O & M services for government-owned facilities and equipment - woodruff/seminole site, chattahoochee, florida - base year requirements

Ended Definitive Contract Awarded Last action

Contract number
W9127810C0122
Awardee
Awarding agency
Obligated
$9,972,215

Award facts

Contract value 82% obligated
$12,148,609.29 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
561210 Facilities Support Services
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 1 offer Negotiated Proposal / Quote
Pricing
Cost Plus Award Fee
Place of performance
Chattahoochee, FL 32324, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00074 · Walter F. George O & M-option year 2 and 3 -$2,754
Funding Only Action P00073 · Modification to incrementally increase funding for lake seminole O & M services. $100,000
Funding Only Action P00072 · Modification to incrementally increase funding for O & M services at lake seminole. $99,998
Funding Only Action P00071 · Modification to incrementally fund contract $100,002
Exercise an Option P00070 · Modification to extend the POP of option year 4 from 30 september 2015 to 31 march 2016 $250,000
Funding Only Action P00069 · Modification to incrementally increase funding for lake seminole O & M services. $135,000
Supplemental Agreement for work within scope P00068 · Modification to add funding for erosion road repair. $327,813
Supplemental Agreement for work within scope P00067 · Option year 4 incorporate new far clause covering O & M services for woodruff/seminole site FL. And GA. $0
Funding Only Action P00066 · MOD to add funding for WFG awrd fee costs for 4TH and 1ST quarter. $25,579
Funding Only Action P00065 · MOD to incrementally increase funding for O & M services $675,035
Funding Only Action P00064 · Modification to deobligate remaining funds for closeout of walter F. George O & M extension. -$15,489
Funding Only Action P00063 · Incremental funding of walter F. George O & M services $50,000
Supplemental Agreement for work within scope P00062 · Modification to incorporate wage rates increase for option year 4. $0
Supplemental Agreement for work within scope P00061 · Exercise of 2 month option for walter F. George O & M $275,000
Exercise an Option P00060 · Exercise of option year four for woodruff/seminole O & M services $300,000
Funding Only Action P00059 · Deobligation of PR & C W31XNJ32961641 for walter F. George O & M. -$77,035
Supplemental Agreement for work within scope P00058 · Modification to add funding for boat ramp paving and incrementally fund for O & M services. $90,537
Supplemental Agreement for work within scope P00057 · Modification to incorporate walter F. George O & M into lake seminole contract. $779,950
Funding Only Action P00056 · MOD to incrementally fund O & M service for lake seminole. $550,000
Funding Only Action P00055 · Modification to incrementally increase funding for lake seminole O & M services. $175,000
Supplemental Agreement for work within scope P00054 · Modification to extend the walter F. George incorporation into lake seminole contract for 60 additional days. -$49,000
Funding Only Action P00053 · Modification to incrementally fund lake seminole O & M services $100,000
Funding Only Action P00052 · Modification to increase funding for walter F. George O & M $300,000
Funding Only Action P00051 · Modification to increase funding for WFG O & M services. $212,000
Funding Only Action P00050 · Modification to increase funding for walter F. George O & M services. $23,000
Funding Only Action P00049 · Modification to adjust wage rates for option year 3 & 4 and modify walter F. George O & M for additional 120 days. $0
Funding Only Action P00048 · Modification to increase funding for O & M services. $100,000
Exercise an Option P00046 · Modification to exercise option year 3 for lake seminole O & M services. $98,411
Funding Only Action P00045 · Modification to deobligate funds -$97,411
Funding Only Action P00044 · Modification to incrementally increase funding for FY13 O & M services for WFG. $250,000
Funding Only Action P00043 · MOD to increase FY13 funding for O & M services for lake seminole and walter F. George $520,630
Funding Only Action P00042 $166,000
Funding Only Action P00041 · Modification to increase funding for O & M services $100,000
Funding Only Action P00040 · Modification to add incrementally funded funds for O & M services for WFG. $55,000
Funding Only Action P00039 · Modification to increase funding for FY13 O & M services for WFG. $300,000
Funding Only Action P00038 · Modification to increase funding for option YR.2 O & M services $125,000
Funding Only Action P00037 · Modification to increase option YR.2 funding for O & M services. $113,172
Supplemental Agreement for work within scope P00036 · Modification to increase option year 2 for O & M services at WFG. $148,010
Funding Only Action P00035 · Modification to increase funding for 2ND option year requirements $100,000
Other Administrative Action P00034 · Modification to correct the total contract amount. $0
Funding Only Action P00033 · Increase funding for option year 2 O & M functions for lake seminole, FL. $55,000
Supplemental Agreement for work within scope P00032 · Modification to increase funding for option YR. 2 O & M work. $195,009
Funding Only Action P00031 · Correct administrative errors and add requirements to obligate incrementally funded funds. $15,321
Other Administrative Action P00030 · Deobligation of funds -$6,001
Funding Only Action P00029 · Adding additional funds for FY13 $0
Supplemental Agreement for work within scope P00028 · 1ST option year requirements $157,000
Supplemental Agreement for work within scope P00027 · Additional work on upgrade of powerhouse security system $60,402
Funding Only Action P00026 · Adding FY12 funds for 1ST option year requirements $26,000
Funding Only Action P00025 · Adding FY12 funds. 1ST option year requirements $0
Funding Only Action P00024 · Obligation of funds $175,000
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a cost-plus-award-fee contract awarded by the U.S. Army Corps of Engineers Mobile District to Anderson Construction Company of Fort Gaines, a small business certified as a HUBZone firm, to provide operations and maintenance (O&M) services for government-owned facilities and equipment at the Woodruff/Seminole site in Chattahoochee, Florida. The contract has a ceiling value of $12,148,609.29 and a period of performance through March 31, 2016. As a prime contractor, Anderson Construction has been tasked with maintaining critical civil works infrastructure such as dams, locks, buildings, roads, and recreation areas managed by the Corps, supporting the agency's mission across over 37,500 acres of project land and water resources in the region.

Quick answers

Who was awarded contract W9127810C0122?

W9127810C0122 was awarded to Anderson Construction Company Of Fort Gaines by ENDIST Mobile (US Army Corps of Engineers) on September 29, 2010.

How much is contract W9127810C0122 worth?

The government has obligated $9,972,215 on W9127810C0122. Its current value, with exercised options, is $12,148,609.

Was contract W9127810C0122 competed?

The extent of competition for W9127810C0122 was full and open competition after exclusion of sources. The government received 1 offer. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award