Gate #1 rehabilitation

Ended Definitive Contract Awarded Last action

Contract number
W911WN09C0004
Awardee
Awarding agency
Obligated
$4,474,981

Award facts

Opportunity
Contract value 172% obligated
$2,600,464.08 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Pittsburgh, PA 15222, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00001 $0
Other Administrative Action P00001 · Gate #3 rehabilitation $0
Change Order A00025 -$2,250
Change Order A00025 · Gate #3 rehabilitation $0
Change Order A00024 $9,000
Change Order A00024 $0
Change Order A00023 · Gate #3 rehabilitation $0
Change Order A00023 $0
Change Order A00021 $0
Change Order A00022 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $12,299
Change Order A00021 $41,923
Change Order A00022 $2,418
Change Order A00020 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00020 $0
Change Order A00019 $0
Change Order A00019 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $5,371
Change Order A00018 $0
Change Order A00018 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00017 · Arra::yes::ARA recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $37,057
Change Order A00016 $0
Change Order A00017 $0
Change Order A00016 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $71,739
Change Order A00015 $0
Change Order A00015 $34,193
Change Order A00014 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00014 $86,225
Change Order A00012 $50,154
Change Order A00013 $3,006
Change Order A00013 $36,349
Change Order A00012 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00010 $0
Change Order A00011 $5,369
Change Order A00010 $34,193
Change Order A00011 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00009 $0
Change Order A00009 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00008 $0
Change Order A00007 $19,169
Change Order A00008 · Arra::yes::arra recoveryproject#::1400::RP# berlin crest gate rehabilitation, berlin DAM, berlin center, OH $0
Change Order A00006 $52,003
Change Order A00006 · Arra::yes::arra recoveryproject#::1400::RP# berlin crest gate rehabilitation, berlin DAM, berlin center, OH $0
Change Order A00007 $19,169
Change Order A00005 $0
Change Order A00005 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00004 $16,404
Change Order A00004 · Arra::yes::arra recoveryproject#::1400::RP# gates 3 and 4 rehab painting testing hoist chains, pulleys, pocket wheels, epoxy floor overlay and refurbish hoist… $0
Change Order A00002 $0
Change Order A00001 · Arra::yes::arra recoveryproject#::1400::RP# berlin crest gate rehabilitation, berlin DAM, berlin center, OH $0
Change Order A00003 $171,000
Change Order A00002 · Crest gate rehabilitation, berlin DAM, berlin center, OH $93,000
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This firm fixed price contract in the amount of $2,600,464.08 was awarded by the U.S. Army Corps of Engineers to Hohl Industrial Services Inc., a for-profit small business organization, for the GATE #1 REHABILITATION project in Pittsburgh, Pennsylvania. The contract does not have a set-aside designation. Hohl Industrial Services has been awarded several prior federal contracts by the Army Corps of Engineers to provide metal fabrication, refurbishment, and installation services, including a $496,652 contract for a coffer beam at the Montgomery Locks and Dam and a $161,395 contract for bulkheads at the Mount Morris Dam. This contract appears to be part of the Army Corps of Engineers' Metal Fabrication, Refurbishment, and Installation Multiple Award Task Order Contract (MATOC) vehicle, which has a total potential value of up to $160 million. The ultimate completion date for this contract is October 31, 2011.

Quick answers

Who was awarded contract W911WN09C0004?

W911WN09C0004 was awarded to Hohl Industrial Services Inc. by ENDIST Pittsburgh (US Army Corps of Engineers) on July 10, 2009.

How much is contract W911WN09C0004 worth?

The government has obligated $4,474,981 on W911WN09C0004. Its current value, with exercised options, is $2,600,464.

Was contract W911WN09C0004 competed?

The extent of competition for W911WN09C0004 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award