FY14 MCA PN057797 echo pier restoration, U.S. Army kwajalein atoll (USAKA), republic of the marshall islands

Active Definitive Contract Awarded Last action

Contract number
W9128A16C0006
Awardee
Awarding agency
Obligated
$58,728,987

Award facts

Opportunity
Contract value 100% obligated
$58,728,987.11 Current and potential, with all options
Completion date 99% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Marshall Islands

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00028 · Echo - A00028 - KC016 - stored material-K9 & K19 clause $0
Change Order P00016 · Notice to proceed $0
Novation Agreement P00015 · Echo pier - novation $0
Supplemental Agreement for work within scope P00014 · Echo pier global settlement $866,508
Funding Only Action P00013 · MCA PN059779 echo pier restoration, U.S. Army kwajalein atoll (USAKA), republic of the marshall islands $18,920
Funding Only Action P00012 · Deobreob clin 0010 $0
Supplemental Agreement for work within scope P00011 · Echo pier - assignment of claims $0
Change Order A00027 · R00039 KC006 A00027 COVI19 pandemic time extension, default $0
Funding Only Action P00010 · The purpose of this no-cost administrative modification is to change the internal funding source in the corps of engineers financial management system (CEFMS)… $0
Supplemental Agreement for work within scope A00026 · R00038, KC003, A00026 cleat repair credit & GFM install add $0
Supplemental Agreement for work within scope A00025 · R00037, KC005, A00025 LSC deobligation FY21 -$368,996
Other Administrative Action P00009 · Reob/deob no cost MOD $0
Supplemental Agreement for work within scope A00024 · R00035, CI043, A00024 OSW elec layout change $205,572
Change Order A00023 · R00034, A00023, KC002 covid-19 pandemic time extension $0
Supplemental Agreement for work within scope A00022 · R00033, KC001, A00022, LSC deobligation FY20 -$278,004
Change Order A00021 · R00032, CI046, weather delays 2018-2019 $0
Change Order P00008 · R00028, CI040, foxtrot/bravo upgrades $2,358,000
Change Order P00006 · R00026, CI021, REA charlie delay $859,500
Supplemental Agreement for work within scope P00007 · Echo pier - P00007 $502,553
Change Order A00020 · R00031, CI016, DSC broken extraction piles, CI024, DSC debris removal, CI037, creosote piles $267,200
Change Order A00019 · R00030, CI030, DSC broken H-piles $477,500
Change Order A00018 · R00029, CI044, project transportation $66,500
Change Order A00017 · R000025, CI041, scour hole bravo $245,000
Change Order A00016 · R00024, CI025 DSC concrete and other structures, CI027, DSC MH27C2 unknown pipe $107,929
Change Order P00005 · R00023, CI039, descope options 1-8 -$5,000,000
Change Order A00015 · Reference no. R00022 CI023 sewer tie-in $78,586
Change Order P00004 · Reference no. R00021 CI019-3 DSC remove 32 addl piles, definitized $1,900,000
Change Order A00014 · Reference no. R00020 CI005 relocate FDC and BFP assemblies $150,000
Change Order A00013 · Reference no. R00018 CI029 cosa batch plant land use $0
Change Order P00003 · Reference no. R00019 CI019-2 DSC remove 32 addl piles, NTE-2 $1,000,000
Change Order A00012 · Reference no. R00017 CI020 sheet pile staging area $0
Change Order A00011 · Contract for FY14 MCA PN059779 echo pier restoration at kwajalein atoll, RMI. Reference no. R00016 CI006 replace specification SEC 09 97 13.27 CI015 replace… $0
Change Order A00010 · Reference no. R00015 CI014 REA for additional asbestos in B-605 $27,730
Change Order A00009 · Reference no. R00014 CI017 weather days for 2017 & 1JAN-31MAY 2018 $0
Change Order P00002 · Reference no. R00013 CI019-1 extract or cut & remove 32 addl piles $1,200,000
Change Order A00008 · Reference no. R00012 CI018 concrete washout PIT $0
Change Order A00007 · R00011, CI008-2, revisions to temp mooring PT (FINALIZE) $80,000
Change Order A00006 · Reference no. R00010 CI011 add rebar utility trench & drain inlet $49,426
Change Order A00005 · Reference no. R00009 CI003 change batch plant location CI004 time extension for delays to LSC avail. -$59,662
Change Order A00004 · Reference no. R00008 CI007-2 repair 2 critical sink holes(FINALIZED) $65,308
Change Order A00003 · R00007, CI007-1, repair 2 critical sink holes $150,000
Supplemental Agreement for work within scope A00002 $200,000
Supplemental Agreement for work within scope A00001 · Echo pier - bid amount $0
Supplemental Agreement for work within scope P00001 · Echo pier LSC funded action -$1,284,592
Original award $54,844,009
Show all 45

About this award

The Department of the Army, contracting through ENDIST Honolulu, awarded a definitive contract to Arkel International, L.L.C. for Echo Pier restoration at U.S. Army Kwajalein Atoll in the Republic of the Marshall Islands on July 28, 2016, with a ceiling value of $61.7 million and ultimate completion date of November 5, 2026.

The contract is firm fixed price with no set-aside applied. Arkel International is a HUBZone joint venture headquartered in Baton Rouge, Louisiana. Place of performance is the Marshall Islands. The awardee delivers overseas construction, engineering, and infrastructure services, with representative work including power system design and installation, facility repair, and design-build construction in remote locations.

Quick answers

Who was awarded contract W9128A16C0006?

W9128A16C0006 was awarded to Arkel International, L.L.C. by ENDIST Honolulu (US Army Corps of Engineers) on July 28, 2016.

How much is contract W9128A16C0006 worth?

The government has obligated $58,728,987 on W9128A16C0006.

Was contract W9128A16C0006 competed?

The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award