Definitive Contract W9128F23C0029
Award Date 8/14/23
Potential Completion Date 11/10/23
Potential Value $440K
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Lincoln, NE 68501, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
5
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a firm fixed-price construction contract awarded by the U.S. Department of the Army Corps of Engineers to TCW Construction, Inc., a minority-owned and small disadvantaged business, for the rehabilitation of the Salt Creek Levee in Lincoln, Nebraska. The contract value is $492,691.90 and has a completion date of August 30, 2017. The original solicitation was set aside for small businesses and described the work to be performed, including installation of sheet piling, excavation and...
- The Department of the Army Corps of Engineers awarded a $4.96 million firm fixed price contract to Blade Masters Grounds Maintenance, Inc. for rehabilitation work on the Salt Creek Levees in Lincoln, Nebraska. As a total small business set aside, the contract is reserved for small businesses. Blade Masters will perform the requested levee rehabilitation services from January 2020 through September 2020. The Corps of Engineers manages civil works projects including flood protection infrastructure...
- This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers Omaha District to TCW Construction, Inc., a minority-owned, small disadvantaged business. The contract has a ceiling value of $1,551,796.58 and was awarded on September 8, 2010 with an ultimate completion date of September 30, 2012. The contract is for the 13811 Camp Ashland Levee Tie-Off project along the Platte River in Saunders County, Nebraska, and was funded through the American Recovery and...
- <p>This is a $7,531,444.06 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE) to Commercial Contractors Equipment, Inc. for an environmental restoration project involving the construction of seven sediment dams in Saunders County, Nebraska. The contract is funded through the American Recovery and Reinvestment Act (ARRA) and has a completion date of November 30, 2013. The contract was set aside for small businesses.</p>
- This is a firm fixed-price definitive contract awarded by the Department of the Army Corps of Engineers Engineering District Omaha to Valley Corp, doing business as Midwest Aggregates, a for-profit subchapter S corporation. The $4,219,802.85 contract is for work related to installing a multi-stage granular filter and drain, removing and replacing conduit with a steel pipe and air shaft, and grading at the downstream end of four high hazard dams in Pawnee City, Nebraska. The contract does not...
- This is a $1,210,436 firm-fixed-price contract awarded by the U.S. Army Corps of Engineers to Alltech Engineering Corp, a small business subchapter S corporation, for sluice gate valve repair at the Harlan County Dam in Nebraska. The work includes installing counterbalance valves, rebuilding control valves, and replacing hydraulic components, with a completion date of May 7, 2024. This contract was competitively bid and is not set aside. Alltech Engineering Corp has extensive experience...
- The U.S. Army Corps of Engineers awarded a $7.9 million firm fixed price contract to Midwest Construction Company for levee repair work along Papio Creek in Papillion, Nebraska. The contract was solicited as a consolidated requirement under the Corps' Papio Creek Levee Repair project, with a written determination justifying this approach. As a total small business set-aside awarded under the Corps' civil works program, the contract aims to strengthen flood protection infrastructure. Midwest...
- This is a $574,606.55 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers to Alltech Engineering Corp, a small business subchapter S corporation, to replace an irrigation gate at the Harlan County Project Office in Nebraska. The contract has a completion date of October 10, 2024. The original solicitation was a pre-solicitation notice for construction services to demolish and install a new 48"x48" water control slide gate, frame, and actuator at Harlan...
- This is a Firm Fixed Price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE), Omaha District to Midwest Levee Inspectors, LLC, a small business concern. The contract is for Levee Safety Inspection Architectural and Engineering (AE) Services and is part of the larger USACE Dam and Levee Safety 2009-2015 Indefinite Delivery Indefinite Quantity (IDIQ) contract vehicle. The contract has a ceiling value of $3,164,814.00 and a period of performance through February 22,...
- The Department of the Army Corps of Engineers awarded a $1.76 million firm fixed price definitive contract to KEU Inc. to perform UNION & NO NAME DIKES PLATTE RIVER LEFT BANK, NE FLOODING REPAIR work in Union, Nebraska. The contract is set aside for total small business and will run from April 6, 2020 through October 13, 2020 to repair flooding along the left bank of the Platte River in Union. The Army Corps of Engineers regularly issues contracts for flood prevention and repair work...
This is a $439,955.78 firm-fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) to Mount Farm Drainage, LLC for the SALT CREEK LEVEE REPAIR in Lincoln, Nebraska. The contract has a completion date of November 10, 2023 and does not have a set-aside designation. The contract was awarded under a full and open competition, and originated from a pre-solicitation notice for the refurbishment of eighteen-foot diameter spiral case inlet butterfly valves and associated systems at the Fort Peck Dam in Montana. The refurbishment work is intended to improve internal bypass leakage, address component end-of-life issues, and improve system reliability at the dam.
Generated 2/26/25, 10:04 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Fort Peck Butterfly Valve Rehabilitation Powerhouse 2 | W9128F23B0009 | Department of the Army Corps of Engineers Engineering District Omaha | Pre-Solicitation 1/1 | 2/6/23, 9:32 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| A00002 | Supplemental Agreement for work within scope | ($23k) | 1/31/24 | |
| A00001 | Supplemental Agreement for work within scope | $70.0k | 10/19/23 | |
| Not listed | Not listed | $392.9k | 8/9/23 |