Design/build two phase construction PF AMC/usasac headquarters, redstone arsenal, alabama.

Ended Definitive Contract Awarded Last action

Contract number
W9127808C0045
Awardee
Awarding agency
Obligated
$53,102,159

Award facts

Contract value 39% obligated
$137,338,575.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
Defense Commissary Agency Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition · 9 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Huntsville, AL 35808, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00084 · Repair parking lot due to sink hole $6,906
Supplemental Agreement for work within scope P00083 · Furniture changes $17,257
Supplemental Agreement for work within scope P00079 · AMC fire pumps $23,443
Supplemental Agreement for work within scope P00078 · Support for joint occupancy $41,388
Supplemental Agreement for work within scope P00080 · Override switch $13,491
Supplemental Agreement for work within scope P00077 · Move CTV equipment in cup $3,860
Supplemental Agreement for work within scope P00076 · Remote badging system $38,134
Supplemental Agreement for work within scope P00071 · Pole work along martin road $13,711
Supplemental Agreement for work within scope P00069 · System furniture changes -$34,265
Supplemental Agreement for work within scope P00067 · AMC organization redesign $25,292
Supplemental Agreement for work within scope P00068 · Finish upgrades- additional cost $58,811
Supplemental Agreement for work within scope P00066 · Install power meter at lift station $1,186
Supplemental Agreement for work within scope P00065 · Change VTC flooring to carpet $6,944
Supplemental Agreement for work within scope P00082 · RP-UPS-ABW6 blank panel at AMC 6TH floor $10,675
Supplemental Agreement for work within scope P00073 · Tackable fabors panels in dirtt walls $76,154
Supplemental Agreement for work within scope P00081 · Security area segregation $139,267
Supplemental Agreement for work within scope P00051 · AMC basement locker rooms $32,987
Supplemental Agreement for work within scope P00064 · AMC/ usasac leed certification $21,887
Supplemental Agreement for work within scope P00074 · Disposal of excess topsoil $131,843
Supplemental Agreement for work within scope P00075 · Movable wall accessories $141,553
Supplemental Agreement for work within scope P00070 · Accessories for system furniture $903,393
Supplemental Agreement for work within scope P00072 · Martin road improvements $424,268
Supplemental Agreement for work within scope P00061 · Change demountable wall to hard walls -$50,898
Supplemental Agreement for work within scope P00060 · System furniture changes $50,973
Supplemental Agreement for work within scope P00059 · Delete UPS requirement for 12 HR security UPS -$59,194
Supplemental Agreement for work within scope P00058 · Display cases: electric, light and glass changes $44,086
Supplemental Agreement for work within scope P00057 · Open storage ROM-04 $19,030
Supplemental Agreement for work within scope P00056 · Change barn door glass from clear to frost $25,621
Supplemental Agreement for work within scope P00055 · Decrease size of south west pond $45,790
Supplemental Agreement for work within scope P00054 · COM/ IT request for equitable adjustments (REA) to include REA-60, 62, 63, & 64 $94,887
Supplemental Agreement for work within scope P00053 · COM/IT REA-058 & 59 $97,750
Change Order P00045 · AMC basement changes $173,339
Supplemental Agreement for work within scope P00052 · COM/ IT REA-57 & 61 $92,212
Supplemental Agreement for work within scope P00063 · Elect from cup to streamline manhole, delete tiered seats, gas line relocation and precast connection $49,545
Supplemental Agreement for work within scope P00062 · AMC upgrade finishes $628,322
Supplemental Agreement for work within scope P00047 · Request for equitable adjustments for COM/IT items on the AMC/usasac headquarters $24,501
Definitize Change Order P00048 · Sinkhole grouting definitization $696,496
Supplemental Agreement for work within scope P00046 · COM/IT requests for equitable adjustments-54 $91,289
Supplemental Agreement for work within scope P00033 · Delete projection screens & food service equipment -$93,485
Supplemental Agreement for work within scope P00049 · Sinkhole repairs $99,855
Supplemental Agreement for work within scope P00039 · COM/IT REA 51, 52, 53 $58,507
Supplemental Agreement for work within scope P00041 · Adverse weather $0
Supplemental Agreement for work within scope P00050 · COM/IT REA 55 & 56 $90,479
Change Order P00040 · Temporary bond liners $53,531
Supplemental Agreement for work within scope P00044 · Procure and deliver furniture, fixtures, and equipment $9,128,245
Change Order P00025 · Cell phone lockers $171,621
Supplemental Agreement for work within scope P00042 · Shages for commanding general's office $107,965
Supplemental Agreement for work within scope P00043 · Security at AMC BCC's (BRIEFING/CONFERENCE/CLASSROOMS) $415,150
Supplemental Agreement for work within scope P00038 · Communication/IT change for REA 40, 42, 43 -$7,967
Supplemental Agreement for work within scope P00037 · Communication/IT change for requests for equitable adjustments (REA) $25,156
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

BL Harbert International LLC was awarded a $137.3 million firm fixed price contract by the Defense Commissary Agency to design and construct Phase Two of the Army Materiel Command/United States Army Security Assistance Command headquarters at Redstone Arsenal, Alabama. The contract has a completion date of September 10, 2012 and was awarded on July 24, 2008 with no set-aside designation specified. BL Harbert International LLC will serve as the prime contractor, drawing upon specialized expertise in design-build and construction management services for federal agencies. Subcontractors may include architectural, engineering and security integration firms as well as suppliers. This project aims to support the critical facilities needs of the Army Materiel Command and United States Army Security Assistance Command through the delivery of new headquarters offices at Redstone Arsenal.

Quick answers

Who was awarded contract W9127808C0045?

W9127808C0045 was awarded to BL Harbert International LLC by ENDIST Mobile (US Army Corps of Engineers) on July 24, 2008.

How much is contract W9127808C0045 worth?

The government has obligated $53,102,159 on W9127808C0045. Its current value, with exercised options, is $137,338,575.

Which agency awarded contract W9127808C0045?

ENDIST Mobile (US Army Corps of Engineers) awarded W9127808C0045, with funding from Defense Commissary Agency (Department of Defense).

Was contract W9127808C0045 competed?

The extent of competition for W9127808C0045 was full and open competition. The government received 9 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award