Fort polk barracks and central energy plants

Ended Definitive Contract Awarded Last action

Contract number
W9126G08C0070
Awardee
Awarding agency
Obligated
$213,398,592

Award facts

Opportunity
Contract value 86% obligated
  • $213,398,591.63 Current, with exercised options
  • $247,755,991.63 Potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y199 Construct/Misc Bldgs
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Johnson South, LA, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00081 · Volar barracks and CEP renovations - modification for ERU filters and bldg 2268 site work $81,706
Change Order P00080 · Volar barracks and CEP renovations - modification to delete base failure repairs and add solar parking lights at 2279. $0
Change Order P00079 · Renovate volar barracks and ceps - modification for solar lighting at building 2278 parking lot and access road. $0
Change Order P00078 · Renovations to volar barracks & CEP's - modification for solar lighting at barracks 293 and CEP attic access louvers $87,529
Change Order P00077 · FY08 volar barracks & CEP renovations - modification to reduce base failure repairs. -$79,559
Other Administrative Action P00076 · MOD to recognize contractors change of name $0
Change Order P00075 · Volar barracks and CEP renovations - modification for 2-day weather time extension. $0
Change Order P00074 · FY08 volar barracks & CEP renovations - modification for government delays due to privatized electric utility provider $492,572
Change Order P00073 · Volar barracks and CEP renovations - modification for misc changes - handrails and guardrails, recreation area screen wall, block retaining wall deletion and PH… -$72,668
Change Order P00072 · Bldgs 1628 & 2271 CEP roofs $862,901
Change Order P00071 · Deletion of asphalt mill -$1,382,731
Change Order P00070 · Volar barracks & CEP renovations - modification for soloar lights at barracks 293 $61,410
Change Order P00069 · Volar barracks and CEP renovations - modification to replace roof on CEP 1941. $264,754
Change Order P00068 · Volar barracks and CEP renovations - modification to delete asphalt mill/overlayment -$137,880
Change Order P00067 · Volar barracks & CEP renovations - modification for misc changes - CEP control panel, PH III barracks wall chase fill-INS, 1631 & 1628 roofs $111,771
Definitize Change Order P00066 · This modification is to definitize the estimated quantities for the phase 2, area C4 design $0
Change Order P00065 · Volar barracks & CEP renovations - modification for additional asbestos abatement building 1950 $248,306
Change Order P00064 · Volar barracks and CEP renovaitons - modificaiton for additional abatement in bldg 1635 $112,496
Change Order P00063 · Renovate barracks & CEP - modification to delete asphalt mill and overlay of parking areas -$475,520
Change Order P00062 · Volar barracks & CEP renovations - modification to key card access system $177,856
Change Order P00061 · Volar barracks & ceps - modification for barracks 1945 ACM caulking abatement. $57,495
Change Order P00060 · Volar barracks and CEP renovations - modification for telecommunication changes $98,010
Change Order P00059 · Volar barracks and CEP renovations - modification to decrease structural wall repairs for phase III buildings -$367,427
Other Administrative Action P00058 · Added trafficking clause $0
Change Order P00057 · Volar barracks & CEP renovations - modification for removal of ACM pipe insulation from bldg 1948. $32,106
Change Order P00056 · Fort polk volar barracks & CEP renovations - modification to delete requirement for abatement and disposal of bldg 1631 exterior caulking as ACM. -$33,117
Change Order P00055 · Fort polk volar barracks and CEP renovations- modification to test/remove/dispose of contaiminated soils under barracks 1950. $96,806
Change Order P00054 · Renovations to barracks & CEP's --modification for removal/disposal of unsuitable soil bldg 2279 retaining wall $31,447
Change Order P00053 · Barracks & CEP renovations - modification for PH II structural wall repairs -$229,562
Change Order P00052 · Renovations to barracks & CEP's - modification for phase III barracks downspouts $779,651
Change Order P00051 · Renovate barracks & ceps - modification for HVAC equip auto dialer and sitework $397,193
Change Order P00050 · Volar barracks & CEP renovations - modification for phase III barracks exterior wall system & additional abatement, and barracks 2278 & 2279 parking areas $3,953,798
Change Order P00049 · Renovations to barracks & CEP - modification -abandon underground HVAC pipe associated with CEP's 2271, 1628 & 1941 -$200,778
Change Order P00048 · Modification for misc changes - chase walls and asbestos free labeling $77,240
Change Order P00047 · Fort polk volar barracks & CEP renovations - phase i FCU thermostats and mass notification speakers $88,048
Change Order P00046 · FT polk volar barracks & CEP renovations ---phase II barracks 2274 and 2386 attach gutters to existing storm sewer system. $201,326
Change Order P00045 · Barracks bldg 293 - parking area and telecom/data changes $217,216
Other Administrative Action P00044 · Modification to W9126G-08-c-0070-P00043 to correct the contractor name from walton construction company, LLC to walton construction - a COR company. All other… $0
Change Order P00043 · Changes to the scope of work to install VCT in lieu of polished concrete floors. $65,925
Change Order P00042 · Phase i asphalt milling/overlayment credit -$36,447
Change Order P00041 · Barracks & CEP renovations - MOD - barracks 2279 removal & disposal of brick veneer $45,103
Change Order P00040 · Volar barracks and CEP renovations --modification bldg 2271 removal of ACM water line and replace with new water line $57,459
Change Order P00039 · Renovate barracks & CEP's ---weather time exension march 2010 - february 2011 $0
Change Order P00038 · Arhoc barracks bldgs 293, 2278 & 2279 - VCT floor tile $286,115
Change Order P00037 · Barracks bldgs 2278 & 2279 exterior wall systems $437,819
Change Order P00036 · Buildings 2278 & 2279 - remove unknow ACM $0
Other Administrative Action P00035 · Administrative change to correct clin numbering on previous modification P00034. $0
Change Order P00034 · Barracks bldg 2274 exterior wall system $496,871
Change Order P00033 · FT polk volar barracks and CEP renovations --barracks 2274 ACM abatement $116,091
Change Order P00032 · Building 2386 exterior wall system $376,804
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Quick answers

Who was awarded contract W9126G08C0070?

W9126G08C0070 was awarded to Walton Construction Company, L by ENDIST Fort Worth (US Army Corps of Engineers) on September 30, 2008.

How much is contract W9126G08C0070 worth?

The government has obligated $213,398,592 on W9126G08C0070. Its potential value, with all options, is $247,755,992.

Was contract W9126G08C0070 competed?

The extent of competition for W9126G08C0070 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award