Base offer air force personnel CTR bldg 499 bwing

Ended Definitive Contract Awarded Last action

Contract number
W9126G21C0016
Awardee
Awarding agency
Obligated
$29,754,614

Award facts

Opportunity
Contract value 100% obligated
$29,754,614.44 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 8 offers Two Step
Pricing
Firm Fixed Price
Place of performance
JBSA FT SAM HOUSTON, TX 78234, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00021 · Afpc, b-wing, building 499, rafb (DBB) MJ036 upgrade RM 224 undersized AC $69,534
Supplemental Agreement for work within scope A00020 · MJ029 add electrical service for dishwasher MJ030 revision to audio/visual rough-in MJ031 demolition of concrete structures & pipe MJ035 framing for roof… $41,266
Supplemental Agreement for work within scope A00019 · Storm drain revisions, revisions to rainwater tank piping $64,413
Supplemental Agreement for work within scope A00018 · Revisions to elevator power, demolition of duct banks, demolition of duct banks, added support for type f walls $57,043
Supplemental Agreement for work within scope P00007 · Fire pump room, part 3 of 3 $429,617
Supplemental Agreement for work within scope A00017 · Add AF & SF logo & terrazzo flooring fire shutter electrical & toiletries roof nailers $33,908
Change Order P00006 · Fire pump room part 2 $539,526
Supplemental Agreement for work within scope A00016 · Change epdm to TPO roofing $0
Supplemental Agreement for work within scope A00015 · REA-2 foundation SOG delays $334,883
Vendor DUNS or Name Change - Non-Novation P00005 · Change of name modification $0
Supplemental Agreement for work within scope A00014 · Change mech RM 111 opening $4,485
Change Order A00013 · MJ014-1 provide fire pump for B499 bwing $60,000
Other Administrative Action P00004 · Modification place correct wage determination. $0
Supplemental Agreement for work within scope A00012 · Reroute communication duct bank $31,222
Supplemental Agreement for work within scope A00011 · Reroute chilled water lines $32,941
Other Administrative Action A00010 · Weather time extension july 22 - november 22 $0
Supplemental Agreement for work within scope A00009 · Increase wall thickness in specific locations due to plumbing lines not fitting the walls the walls. $6,045
Supplemental Agreement for work within scope A00008 · Chilled water line hydro excavation $16,532
Other Administrative Action A00007 · Extends the time 3 calendar days for delays caused by adverse weather in excess of anticipated during the period 01 may 2022 through 30 june 2022 $0
Supplemental Agreement for work within scope A00006 · Site & utility revisions $24,398
Other Administrative Action P00003 · Removing far clause 52.229-12 tax on certain foreign procurements which was included in the contract by mistake $0
Other Administrative Action A00005 · Weather time extension march - april 2022 $0
Supplemental Agreement for work within scope A00004 · Changes to utilities within building footprint $217,727
Other Administrative Action A00003 · Time extension for weather days (7) beyond anticipated for february 2022. $0
Supplemental Agreement for work within scope A00002 · MJ001-2 DSC - unforeseen duct bank & piers this change is for the demolition or partial removal of the unforeseen piers, duct banks, manholes, etc. Found during… $108,709
Change Order A00001 · DSC - demolition of unforeseen duct bank & piers $93,367
Other Administrative Action P00002 · NTP modification base offer $0
Other Administrative Action P00001 · Admin MOD change funding no money increase base offer $0
Original award $27,589,000
Show all 29

About this award

The U.S. Army Corps of Engineers, procuring on behalf of the Air Force Personnel Center (ENDIST Fort Worth), awarded a $29.75 million firm-fixed-price definitive contract to Joeris General Contractors, LLC on July 23, 2021, for construction of additional administrative space at Joint Base San Antonio–Fort Sam Houston, Texas.

The originating pre-solicitation, posted March 30, 2021, describes a two-story, approximately 2-acre facility to provide additional administrative space for AFPC B-Wing, Building 499 at JBSA–Randolph AFB. Work involves structural, electrical, plumbing, HVAC, and other trades. The contract carries a 540 calendar day period of performance with an ultimate completion date of July 7, 2025. NAICS code 236220 (general commercial and institutional building construction) applies, with a size standard of $39.5 million. No set-aside was used. Place of performance is JBSA Fort Sam Houston, TX.

Quick answers

Who was awarded contract W9126G21C0016?

W9126G21C0016 was awarded to Joeris General Contractors, LLC by ENDIST Fort Worth (US Army Corps of Engineers) on July 23, 2021.

How much is contract W9126G21C0016 worth?

The government has obligated $29,754,614 on W9126G21C0016.

Was contract W9126G21C0016 competed?

The extent of competition for W9126G21C0016 was full and open competition. The government received 8 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award