Definitive Contract W9127823C0005

Award Date 2/22/24
Potential Completion Date 7/25/25
Potential Value $3.5M
Funding Federal Agency
US Army Corps of Engineers
Contracting Federal Agency
ENDIST Mobile
Ultimate Awardee
Not listed
Set-Aside Type
Total Small Business
Federal Contract Vehicle
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Gibsonton, FL 33534, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
3
Legislative Mandate
Not listed
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This is a $8,328,072.80 firm-fixed-price contract awarded by the U.S. Army Corps of Engineers to Tampa Tank & Welding, LLC for the fabrication and delivery of vertical lift gate structures for the Lockport Lock and Dam in Lockport, Illinois. The contract is a 100% small business set-aside and was awarded under a lowest price technically acceptable (LPTA) source selection approach. The original solicitation was a pre-solicitation notice posted on June 28, 2021 seeking proposals from small...
The Department of the Army Corps of Engineers, Engineering District Mobile, awarded a firm fixed-price definitive contract to Steward Machine Co Inc., doing business as Earle Reducers, to fabricate and deliver a new spillway tainter gate for the Stennis Lock and Dam on the Tennessee-Tombigbee Waterway in Mississippi. The contract, valued at $755,615.00, was set aside for small businesses. Steward Machine Co Inc. is a for-profit manufacturer registered in the System for Award Management (SAM)...
This firm-fixed-price definitive contract was awarded by the U.S. Army Corps of Engineers to Massman Construction CO., a general contractor specializing in heavy civil marine construction, to rehabilitate the miter gates at the National Aeronautics and Space Administration's (NASA) John C. Stennis Space Center Navigation Lock in Carriere, Mississippi. The $7,149,702.55 contract, awarded on September 14, 2021, with a completion date of December 16, 2023, involves removing and rehabilitating...
This federal contract award, W912EE23C0005, is for the furnish and installation of a Tainter gate by the prime contractor, Sealevel Construction Inc. The contract has a ceiling value of $34,841,473.55 and is a definitive, firm-fixed price contract awarded by the U.S. Army Corps of Engineers, Vicksburg District (USACE-MVK), a defense agency. The contract has a period of performance through July 28, 2026, with no set-aside designation. The original contract opportunity was a sources...
The U.S. Army Corps of Engineers awarded a $18,216,838.00 Firm Fixed Price contract to G & G Steel Inc., a small business manufacturer in Russellville, Alabama, to fabricate and deliver replacement miter gates and associated equipment for Locks 3, 4, and 5 on the Upper Mississippi River. This contract is part of the Corps' efforts to maintain and improve the nation's inland waterway infrastructure. The contract is a set-aside for small businesses and includes options for ancillary...
This is a definitive contract awarded by the U.S. Army Corps of Engineers to G & G Steel Inc., a small business manufacturer based in Russellville, Alabama. The $1,187,798.83 fixed-price contract is for the fabrication, delivery, and installation of a replacement main lock miter gate for Locks 27 located in Granite City, Illinois. The work is funded through the American Recovery and Reinvestment Act (ARRA) and is part of a project to maintain and improve the nation's inland waterway...
The U.S. Department of the Army Corps of Engineers Engineering District Mobile awarded a $168,994.18 firm fixed price delivery order to the WSP E&I HDR Civil Works Joint Venture for the quality assurance inspection of the Stennis Lock spillway gate fabrication at the John C. Stennis Space Center in Mississippi. The contract, which does not have a set-aside designation, was awarded on December 22, 2017 and is scheduled for completion on November 22, 2019. As the Corps of Engineers is...
This is a $7,892,784.00 definitive contract awarded by the U.S. Army Corps of Engineers to G & G Steel Inc., a for-profit manufacturing corporation, to supply hydraulic steel lift gates for the Melvin Price Locks and Dam Main Lock in Russellville, Alabama. The contract has a firm fixed price and a period of performance through February 14, 2025. This award is not associated with a set-aside program. The original solicitation, issued as a request for proposal on June 11, 2021, sought...
This is a $12,003,822.03 fixed-price contract awarded by the U.S. Army Corps of Engineers to G & G Steel Inc., a small business manufacturer in Russellville, Alabama. The contract is for the fabrication and delivery of miter gates, spare parts, and valves for the Holt Lock and Dam on the Black Warrior River in Cottondale, Alabama. The original solicitation was a 100% small business set-aside seeking bids for the construction and delivery of a set of miter gates, with an optional item for...
The Department of the Army Corps of Engineers Engineering District St Paul awarded a $1.55 million firm fixed price contract to Missouri Fabricators of Fulton, Missouri to replace tainter valves at Lock and Dam 2 on the upper Mississippi River. The contract, set aside for total small businesses under NAICS Code 332312 for Fabricated Structural Metal Manufacturing, calls for Missouri Fabricators to fabricate and deliver replacement tainter valves and associated ancillary equipment. This work...

This $3,470,686.00 firm fixed price contract was awarded by the U.S. Army Corps of Engineers to Precision Build Solutions LLC, doing business as Tampa Tank, for the fabrication and delivery of Stennis Spillway Gate #2 for the John C. Stennis Lock and Dam on the Tennessee-Tombigbee Waterway near Columbus, Mississippi. The new 60-foot wide, 29-foot tall, 180,000-pound gate is to be delivered via barge by July 2025. The contract also includes an option to repair the existing Spillway Gate #3. This contract is set aside for small businesses and was competed under the Corps of Engineers' $160 million Metal Fabrication, Refurbishment, and Installation Multiple Award Task Order Contract (MATOC), which supports a wide range of infrastructure projects across the Great Lakes and Ohio River Division.

Generated 11/13/24, 9:09 AM