The sacramento weir widening will reduce water surface elevation in sacramento river and allow water to flow into the yolo bypass system. Project consists of construction of a passive weir, levee…
Active Definitive Contract Awarded Last action
- Contract number
- W9123823C0014
- Awardee
-
Granite Construction Company UEI VAYJNMM2KBE5 Part of Granite Construction Company Guam
- Awarding agency
-
ENDIST Sacramento
US Army Corps of Engineers, Department of Defense
- Obligated
- $199,873,797
Award facts
- Opportunity
-
- American River Common Features 2016, Sacramento Weir Widening Pre-Solicitation · W9123823B0005 · Posted Jan 11, 2023
- Contract value 84% obligated
- $239,133,774.47 Current and potential, with all options
- Completion date 98% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Broderick, CA 95605, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $4,000,000 | |
| Supplemental Agreement for work within scope | $658,962 | |
| Supplemental Agreement for work within scope | $85,461 | |
| Supplemental Agreement for work within scope | $7,000,000 | |
| Definitize Change Order | $187,168 | |
| Supplemental Agreement for work within scope | $15,639 | |
| Supplemental Agreement for work within scope | $3,500,000 | |
| Supplemental Agreement for work within scope | $150,863 | |
| Supplemental Agreement for work within scope | $1,578,701 | |
| Supplemental Agreement for work within scope | -$223 | |
| Supplemental Agreement for work within scope | $4,000,000 | |
| Supplemental Agreement for work within scope | $121,320 | |
| Supplemental Agreement for work within scope | $9,232 | |
| Supplemental Agreement for work within scope | $299,241 | |
| Supplemental Agreement for work within scope | $53,685 | |
| Supplemental Agreement for work within scope | $150,000 | |
| Change Order | $600,000 | |
| Change Order | $51,000 | |
| Supplemental Agreement for work within scope | $51,485 | |
| Supplemental Agreement for work within scope | $243,565 | |
| Supplemental Agreement for work within scope | $9,770 | |
| Supplemental Agreement for work within scope | $379,490 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $196,563 | |
| Supplemental Agreement for work within scope | $174,986 | |
| Supplemental Agreement for work within scope | $162,601 | |
| Supplemental Agreement for work within scope | $243,626 | |
| Supplemental Agreement for work within scope | $262,613 | |
| Supplemental Agreement for work within scope | $33,248 | |
| Supplemental Agreement for work within scope | $40,504 | |
| Supplemental Agreement for work within scope | $370,148 | |
| Supplemental Agreement for work within scope | $213,304 | |
| Supplemental Agreement for work within scope | $292,040 | |
| Supplemental Agreement for work within scope | $583,000 | |
| Supplemental Agreement for work within scope | $53,254 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $800,000 | |
| Supplemental Agreement for work within scope | $49,104 | |
| Supplemental Agreement for work within scope | $202,600 | |
| Supplemental Agreement for work within scope | $43,252 | |
| Supplemental Agreement for work within scope | $59,195 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Original award | $172,948,401 |
Show all 44
About this award
The U.S. Army Corps of Engineers Sacramento District awarded a $202.4 million definitive contract to Granite Construction Company for the Sacramento Weir Widening project on June 1, 2023, completing December 2, 2026, on a firm fixed-price basis with no set-aside.
The project constructs a passive weir, levee setback, fish passage control facilities, and supporting infrastructure to reduce water surface elevation in the Sacramento River and route flow into the Yolo Bypass System. Scope includes a 1,500-foot road bridge, 1,450-foot passive weir, 2,500-foot levee, drainage infrastructure, and erosion protection along 4,000 feet of new county roads. Place of performance is Broderick, California. The originating solicitation was posted January 11, 2023, as a design-build invitation for bids due March 17, 2023. Work is classified under NAICS 237990 (Other Heavy and Civil Engineering Construction) and PSC Y1PZ (non-building construction).
Description
The sacramento weir widening will reduce water surface elevation in sacramento river and allow water to flow into the yolo bypass system. Project consists of construction of a passive weir, levee setback, fish passage control among others.
Quick answers
Who was awarded contract W9123823C0014?
W9123823C0014 was awarded to Granite Construction Company by ENDIST Sacramento (US Army Corps of Engineers) on June 1, 2023.
How much is contract W9123823C0014 worth?
The government has obligated $199,873,797 on W9123823C0014. Its current value, with exercised options, is $239,133,774.
Was contract W9123823C0014 competed?
The extent of competition for W9123823C0014 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award