Lookout point spillway gate hoist rope replacement

Ended Definitive Contract Awarded Last action

Contract number
W9127N10C0028
Awardee
Awarding agency
Obligated
$1,457,826

Award facts

Contract value 270% obligated
$539,752.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Lowell, OR 97452, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00006 · Arra::yes::arra recoveryproject#::322610::RP# fall creek rehabilitation of spillway trunnion and hoist rope replacement and lookout point spillway gate hoist… $0
Supplemental Agreement for work within scope P00006 · Fall creek rehabilitation of spillway trunnion and hoist rope replacement and lookout point spillway gate hoist replacement -$40,044
Additional Work (new agreement, FAR part 6 applies) P00005 · Arra::yes::arra recoveryproject#::322610::RP# fall creek spillway trunnion rehabilitation and hoist rope replacement and lookout point spillway gate hoist… -$42,400
Additional Work (new agreement, FAR part 6 applies) P00005 · LOP SW gate wirerope RPL CT --- project $0
Additional Work (new agreement, FAR part 6 applies) P00004 · LOP SW gate wirerope RPL $4,968
Additional Work (new agreement, FAR part 6 applies) P00004 · Fall CK spillway trunnion replacement arra $0
Change Order P00003 · Arra::yes::arra recoveryproject#::322610::RP# fall creek spillway gates trunion rehabilitation and wire rope replacement and lookout point spillway gates wire… $0
Change Order P00003 · Green peter spillway gate repair $52,000
Exercise an Option P00002 · LOP SW gate wirerope RPL CT --- project $275,110
Exercise an Option P00002 · Fall CK spillway trunnion replacement $0
Change Order P00001 · Fall creek spillway gate trunnion rehabilitation and hoist rope replacement $42,400
Change Order P00001 · Recoveryproject#::322910::RP# fall creek spillway gate trunnion rehabilitation and hoist rope replacement. This modification exercise optional items 7009 for… $42,400
Modification Recoveryproject#::322610::RP# fall creek spillway gate trunion rehabilitation and hoist rope replacement. The scope of the project includes replacing the wire… $539,752
Original award $583,640
Show all 14

About this award

This is a federal contract award to Knight Construction & Supply, Inc. for the Lookout Point Spillway Gate Hoist Rope Replacement project. The $539,752.00 firm fixed price contract was awarded on May 25, 2010 by the U.S. Army Corps of Engineers, and has a completion date of November 19, 2010. The contract does not have a set-aside designation. Knight Construction & Supply, Inc. is a heavy industrial construction company that specializes in dam maintenance and construction, plant maintenance and rehabilitation, and other infrastructure projects. They have previously held prime federal contracts with agencies like the Department of the Interior Bureau of Reclamation and the Department of Energy Bonneville Power Administration.

Quick answers

Who was awarded contract W9127N10C0028?

W9127N10C0028 was awarded to Knight Const. & Supply, Inc. by ENDIST Portland (US Army Corps of Engineers) on May 25, 2010.

How much is contract W9127N10C0028 worth?

The government has obligated $1,457,826 on W9127N10C0028. Its current value, with exercised options, is $539,752.

Was contract W9127N10C0028 competed?

The extent of competition for W9127N10C0028 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award