Change Order
A00077 · Contract 1, charleroi l/d, monongahela river, PA MOD A00077, change DZ, shaft repair final QTY adjustments.
$0
Change Order
P00050 · Charleroi locks, contract 1 modification P00050 issued to add funding to contract line item 3048 for the second (and final) payment of the drilled shaft REA…
$4,650,000
Supplemental Agreement for work within scope
P00049 · Charleroi locks, contract 1 modification P00049 issued to memorialize REA settelement for the demonstration and repair of non-cofferbox drilled shaft anomalies.
$3,000,000
Change Order
A00076 · Change DW, structural repair of drilled shafts, charleroi locks, monessen, PA
$244,488
Change Order
P00048 · Charleroi locks, contract 1 - MOD P00048 incorporates requirement for drilled shaft exploratory drilling.
$937,327
Other Administrative Action
P00047 · Arra::yes::arra reoveryproject#::010286::RP# modification to finalize quanities in support of the project to construct a riverwall at charleroi locks and DAM,…
-$1,000
Other Administrative Action
P00046 · Contract 1, charleroi l/d, monongahela river, pennsylvania
$1,000
Change Order
P00045 · Arra::yes::arra recoveryproject#::010286:RP# contract 1, charleroi l/d, monongahela river, pennsylvania
-$11,540
Change Order
P00044
-$216,683
Change Order
P00043
$111,307
Change Order
A00075 · Charleroi locks, contract 1
$0
Change Order
A00074
$120,000
Change Order
A00073
$120,000
Change Order
A00072
$0
Other Administrative Action
A00071
$275,689
Other Administrative Action
A00070
$0
Other Administrative Action
P00042 · Arra::yes::arra recoveryproject#::010286::RP# modification to contract 1, charleroi l/d, monongahela river, pennsylvania, cofferbox concrete crack remediation
$203,444
Change Order
P00041 · Arra::yes::arra recovery project#::010286::RP# modification involving delay scheduled concrete placements in the upstream and downstream cofferboxes to permit…
$0
Change Order
A00069 · Arra::yes::arra recovery project#::010286::RP# modification involving exploratory core drilling of non-cofferbox corner drilled shafts in support of the project…
$64,968
Supplemental Agreement for work within scope
P00040 · Arra::yes::arra recovery project#::10286::RP#1028610286 funding for next phase of third party expert services to develop a sampling plan and repair procedure…
$4,680
Supplemental Agreement for work within scope
P00039 · Arra::yes::arra recoveryproject#::10286::RP# 10286 third party expert services to develop a sampling plan and repair procedure for the drilling shaft issue at…
$11,300
Change Order
P00038 · Arra::yes arra recovery project:#::010286::RP# modification to finalize quantites in support of the project to construct a river wall at charleroi locks and…
$1,291,174
Change Order
A00068 · Arra::yes::arra recovery project#::010286::RP# modification involving PH facility surge protection in support of the project to construct a river wall at…
$6,485
Change Order
A00067 · Arra::yes::arra recoveryproject#::010286::RP# modification involving non-cofferbox shaft core drilling in support of the project to construct a river wall at…
$98,016
Change Order
A00066 · Arra::yes::arra recoveryproject#::010286::RP# modification to switch to armstrong cement in support of the project to construct a river wall at charleroi…
$79,060
Change Order
A00065 · Arra::yes::arra recoveryproject#::010286::RP# modification to install expansion material and waterstop in support of the project to construct a river wall at…
$36,066
Change Order
A00063 · Recoveryproject#::10286::RP# construct river wall at charleroi lock and DAM number 4 monongahela river, PA
$9,083
Change Order
A00062 · Charleroi locks, contract 1
$0
Change Order
A00064 · Recoveryproject#::010286::RP# modification to install a water sump in support of the river wall construction contract at charleroi locks and DAM, monongahela…
$80,600
Supplemental Agreement for work within scope
P00037 · Recovery project#::010286:: modification to provide and deliver concrete, to inlcude purchase of a concrete conveyor system in support of the upper and lower…
$7,317,340
Change Order
A00061
$60,000
Change Order
A00060
$52,970
Change Order
A00059
$100,000
Change Order
A00058 · Recoveryproject#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, modification to compensate the contractor for evacuation and unwatering the…
$60,000
Change Order
A00057 · Charleroi locks, contract 1
$0
Change Order
A00056 · Recoveryproject#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, grout tubes installation at R12 and R32 in support of the construction of the…
$19,300
Change Order
A00055 · Recoveryproject#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, construct baffles/install float curtain in support of the construction of the…
$19,000
Change Order
A00054 · Recoveryproject#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, additional materials for upstream cofferbox in support of the construction of…
$63,600
Change Order
A00053 · Recoveryproject#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, downstream cofferbox sealing in support of the construction of the charleroi…
$73,000
Change Order
A00052 · Recoveryproject#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, change to downstream cofferbox strut in support of the construction of the…
$72,000
Change Order
A00051 · Locks and DAM 2, 3, and 4, monongahela river, PA, adverse weather modification
$0
Change Order
A00050 · Recovery project#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, revisions to R18/R19 waterstop in support of the construction of the…
$9,300
Change Order
A00047 · Charleroi locks, contract 1
$0
Change Order
A00049 · Recovery project#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, repair to standpipe at victory hollow in support of the construction of the…
$2,800
Change Order
A00048 · Recovery project#::010286::RP# locks and DAM 2, 3, and 4, monongahela river, PA, victory hollow sediment pond cleaning in support of the construction of the…
$8,500
Supplemental Agreement for work within scope
P00034
$0
Funding Only Action
P00035 · Charleroi locks, contract 1
-$8,590,804
Funding Only Action
P00036 · Rercovery balance of funding for charleroi locks, contract 1 arra::yes::arra
W911WN04C0003 was awarded to Trumbull Corporation And Brayman Construction Corporation, A Joint Venture by ENDIST Pittsburgh (US Army Corps of Engineers) on September 27, 2004.
How much is contract W911WN04C0003 worth?
The government has obligated $119,369,572 on W911WN04C0003.
Was contract W911WN04C0003 competed?
The extent of competition for W911WN04C0003 was full and open competition. The government received 3 offers.