Project requires demolition tenkiller bridge in sequoyah county, design/construction of temporary electrical and safety walkways, construction of a new bridge, new electrical/catwalks/water lines, and…

Active Definitive Contract Awarded Last action

Contract number
W912BV25C0012
Awardee
Awarding agency
Obligated
$32,496,109

Award facts

Opportunity
Contract value 88% obligated
$36,957,075.21 Current and potential, with all options
Completion date 70% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Vian, OK 74962, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00002 -$273,324
Other Administrative Action P00003 $0
Supplemental Agreement for work within scope P00002 $2,890,964
Supplemental Agreement for work within scope P00001 · Part 1 of this modification will allow the contractor to procure the wire ropes and begin offsite fabrication of this required feature. $1,182,827
Other Administrative Action A00001 · Meet the requirements listed in the solicitation. $0
Original award $28,695,642

About this award

ENDIST Tulsa, a Defense organization, awarded a $36.7 million firm-fixed-price definitive contract to Kiewit Infrastructure South Co on June 2, 2025, for demolition and replacement of the Tenkiller Dam spillway bridge. Part 1 of the action authorizes the contractor to procure wire rope and begin offsite fabrication of a required feature. The contract carries no set-aside and ceiling value is $36,707,075.21.

Scope covers demolition of the existing bridge, design and construction of temporary electrical and safety walkways, construction of a new bridge, new electrical, catwalk, and water line systems, and full site restoration. Place of performance is Vian, Oklahoma.

The originating opportunity, issued by the U.S. Army Corps of Engineers, Tulsa District, was an unrestricted pre-solicitation posted September 24, 2024, under NAICS 237310. Offerors were required to be registered in SAM.gov, and proposals were evaluated on a best value basis considering specialized experience, technical approach, key personnel, past performance, contract schedule, price reasonableness, and price realism. The solicitation estimated construction magnitude at $25 million to $100 million and required performance and payment bonds.

Ultimate completion is July 22, 2027. The contractor must commence work within 10 days of Notice to Proceed and complete the work within 600 calendar days.

Description

Project requires demolition tenkiller bridge in sequoyah county, design/construction of temporary electrical and safety walkways, construction of a new bridge, new electrical/catwalks/water lines, and full site restoration.

Quick answers

Who was awarded contract W912BV25C0012?

W912BV25C0012 was awarded to Kiewit Infrastructure South Co by ENDIST Tulsa (US Army Corps of Engineers) on May 14, 2025.

How much is contract W912BV25C0012 worth?

The government has obligated $32,496,109 on W912BV25C0012. Its current value, with exercised options, is $36,957,075.

Was contract W912BV25C0012 competed?

The extent of competition for W912BV25C0012 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award