Construction of cutoff wall in clearwater DAM

Ended Definitive Contract Awarded Last action

Contract number
W9127S08C0031
Awardee
Awarding agency
Obligated
$103,529,786

Award facts

Opportunity
Contract value 809% obligated
$12,790,320.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Piedmont, MO 63957, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00049 $0
Supplemental Agreement for work within scope P00049 · P00049 final quantities $0
Supplemental Agreement for work within scope P00048 $0
Supplemental Agreement for work within scope P00048 · P00048 additional stone protection $0
Change Order P00047 $0
Change Order P00047 · Provide for a negotiated settlement of the indirect costs associated with the contractor¿S request for equitable adjustment proposal for panel obstructions… $0
Change Order P00046 · First 87,000 square feet-arra $0
Change Order P00046 · A. Description 1. Provide for a negotiated settlement of all costs for the contractor S request for equitable adjustment proposal dated august 26, 2013,… $6,113,455
Change Order P00045 · A. Description provide for an equitable adjustment to the contract for the following: 1. Add 2-foot thick stone protection above a 1-foot thick bedding/filter… $0
Other Administrative Action P00044 $0
Other Administrative Action P00044 · This administrative change incorporates the following described, necessary actions to remedy prior modification data entries into the standard procurement… $0
Change Order P00043 · Direct costs RFR $1,673,843
Change Order P00043 · Direct cost RFR obstructions $0
Definitize Change Order P00042 · Definitize change order P00042 $0
Definitize Change Order P00042 · Definitize change order P000042 $432,893
Supplemental Agreement for work within scope P00041 $0
Supplemental Agreement for work within scope P00041 · P00041 gate and asphalt $0
Other Administrative Action P00040 · Quanity adjustment modification $0
Other Administrative Action P00040 · Quantity adjustment modification $0
Supplemental Agreement for work within scope P00039 · Handrails and guard $0
Supplemental Agreement for work within scope P00039 · Handrails and gates $0
Supplemental Agreement for work within scope P00038 $0
Supplemental Agreement for work within scope P00038 · Guardrail and filter rock and seeding $0
Supplemental Agreement for work within scope P00037 $0
Supplemental Agreement for work within scope P00037 · Quantity adjustment modification $0
Supplemental Agreement for work within scope P00036 $0
Supplemental Agreement for work within scope P00036 · P00036 platform fill and rock placement $0
Supplemental Agreement for work within scope P00034 · Clearwater major rehab cutoff wall $0
Supplemental Agreement for work within scope P00035 · Clearwater cutoff wall construction $0
Supplemental Agreement for work within scope P00034 · Clearwater major rehab cutoff wall $0
Supplemental Agreement for work within scope P00035 · Clearwater cutoff wall construction $0
Supplemental Agreement for work within scope P00033 · Clearwater cut off wall, clearwater lake, piedmont MO $0
Supplemental Agreement for work within scope P00033 · Clearwater cut off wall $0
Other Administrative Action P00032 · Contract modification number P00032 to provide additional funds in the amount of $75,500 in support of the cutoff wall construction, clearwater major… $0
Other Administrative Action P00032 · Contract modification P00032 to provide for additional funds in the amount of $75,500 for the cutoff wall construction, clearwater major rehabilitation,… $75,500
Funding Only Action P00031 · First 170,000 square feet $0
Funding Only Action P00031 · First 87,000 square feet-arra $1,300,000
Change Order P00029 $0
Funding Only Action P00030 · First 170,000 square feet $0
Change Order P00029 $0
Funding Only Action P00030 · First 87,000 square feet-arra $0
Other Administrative Action P00028 · First 170,000 square feet $0
Other Administrative Action P00028 · First 87,000 square feet-arra $0
Other Administrative Action P00027 · First 170,000 square feet $0
Other Administrative Action P00027 · First 87,000 square feet-arra $0
Other Administrative Action P00016 · First 87,000 square feet-arra MOD P00016 $0
Other Administrative Action P00016 · First 170,000 square feet - MOD P00016 $0
Other Administrative Action P00015 · First 87,000 square feet-arra $0
Other Administrative Action P00015 · First 170,000 square feet MOD P00015 $0
Other Administrative Action P00026 · First 170,000 square feet $516,820
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $12,790,320.00 firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers (USACE), Little Rock District, to the Bencor-Recon Joint Venture for the construction of a cutoff wall at the Clearwater Dam in Piedmont, Missouri. The contract has a completion date of February 28, 2015 and does not have a set-aside designation. The USACE is responsible for the oversight and management of this construction project.

Quick answers

Who was awarded contract W9127S08C0031?

W9127S08C0031 was awarded to Bencor-Recon, Joint Venture by ENDIST Little Rock (US Army Corps of Engineers) on September 25, 2008.

How much is contract W9127S08C0031 worth?

The government has obligated $103,529,786 on W9127S08C0031. Its current value, with exercised options, is $12,790,320.

Was contract W9127S08C0031 competed?

The extent of competition for W9127S08C0031 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award