Webber falls rehabilitation

Ended Definitive Contract Awarded Last action

Contract number
W912BV09C1017
Awardee
Awarding agency
Obligated
$3,733,308

Award facts

Opportunity
Contract value 108% obligated
$3,464,192.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Webbers Falls, OK, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00005 · Supplemental $0
Other Administrative Action P00005 · Arra - wfalls L & D $0
Change Order P00004 · Arra::yes::arra recoveryproject#::xxxxxxx::RP# webbers falls gantry crane rehab. Change storm brake and add spare parts. -$7,535
Change Order P00004 · Arra - wfalls L & D MOD was done under arra funding. $0
Other Administrative Action P00001 · Arra::yes::arra recoveryproject#19590::RP# webbers falls lock & DAM, OK. Rehabilitate gantry crane, webbers fall powerhouse, OK. -$276,651
Other Administrative Action P00001 · Webbers falls lock & DAM, OK. Rehabilitate gantry crane, webbers fall powerhouse, OK. $276,651
Other Administrative Action P00003 · Field modifcation for P00003 went on other car with arra funds. Modifcation for intake crane, leg weld repair. $0
Other Administrative Action P00003 · Recoveryproject#19590:RP# webbers falls lock & DAM, OK. Rehabilitate gantry crane webbers falls powerhouse, oklahoma modification for repairs to the intake… $99,700
Other Administrative Action P00002 · Webber falls gantry crane rehab, webbers falls lake, oklahoma $0
Other Administrative Action P00002 · Arra::yes::arra recoveryproject#19590:RP# webbers falls lock & DAM, OK. Rehabilitate gantry crane webbers falls powerhouse, oklahoma modification to paint… $145,000
Modification Recoveryproject#19590:RP# webbers falls lock & DAM, OK. Rehabilitate gantry crane webbers falls powerhouse, oklahoma $3,496,143
Original award $0
Show all 12

About this award

This is a $3,464,192.00 firm fixed price contract awarded by the U.S. Army Corps of Engineers to Prairie Breeze, LTD., an 8(a) sole source small disadvantaged business. The contract is for the rehabilitation of the Webbers Falls project located in Webbers Falls, Oklahoma. The award date was July 30, 2009, and the ultimate completion date is March 31, 2011. This contract is for the U.S. Army Corps of Engineers' civil works program.

Quick answers

Who was awarded contract W912BV09C1017?

W912BV09C1017 was awarded to Prairie Breeze, LTD. by ENDIST Tulsa (US Army Corps of Engineers) on July 30, 2009.

How much is contract W912BV09C1017 worth?

The government has obligated $3,733,308 on W912BV09C1017. Its current value, with exercised options, is $3,464,192.

Was contract W912BV09C1017 competed?

The extent of competition for W912BV09C1017 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award