Folsom main, left & right wing dams

Active Definitive Contract Awarded Last action

Contract number
W9123823C0010
Awardee
Awarding agency
Obligated
$125,723,140

Award facts

Opportunity
Contract value 92% obligated
  • $137,174,694.13 Current, with exercised options
  • $137,274,694.13 Potential, with all options
Completion date 84% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Folsom, CA 95630, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00034 · Reference no. R00054 gate seal water system (gate 8)contract for DAM raise: main DAM gates, LWD, RWD at sacramento, casee page 2. $23,687
Change Order A00033 · Reference no. R00054 $20,000
Exercise an Option P00018 $184,960
Supplemental Agreement for work within scope P00017 $103,659
Supplemental Agreement for work within scope A00032 $354,087
Supplemental Agreement for work within scope A00031 · Reference no. R00050 $191,877
Supplemental Agreement for work within scope A00030 · Reference no. R00049 $88,000
Change Order P00016 $495,000
Supplemental Agreement for work within scope A00029 $200,335
Change Order P00015 $460,000
Definitize Change Order P00014 $809,744
Change Order P00013 $375,324
Change Order A00028 $30,000
Supplemental Agreement for work within scope A00027 $211,753
Supplemental Agreement for work within scope A00026 $100,000
Other Administrative Action P00012 $100,000
Supplemental Agreement for work within scope P00011 $609,957
Supplemental Agreement for work within scope A00025 $75,000
Supplemental Agreement for work within scope A00024 $221,398
Supplemental Agreement for work within scope A00023 $200,000
Supplemental Agreement for work within scope A00022 $138,557
Other Administrative Action P00010 $0
Supplemental Agreement for work within scope A00021 $200,000
Supplemental Agreement for work within scope P00009 $1,350,454
Supplemental Agreement for work within scope P00008 $0
Supplemental Agreement for work within scope A00020 $239,531
Supplemental Agreement for work within scope A00019 $75,000
Supplemental Agreement for work within scope A00018 $75,131
Supplemental Agreement for work within scope A00017 · Folsom main, left & right wing dams pier 8 guide beam seal CD44-1 R24/A17 $125,000
Supplemental Agreement for work within scope P00007 $814,329
Supplemental Agreement for work within scope A00016 $59,025
Definitize Change Order A00015 $19,546
Supplemental Agreement for work within scope P00006 · Folsom main, left & right wing dams, R20/P6/CD039-1 corbel modification - dry work $500,000
Supplemental Agreement for work within scope A00014 · Folsom main, left & right wing dams, R19/A14/CD037 remove stoplogs (gate 8) $101,132
Supplemental Agreement for work within scope A00013 · Folsom main, left & right wing dams, R18/A13 CD024 provide guard house for 2ND access & CD026 hardpoint between RWD & MD. $297,889
Other Administrative Action P00005 · Folsom main, left & right wing dams, R17/P5/CD22 modified POC schedule and SS 01 14 30. $0
Supplemental Agreement for work within scope A00012 · Folsom main, left & right wing dams, R16/A12/CD033-1 stop log seal modification. $200,000
Supplemental Agreement for work within scope A00011 · CD034 stoplogs guide beams $168,605
Other Administrative Action A00010 · Folsom main, left & right wing dams A00010 R00014 CD028, administrative modification, lead abatement independent clin. $0
Supplemental Agreement for work within scope A00009 · Folsom main, left & right wing dams CD011 R00013 A00009 stoplog testing prior to demolition $168,280
Supplemental Agreement for work within scope A00008 · Folsom main, left & right wing dams CD019 R00012 A00008, provide guard shack and power LWD $365,781
Supplemental Agreement for work within scope A00007 · CD004 pier demolition corrections and CD017 correct hoist platform installation $231,405
Supplemental Agreement for work within scope A00006 · Folsom main, left & right wing dams unilateral modification CD023-1 excavate and locate grout columns $50,000
Supplemental Agreement for work within scope A00005 · Folsom main, left & right wing dams VF003 R00009 A00005 tainter gate rib support brace plate. $355,763
Supplemental Agreement for work within scope A00004 · Folsom main, left & right wing dams CD014 R00008 A00004 create zone 1 fenced-in security area. $193,774
Supplemental Agreement for work within scope P00004 · Folsom main, left & right wing dams. This CD015 unilateral modification is composed of two parts: CD015-1 and CD015-2. The total cost for these two parts… $150,000
Supplemental Agreement for work within scope P00003 · Folsom main, left & right wing dams R00006 A00004 bushing for trunnion, gate CON., rollers (unilateral MOD). $250,000
Supplemental Agreement for work within scope A00003 · Folsom main, left & right wing dams R00005 A00003 CD012 drawing corrections and VF004 generator power in lieu of local utility. $198,361
Supplemental Agreement for work within scope A00002 · Folsom main, left & right wing dams, VF001 VF002 R00002 A00002 $235,905
Supplemental Agreement for work within scope A00001 · Folsom main, left & right wing dams - R00001/A00001 $144,477
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The U.S. Army Corps of Engineers Engineering District Sacramento awarded a $125.9 million firm fixed-price definitive contract to Folsom Dam Constructors for the Folsom Main, Left Wing, and Right Wing Dams raise project on March 30, 2023, with no set-aside applied.

The originating solicitation (W91238-22-R-0055) seeks to raise the elevations of the three dams to increase flood protection for communities along the American River in California. Work includes raising portions of the dams, installing reinforced concrete floodwalls, and modifying Tainter gates and anchorage at the main dam, with specifications requiring construction sequencing, environmental protocols, and coordination with the U.S. Bureau of Reclamation. Place of performance is Folsom, CA. Ultimate completion is scheduled for July 6, 2027.

Quick answers

Who was awarded contract W9123823C0010?

W9123823C0010 was awarded to Folsom Dam Constructors by ENDIST Sacramento (US Army Corps of Engineers) on March 30, 2023.

How much is contract W9123823C0010 worth?

The government has obligated $125,723,140 on W9123823C0010. Its current value, with exercised options, is $137,174,694. Its potential value, with all options, is $137,274,694.

Was contract W9123823C0010 competed?

The extent of competition for W9123823C0010 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award