Sutter basin frmp levee repairs cypress AVE to tudor RD

Ended Definitive Contract Awarded Last action

Contract number
W9123819C0008
Awardee
Awarding agency
Obligated
$39,350,868

Award facts

Opportunity
Contract value 100% obligated
$39,350,867.50 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Yuba City, CA, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00020 · Sutter levee repair cypress tudor 2019 $161,225
Supplemental Agreement for work within scope A00019 · Sutter levee repair cypress tudor 2019 VF023 sutter basin gate riser credit -$5,414
Supplemental Agreement for work within scope P00007 · Sutter levee repair cypress tudor 2019 VF022 final adjustment to estimated quantities $566,941
Supplemental Agreement for work within scope A00018 · Sutter levee repair cypress tudor 2019 VF021 $5,743
Supplemental Agreement for work within scope A00017 · Sutter levee repair cypress tudor 2019 VF020 $59,922
Supplemental Agreement for work within scope A00016 · Sutter levee repair cypress tudor 2019. VF019 $39,779
Supplemental Agreement for work within scope A00015 · Sutter levee repair cypress tudor 2019. VF018 $143,041
Supplemental Agreement for work within scope A00014 · Sutter levee repair cypress tudor 2019. VF017. $61,371
Supplemental Agreement for work within scope A00013 · Sutter levee repair cypress tudor 2019. VF016. $42,174
Supplemental Agreement for work within scope P00006 · Sutter levee repair cypress tudor 2019. VF010 rapid recovery and levee degrade. $588,709
Definitize Change Order P00005 · Sutter levee repair cypress tudor 2019. VF001-2 tribal monitoring rates part 2. $246,059
Supplemental Agreement for work within scope A00012 · Sutter levee repair cypress tudor 2019. VF015. $282,884
Supplemental Agreement for work within scope A00011 · Sutter levee repair cypress tudor 2019. VF014. $50,603
Supplemental Agreement for work within scope A00010 · Sutter levee repair cypress tudor 2019. VF013. $26,095
Supplemental Agreement for work within scope A00009 · Sutter levee repair cypress tudor 2019. VF012. $43,803
Definitize Change Order A00008 · Sutter levee repair cypress tudor 2019. Monitoring of levee rebuild part 2. $220,052
Definitize Change Order A00007 · Sutter levee repair cypress tudor 2019. VF004 2 add 2ND shift part 2. $299,440
Supplemental Agreement for work within scope A00006 · Sutter levee repair cypress tudor 2019. VF002 2 rapid recovery MOD part 2. $167,588
Supplemental Agreement for work within scope A00005 · Sutter levee repair cypress tudor 2019 MOD A00001 VF007 and VF009. -$56,786
Supplemental Agreement for work within scope A00004 · Reference no R00009 VF008 (cultural soil burial) $58,500
Supplemental Agreement for work within scope A00003 · Sutter levee repair cypress tudor 2019 $54,690
Supplemental Agreement for work within scope A00002 · MOD A00002-k-rails, gate, and fence $51,941
Change Order A00001 · REF no. R00006 (VF005-1) - monitoring of levee rebuild, part 1 $100,000
Change Order P00004 · 004-1 add second shift: heading GL1- part 1 $200,000
Change Order P00003 · P00003 VF002-1 rapid recovery: arch & tribal monitoring. Part i modification. $93,000
Change Order P00002 · Unilateral modification - section 01 57 19 $875,000
Supplemental Agreement for work within scope P00001 · Sutter levee repair cypress - tudor 2019; NTP modification $0
Original award $34,974,509
Show all 28

About this award

This is a $39,350,867.50 Firm Fixed Price contract awarded by the U.S. Army Corps of Engineers Sacramento District to Forgen LLC, a geotechnical and environmental construction company, for the Sutter Basin Flood Risk Management Project (FRMP) Levee Repairs from Cypress Avenue to Tudor Road. The contract was not set aside for any specific business type. The work includes levee repairs and stabilization, slurry wall construction, and environmental monitoring services provided by subcontractors Crawford & Associates, Construction Testing Services, GEI Consultants, Selby's Soil Erosion Control, Mcguire & Hester, Frank Medina General Engineering, Raito, and Get 'Er Done. This contract supports the U.S. Army Corps of Engineers' civil works program for flood protection infrastructure.

Quick answers

Who was awarded contract W9123819C0008?

W9123819C0008 was awarded to Forgen LLC by ENDIST Sacramento (US Army Corps of Engineers) on February 20, 2019.

How much is contract W9123819C0008 worth?

The government has obligated $39,350,868 on W9123819C0008.

Was contract W9123819C0008 competed?

The extent of competition for W9123819C0008 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award