Renovate building 44. Fort SAM houston POP 365 after NTP

Ended Definitive Contract Awarded Last action

Contract number
W9126G18C0100
Awardee
Awarding agency
Obligated
$13,993,349

Award facts

Opportunity
Contract value 100% obligated
$13,993,348.68 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
San Marcos, TX 78666, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00019 · Renovate building 44 MJ031 time extension due to existing fire suppression system issue $0
Supplemental Agreement for work within scope A00018 · Renovate building 44 MJ030 excusable delays for materials $0
Supplemental Agreement for work within scope P00008 · Renovate building 44 MJ023 revised foundation & staircase design $291,375
Supplemental Agreement for work within scope A00017 · Renovate building 44 MJ028 access card reader system addition $66,027
Supplemental Agreement for work within scope A00016 · Renovate building 44 MJ026 data switches addition $287,520
Supplemental Agreement for work within scope A00015 · Renovate building 44 MJ027 comms cable tray addition $60,790
Supplemental Agreement for work within scope A00014 · Renovate building 44 MJ025 sipr icids 4 addition $183,000
Supplemental Agreement for work within scope A00013 · Renovate building 44 MJ014 remove sipr -$53,304
Supplemental Agreement for work within scope A00012 · Renovate building 44 MJ024 access control door variation -$688
Supplemental Agreement for work within scope A00011 · Renovate building 44 MJ015 REA additional duct demo $75,643
Supplemental Agreement for work within scope A00010 · Renovate building 44 MJ022 install coaxial cable $17,447
Supplemental Agreement for work within scope A00009 · Renovate building 44 MJ018 add access door $12,721
Supplemental Agreement for work within scope A00008 · Renovate building 44 MJ020 exit access during stair construction $118,928
Supplemental Agreement for work within scope A00007 · Renovate building 44 MJ021 flooring and corridor floor $179,498
Supplemental Agreement for work within scope A00006 · Renovate building 44 MJ012 AV make ready 2ND & 3RD FL $300,500
Supplemental Agreement for work within scope A00005 · Renovate building 44 MJ013 reconfigure AHU $84,418
Change Order P00007 · Modification to revisee piers MJ016 $645,442
Supplemental Agreement for work within scope A00004 · Renovate building 44 MJ011 mechanical unforeseen $179,097
Change Order P00006 · Incorporate the clause 52.204-25, prohibition of contracting for certain telecommunications and video surveillance services or equipment (august 2020) in the… $0
Change Order P00005 · Renovate building 44, FF & E purchase 2ND & 3RD floors delivery date: 22-AUG-2020 $720,052
Other Administrative Action P00004 · Admin MOD to correct funding of options 1 & option 3, for the purchase of FF & E $0
Supplemental Agreement for work within scope A00003 · MJ005, structural discoveries MJ008, window discovery MJ009, replace discovered wooden floor $374,436
Supplemental Agreement for work within scope A00002 · Renovate building 44 MJ003 discoveries wood- concrete deck $64,691
Supplemental Agreement for work within scope A00001 · Renovate building 44 MJ002 demolition discoveries $23,756
Exercise an Option P00003 · The purpose of this modification is to exercise options 01 and 03 clns 0003 and 0005. $846,500
Other Administrative Action P00002 · Modification to correct due date for renovation of building 44 $0
Other Administrative Action P00001 · Extend the period of performance through 22 march 2020 for renovations of bldg 44, joint base SAN antonio, fort SAM houston, SAN antonio TX $0
Original award $9,515,500
Show all 28

About this award

This is a definitive contract awarded by the Department of the Army Corps of Engineers Engineering District Fort Worth to K-W Construction, Inc. (K-W) for the renovation of Building 44 at Fort Sam Houston in San Antonio, Texas. The contract has a firm-fixed price of $13,993,348.68 and a completion date of March 10, 2023. The contract was set aside for small businesses.

The renovation project includes general space planning, hazardous material abatement, new interior finishes, life safety code compliance, new fire protection systems, elevator repairs, and the installation of new building systems. The work is being delivered in two separate design packages, one for the second floor and one for the third floor. The project was originally posted as a pre-solicitation with a total small business set-aside, and bids were due on August 20, 2018. The contract was awarded to K-W on September 30, 2018.

Quick answers

Who was awarded contract W9126G18C0100?

W9126G18C0100 was awarded to K-W Construction, Inc. by ENDIST Fort Worth (US Army Corps of Engineers) on September 30, 2018.

How much is contract W9126G18C0100 worth?

The government has obligated $13,993,349 on W9126G18C0100.

Was contract W9126G18C0100 competed?

The extent of competition for W9126G18C0100 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award