TAS::96 3135TAS recoveryproject#::140568::RP# rehab tainter gates at FT gibson and john redmond arra

Ended Definitive Contract Awarded Last action

Contract number
W912BV09C1013
Awardee
Awarding agency
Obligated
$15,388,955

Award facts

Contract value 662% obligated
$2,325,985.87 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Burlington, KS 66839, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action A00001 · FT gibson tainter gatesnon-arra $0
Other Administrative Action A00001 $0
Change Order P00028 · FT gibson tainter gates-arra $65,317
Change Order P00028 · FT gibson tainter gatesnon-arra $0
Change Order P00027 · FT gibson tainter gates-arra -$39,989
Change Order P00027 $0
Other Administrative Action P00025 $0
Other Administrative Action P00026 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00026 $0
Other Administrative Action P00025 $0
Other Administrative Action P00023 $0
Other Administrative Action P00024 · FT gibson tainter gates-arra $0
Other Administrative Action P00024 $0
Other Administrative Action P00023 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00022 · Brace repairs to gates 13 to 30 MOD#22 $0
Other Administrative Action P00021 · FG gate web repairs on bottom girder MOD#21 paid with arra funds $0
Other Administrative Action P00021 · Arra::yes::arra recoveryproject#::141742::RP# FT gibson and john redmond T-gate rehab FG gate web repairs on bottom grider MOD#21 $51,387
Other Administrative Action P00022 · Arra::yes::arra recoveryproject#::141742::RP# FT gibson & john redmond T-gate rehab brace repairs to gates 13 to 30 $96,930
Other Administrative Action P00020 · MOD#20 arra $0
Other Administrative Action P00020 · Arra::yes::arra recoveryproject#::xxxxx::RP# FT gibson & john redmond T-gate rehab add on days for work 7/1/10 to 6/30/11 $0
Other Administrative Action P00019 · Arra::yes::arra recoveryproject#::140568::RP# FT gibson & john redmond T-gate rehab JR repairs to tainter gate 6 $1,144
Other Administrative Action P00019 · Paid with arra funds $0
Other Administrative Action P00018 · Reference no. R00018 00020 FG-arch goug seam weld BTM gates 25-30 this MOD was paid with arra money. $0
Other Administrative Action P00018 · Arra::yes::arra recoveryproject#::141742::RP# FT gibson & john redmond T-gate rehab 00020 FG-arch goug seam weld BTM gates 25-30 $64,750
Other Administrative Action P00017 · 00018 FG gate 11 web repair on bottom girder. This MOD was funded with arra money. $0
Other Administrative Action P00017 · Arra::yes::arra recoveryproject#::141742::RP# FT gibson & john redmond T-gate rehab 00018 FG gate 11 web repair on bottom girder $2,288
Other Administrative Action P00016 · Arra::yes::arra recoveryproject#::141742::RP# FT gibson and john redmond T-gate rehab. FG G9 replace brace on W trunnion $17,771
Other Administrative Action P00016 · FG G9 repalce brace on W trunnion - this modification was used on arra funds $0
Other Administrative Action P00015 · Modification was used on arra funds. $0
Other Administrative Action P00015 · Arra::yes::arra recoveryproject#::141742::RP# FT. Gibson & john redmond T-gate rehab modification to extend completion date (john redmond only). $0
Change Order P00014 · FT gibson tainter gatesnon-arra $0
Supplemental Agreement for work within scope P00014 · Arra::yes::arra recoveryproject#::141742::RP# FT gibson & john redmond T-gate rehab, fort gibson, OK and john redmond, KS. Modification toremove and replace 3… $8,768
Other Administrative Action P00005 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00006 · Arra::yes::arra recoveryproject#::141742::RP# FT. Gibson & john redmond T-gate rehab modification for additional weld repair quantities required to repair 30… $207,000
Other Administrative Action P00008 $0
Other Administrative Action P00004 $0
Other Administrative Action P00010 $0
Other Administrative Action P00007 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00013 · FT. Gibson & john redmond T-gate rehab modification to ARC gouge the weld on the skin plate and W14X34 along the bottom of the tainter gate the entire 40'… $0
Other Administrative Action P00007 · Arra::yes::arra recoveryproject#::141742::RP# FT. Gibson & john redmond T-gate rehab modification add 95% UT testing TG chain links for tainter gates not… $60,324
Other Administrative Action P00009 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00005 · Arra::yes::arra recoveryproject#::140568::RP# FT. Gibson & john redmond T-gate rehab modification to provide equipment and services to retrieve bulkhead from… $11,063
Other Administrative Action P00012 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00010 $14,123
Other Administrative Action P00012 $37,950
Other Administrative Action P00009 · Arra::yes::arra recoveryproject#::140568::RP# FT. Gibson & john redmond T-gate rehab modification to repair bulkhead and concrete peir damage due to a high… $30,796
Other Administrative Action P00006 · FT gibson tainter gatesnon-arra $0
Other Administrative Action P00004 · Arra::yes::arra recoveryproject#::140568::RP# FT. Gibson & john redmond T-gate rehab modification for revisions to gates 10, 11 & 12. $182,664
Other Administrative Action P00013 $259,000
Other Administrative Action P00011 · FT gibson tainter gatesnon-arra $0
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a federal contract award from the U.S. Army Corps of Engineers (USACE) to Hartman-Walsh Painting Company, a subsidiary of Hartman-Walsh Corp, for the rehabilitation of tainter gates at Fort Gibson and John Redmond Dams. The contract, valued at $2,325,985.87, is a definitive, firm-fixed-price contract awarded on September 22, 2009, with a completion date of July 1, 2013. This contract is not designated as a set-aside. Hartman-Walsh Painting Company is a for-profit Subchapter S Corporation that specializes in protective coating services, surface preparation, and corrosion mitigation for critical infrastructure facilities, particularly dams and hydroelectric power plants. The company has a history of securing similar contracts from the Bureau of Reclamation for maintenance and rehabilitation projects at federal water and power assets across the western United States.

Quick answers

Who was awarded contract W912BV09C1013?

W912BV09C1013 was awarded to Hartman-Walsh Painting Company by ENDIST Tulsa (US Army Corps of Engineers) on September 22, 2009.

How much is contract W912BV09C1013 worth?

The government has obligated $15,388,955 on W912BV09C1013. Its current value, with exercised options, is $2,325,986.

Was contract W912BV09C1013 competed?

The extent of competition for W912BV09C1013 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award