Water treatment plant lake davis

Ended Definitive Contract Awarded Last action

Contract number
W9123808C0001
Awardee
Awarding agency
Obligated
$5,057,499

Award facts

Opportunity
Contract value 96% obligated
  • $5,057,499.32 Current, with exercised options
  • $5,277,323.32 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Portola, CA 96122, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00003 · Modification adds ICE breaks to the aluminum roofing, increases the exterior wall insulation, and install 4" PVC pipe water line from the pump station located… $45,921
Vendor Address Change A00002 · WTP lake davis; swap out the 20 HP VFD from the finished water transfer pump and install IT in the air compressor bucket. Purchase and install a new 20 HP VFD… $7,200
Supplemental Agreement for work within scope P00012 · WTP lake davis; install the tepid water delivery system to three emergency shower eye wash and chemical feed room wash basin facilities. $20,920
Supplemental Agreement for work within scope P00010 · WTP lake davis; change in depth - carbon valving vault, RFI 34 $15,500
Supplemental Agreement for work within scope P00011 · WTP lake davis; revise the proposed concept temporary rental irrigation discharge system as required by the contract to a permanent irrigation discharge system. $15,776
Supplemental Agreement for work within scope P00009 · WTP lake davis. Change elevation of saddle bases for the filter tanks; increase thickness of equipment pad; increase pad for the filter water tank; remove… $25,830
Supplemental Agreement for work within scope P00007 · WTP lake davis. Increase excavation depth and shoring approximately 5 feet; install a door mechanism that will allow 2 overhead roll up doors; enlarge the… $24,902
Supplemental Agreement for work within scope P00008 · WTP lake davis. Replace 1/2 inch copper pipe and add in its place 1-1/2 inch copper pipe. $9,417
Supplemental Agreement for work within scope P00006 · WTP lake davis. Add a waste pump station with all electrical and mechanical appurtenances. Sump pump requirements and location shall be as described. $24,898
Supplemental Agreement for work within scope P00005 · WTP lake davis, install remote reading power use meter exterior of building; electrical utility specified meter panel type nema 3R six jaw remote reading with… $3,415
Supplemental Agreement for work within scope P00003 · WTP lake davis, replace 2 gate valves and appurtenances at inflow and discharge pipelines attached to 250K gallon storage tank. $22,109
Supplemental Agreement for work within scope P00004 · WTP lake davis, additional 15 calendar days due to weather delays. $0
Supplemental Agreement for work within scope P00002 · Weather delays 12/1/08 to 03/01/09 $0
Supplemental Agreement for work within scope P00001 · WTP lake davis, relocate glrid water line. The contractor shall provide all labor, material and equipment to install the 4" water line underground. Install a… $8,926
Change Order A00001 · WTP lake davis $2,679
Original award $4,830,006
Show all 16

About this award

Engineering/Remediation Resources Group, Inc. (ERRG) was awarded a competitive 8(a) set aside definitive contract by the Department of the Army Corps of Engineers Engineering District Sacramento. With a potential value of $5,277,323.32, this firm fixed price contract is for the Water Treatment Plant Lake Davis project located in Portola, California. Completion is scheduled for August 23, 2009.

As a woman and minority owned small business, ERRG provides environmental remediation and consulting services as a prime contractor. The company holds several indefinite delivery vehicles to provide technical and remediation services to federal agencies on an as-needed basis, such as a $17 million Region 5 CERCLA Environmental Response IDIQ.

Quick answers

Who was awarded contract W9123808C0001?

W9123808C0001 was awarded to Engineering / Remediation Resources Group, Inc. by ENDIST Sacramento (US Army Corps of Engineers) on December 21, 2007.

How much is contract W9123808C0001 worth?

The government has obligated $5,057,499 on W9123808C0001. Its potential value, with all options, is $5,277,323.

Was contract W9123808C0001 competed?

The extent of competition for W9123808C0001 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award