The marysville ring levee (MRL) project is located in marysville, california. The purpose of the project is to reduce flood risk to the urban area of marysville. The phase 2A north project is situated…

Ended Definitive Contract Awarded Last action

Contract number
W9123817C0048
Awardee
Awarding agency
Obligated
$3,570,289

Award facts

Opportunity
Contract value 100% obligated
$3,570,289.12 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Marysville, CA, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00009 · Marysville ring levee (MRL) 2A north, marysville, CA the purpose of this modification is to incorporate R00010/CD012 removal of fiber rolls no time $10,000
Supplemental Agreement for work within scope P00004 · Change CD011/R00009 final quantities modification -$399,029
Supplemental Agreement for work within scope A00007 · Change CD009/R00008 bike path/patrol road change a. Scope of work CD009 bike path/patrol road change the contractor shall provide all labor, materials, and… $1,601
Supplemental Agreement for work within scope A00005 · Change CD008/R00007 grout pocket sleeve install a. Scope of work CD008 grout pocket sleeve install the contractor shall provide all labor, materials and… $1,247
Exercise an Option P00003 · Change CD007/R00006 imported top soil option a. Scope of work CD007 imported top soil option exercise the option for topsoil. B. Change in contract price… $80,712
Exercise an Option P00002 · Change CD006/R00004 standby options a. Scope of work CD006 standby options exercise 2 option days of construction standby due to cultural resources. B. Change… $20,000
Supplemental Agreement for work within scope A00004 · CD004/R00005 change in wall alignment a. Scope of work CD004 change in wall alignment item 1. The contractor shall provide all labor, equipment, and materials… $12,700
Change Order A00003 · Change CD005/R03 cultural $1,500
Other Administrative Action A00002 $0
Other Administrative Action A00001 · Marysville ring levee 2A north the purpose of this modification is to incorporate R00001/CD001 change administrating office. $0
Supplemental Agreement for work within scope P00001 · Establish calendar dates for the period of performance in the base clin and the option clins for marysville ring levee phase 2A north $0
Original award $3,841,558
Show all 12

About this award

The Department of the Army Corps of Engineers Engineering District Sacramento awarded a Firm Fixed Price contract to North Star Great Lakes E & I JV, a Minority Owned Business, Self Certified Small Disadvantaged Business, for the Marysville Ring Levee (MRL) Phase 2A North Project in Marysville, California. The $3,570,289.12 contract is to strengthen the existing levee system by constructing a seepage cutoff wall and embankment modifications to reduce flood risk in the Marysville urban area. The project is set-aside for small businesses. The work includes constructing approximately 1,200 linear feet of a 30-inch thick cutoff wall, removing and replacing a portion of the levee embankment, and related site work and coordination with utility companies.

Description

The marysville ring levee (MRL) project is located in marysville, california. The purpose of the project is to reduce flood risk to the urban area of marysville. The phase 2A north project is situated just north of the 5TH street bridge abutment. The project consists of strengthen the existing levee system from station 195+40 to 208+60, by means of a seepage cutoff wall under the riverside TOE of the levee, and backfilling the excavated levee slope with a portion of the excavated material and imported impervious fill. The cutoff wall is approximately 1200 lineal feet (LF), the depth of the cutoff wall varies from 36 to 38 feet, and a minimum thickness of 30 inches. Additionally, the cutoff wall will tie into an existing cutoff wall near station 195+40. The cutoff wall will be constructed using the open trench. A portion of the waterside embankment will be removed and replaced with a portion of removed material and impervious imported material, with a final slope of 3:1. The embankment removal will encroach on the levee crown road and the bituminous concrete pavement (BC) and aggregate base (AB) will be removed and replaced. An area with stone and concrete rubble on levee embankment will need to be removed as IT lies within the cutoff wall alignments. Erosion control measures will need to be applied to all disturbed areas. Remove and reconstruct approximately 200 feet of the upper portion of the bike trail and safety rail. The project is located adjacent to an active uprr tracks. Safety precautions will need to be taken and access to the construction site will not require crossing the tracks. Coordination with PG & E will be required to address relocation of overhead utilities before excavation of the embankment and during construction of the cutoff wall. Removal and protection of some trees, branches and bushes may be necessary within the temporary construction easement.

Quick answers

Who was awarded contract W9123817C0048?

W9123817C0048 was awarded to North Star Great Lakes E & I JV by ENDIST Sacramento (US Army Corps of Engineers) on September 30, 2017.

How much is contract W9123817C0048 worth?

The government has obligated $3,570,289 on W9123817C0048.

Was contract W9123817C0048 competed?

The extent of competition for W9123817C0048 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award