 53 structural repairs to contract for multiple building repairs, fort leavenworth, KS $18,963
Supplemental Agreement for work within scope P00017 · Modification for building 53 lead repair & abatement to contract for multiple building repairs, fort leavenworth, KS $8,840
Supplemental Agreement for work within scope P00016 · Modification for building 226 structural repairs to contract for multiple building repairs, fort leavenworth, KS. $62,896
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Quick answers

Who was awarded contract W912DQ14C4026?

W912DQ14C4026 was awarded to Orocon - Carothers JV2 by ENDIST Kansas City (US Army Corps of Engineers) on September 29, 2014.

How much is contract W912DQ14C4026 worth?

The government has obligated $25,374,203 on W912DQ14C4026. Its potential value, with all options, is $40,192,003.

Was contract W912DQ14C4026 competed?

The extent of competition for W912DQ14C4026 was full and open competition after exclusion of sources. The government received 8 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award