Rehabilitate hulah tainter gates and seals, copan, OK.

Ended Definitive Contract Awarded Last action

Contract number
W912BV16C0051
Awardee
Awarding agency
Obligated
$4,931,061

Award facts

Opportunity
Contract value 91% obligated
  • $4,931,060.61 Current, with exercised options
  • $5,412,560.61 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Copan, OK 74022, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00008 · The contractor is required to apply a smoothable paint surface to weld fractures and pitting at the trunnion support and torque bracket. An approved product for… $2,349
Supplemental Agreement for work within scope A00007 · Extend the duration of the temporary traffic control system that is being utilized at copan DAM for an additional two weeks. $5,632
Supplemental Agreement for work within scope A00006 · Extension of the temporary traffic control setup at copan DAM by 4 weeks. $11,264
Supplemental Agreement for work within scope A00005 · Weather time extension july 2017 - march 2018 $0
Supplemental Agreement for work within scope A00004 · Award of tainter gate 6 $481,500
Supplemental Agreement for work within scope A00003 · Torque bracket repair $27,466
Additional Work (new agreement, FAR part 6 applies) A00002 · Copan temporary traffic control $69,350
Other Administrative Action P00003 · Correct funding LOA for gate 3 under subclin 0001-07. $0
Other Administrative Action A00001 · Weather time extension $0
Other Administrative Action P00002 · Hulah service gates, hulah lake oklahoma; MOD to remove GFP clause. $0
Exercise an Option P00001 · Exercise options 3 & 4 $963,000
Original award $3,370,500
Show all 12

About this award

This is a $5,412,560.61 firm fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) Tulsa District to Blastco, Inc. to rehabilitate the Hulah Tainter gates and seals in Copan, Oklahoma. The contract was set aside for small businesses and has an ultimate completion date of October 23, 2018. The work includes disconnecting and securing the tainter gate chain assemblies, repairing welds, blasting and painting the tainter gates and side seal assemblies, and final cleanup and debris removal. This contract was awarded under a larger USACE construction project, as indicated by the federal contract opportunity details provided.

Quick answers

Who was awarded contract W912BV16C0051?

W912BV16C0051 was awarded to Blastco, Inc. by ENDIST Tulsa (US Army Corps of Engineers) on September 30, 2016.

How much is contract W912BV16C0051 worth?

The government has obligated $4,931,061 on W912BV16C0051. Its potential value, with all options, is $5,412,561.

Was contract W912BV16C0051 competed?

The extent of competition for W912BV16C0051 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award