Base year BW & T operation and maintenance.

Ended Definitive Contract Awarded Last action

Contract number
W9127821C0018
Awardee
Awarding agency
Obligated
$72,553,662

Award facts

Contract value 88% obligated
  • $80,075,584.30 Current, with exercised options
  • $82,828,654.00 Potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
NAICS code
561210 Facilities Support Services
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Tuscaloosa, AL 35401, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Exercise an Option P00071 $688,267
Funding Only Action P00070 · BWT operations and maintenance $197,540
Funding Only Action P00069 · The purpose of this modification is to increase option year 4 funding for the operation and maintenance of government owned facilities and equipment, black… $25,000
Other Administrative Action P00067 $0
Change Order P00066 $109,698
Change Order P00065 $137,738
Funding Only Action P00064 · The purpose of this modification is to increase option year 4 contract funding for the operation and maintenance of government owned facilities and equipment,… $334,560
Supplemental Agreement for work within scope P00063 · The purpose of this modification incorporate repair work for bankhead transformer emergency replacement in accordance with scope of work. $88,442
Change Order P00062 $56,690
Funding Only Action P00061 $2,554,000
Funding Only Action P00060 · The purpose of this modification is to DE-obligate cost-plus funding from option years 3 and 4 contract funding for the operation and maintenance of… -$723,824
Funding Only Action P00059 · The purpose of this modification is to increase incremental funding. $15,044
Change Order P00058 · The purpose of this modification is to incorporate performance and payment bond for elevator repair bankhead lock and DAM. $3,485
Change Order P00057 · The purpose of this modification incorporates repair work for choctawhatchee and lawson repair in accordance with scope of work, and increase OY4 funding, for… $141,371
Change Order P00056 · The purpose of this modification is to increase incremental funding. $3,753,050
Change Order P00055 · The purpose of this modification is to increase option year 4 contract amount for elevator repair bankhead lock and DAM and increase OY4 funding. $276,255
Exercise an Option P00054 · The purpose of this modification is to exercise option year 4. $912,500
Funding Only Action P00053 · The purpose of this modification is to increase & DE-obligate funding to option year 3, for the operation and maintenance of government owned facilities and… $309,513
Funding Only Action P00052 · The purpose for this modification is to obligate & DE-obligate funding. -$36,420
Funding Only Action P00051 · The purpose of this modification is to adjust the contract value to incorporate the request for equitable adjustment due to the federal minimum wage increase… $928,594
Funding Only Action P00050 · The purpose of this modification is to increase incremental funding. $15,000
Change Order P00049 · The purpose of this modification is to incorporate the additional work for R. F. Henry spillway gate repainting and repairs. $3,628,722
Change Order P00048 · The purpose of this modification is to incorporate additional work for service campground water line replacement and increase funding for OY3. $422,486
Funding Only Action P00047 · The purpose of this modification is to add funding to OY3. $689,370
Change Order P00046 · The purpose of this modification is to incorporate R.F. Henry gate #1 machinery repairs in accordance with the SOW. $714,326
Funding Only Action P00045 · The purpose of this modification is to decrease OY2 funding. -$3,075,955
Funding Only Action P00044 · The purpose of this modification is to increase OY3 funding. $2,153,890
Change Order P00043 $416,276
Change Order P00042 $3,155
Change Order P00041 · The purpose of this modification is to increase option year 3 contract amount for jones bluff powerhouse - handrails repair. $61,139
Exercise an Option P00040 · The purpose of this modification is to exercise OY3. $2,088,000
Funding Only Action P00039 · The purpose of this modification is to increase OY2 funding. $140,000
Change Order P00038 · The purpose of this modification is to incorporate additional work for holt bulkhead repair in accordance with the SOW. $1,312,187
Funding Only Action P00037 · The purpose of this modification is to add funding for option year 2. $650,611
Funding Only Action P00036 · The purpose of this modification is to incrementally fund contract W9127821C0018. $540,000
Change Order P00035 · The purpose of this modification is to increase incremental funding, and incorporate dfars clause 252.245-7005 and removes dfars clauses 252.211-7007,… $1,195,000
Change Order P00034 · The purpose of this modification is to add the nitrogen injection system for demopolis miter gate remair. $388,505
Change Order P00033 · The purpose of this modification is to add additional working days for concrete removal. $499,069
Funding Only Action P00032 · The purpose of this modification is to increase funding to option year 2. $720,000
Change Order P00031 · The purpose of this modification is to increase option year 2 contract amount for demopolis emergency lock additional concrete mixing plant. $255,787
Funding Only Action P00029 · The purpose of this modification is to increase funding for OY2. $545,000
Change Order P00030 · The purpose of this modification is to increase option year 2 contract amount for demopolis emergency lock concrete removal. $604,494
Supplemental Agreement for work within scope P00028 · The purpose of this modification is to accomplish within scope work for demopolis lock sill repair OY 2 - technical provisions 7. $18,010,982
Change Order P00027 · The purpose of this modification is to incorporate additional work for the closure and dewater demopolis lock for inspection and repair of the upper miter sill. $747,163
Change Order P00026 · The purpose of this modification is to increase option year 2 funding, and to incorporate additional work in accordance with scope of work for miscellaneous… $1,958,244
Funding Only Action P00025 $1,474,895
Funding Only Action P00024 $222,418
Funding Only Action P00023 $1,098,000
Funding Only Action P00022 · The purpose of this modification is to add additional funding to option year 2. $35,634
Change Order P00021 · The purpose of this modification is to complete additional repairs in accordance with scope of work for R. F. Henry and claiborne spillway repairs. $3,242,559
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

ENDIST Mobile, a Defense organization, awarded an $82.8 million ceiling definitive contract to R & D Maintenance Services Inc. on July 1, 2021, under a total small business set-aside for base-year operation and maintenance of Black-Warrior-Tombigbee (BWT) facilities. The prime awardee is described as a small-business Subchapter S corporation based in Tulsa, Oklahoma.

The originating pre-solicitation, posted November 3, 2020 by Corps of Engineers Engineering District Mobile with proposals due January 20, 2021, sought operation and maintenance of government-owned facilities and equipment along the Black-Warrior-Tombigbee and Alabama River waterways in Alabama. Scope covers buildings, structures, electrical and mechanical systems, recreation areas, docks, dams, equipment, and vehicles. Place of performance is Tuscaloosa, Alabama. The solicitation contemplated a hybrid firm fixed-price contract with cost-plus-fixed-fee line items for a base year plus four one-year options, set aside 100% for small businesses under NAICS 561210 with a $41.5 million average annual revenue size standard. The award is recorded as firm fixed price with an ultimate completion date of February 28, 2027.

Quick answers

Who was awarded contract W9127821C0018?

W9127821C0018 was awarded to R & D Maintenance Services Inc. by ENDIST Mobile (US Army Corps of Engineers) on July 1, 2021.

How much is contract W9127821C0018 worth?

The government has obligated $72,553,662 on W9127821C0018. Its current value, with exercised options, is $80,075,584. Its potential value, with all options, is $82,828,654.

Was contract W9127821C0018 competed?

The extent of competition for W9127821C0018 was full and open competition after exclusion of sources. The government received 1 offer. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award