Construct missile field 4 mechanical electrical bldg at fort greely, alaska

Ended Definitive Contract Awarded Last action

Contract number
W911KB18C0030
Awardee
Awarding agency
Obligated
$33,724,100

Award facts

Contract value 100% obligated
  • $33,724,100.00 Current, with exercised options
  • $33,746,100.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Fort Greely, AK 99731, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00043 · REA for ATS 405 $29,519
Supplemental Agreement for work within scope P00042 · Provide ATS capabilities for MEB4 $850,799
Supplemental Agreement for work within scope P00041 · Incremental commissioning $140,010
Supplemental Agreement for work within scope P00040 · Balance of CX tab $14,116
Supplemental Agreement for work within scope P00039 · Low voltage CT's $290,938
Supplemental Agreement for work within scope P00038 · High voltage CTS $226,280
Change Order P00037 · Low voltage CT's $50,000
Supplemental Agreement for work within scope P00036 · Demodulated timing signal modifications $24,245
Supplemental Agreement for work within scope P00035 · FEP/EBS locations & quantities $3,160
Supplemental Agreement for work within scope P00034 · S-011 & S-012 pipe shoe guide removal $7,383
Change Order P00033 · Provide ATS capability $1,000,000
Supplemental Agreement for work within scope P00032 · 0041 MEB IV humidifier alterations $99,648
Supplemental Agreement for work within scope P00031 $206,182
Change Order P00030 $79,894
Change Order P00029 $11,550
Change Order P00028 $5,216
Change Order P00027 $65,513
Change Order P00026 · Construct mechanical electrical bldg $1,150,000
Supplemental Agreement for work within scope P00025 · Construct mechanical electrical bldg, modification no. P00025, change item no. 0033 (add a surge arrestor for DP-9461001) $3,279
Change Order P00024 · Construct mechanical electrical bldg, modification no. P00024, change item no. 0027-1 (provide ATS capability MEB4 part-1) $350,000
Supplemental Agreement for work within scope P00023 · Construct mechanical electrical bldg, modification no. P00023, change item no. 0031 (MF4 evacuation and SIP) $0
Supplemental Agreement for work within scope P00022 · Construct mechanical electrical bldg, modification no. P00022, change item no. 0030 (modify blast damper embeds to fit reinforcement) $5,968
Supplemental Agreement for work within scope P00021 · Construct mechanical electrical bldg, modification no. P00021, change item no. 0026 (modify MEB2 for power to MEB4 (FCP-1418)) $40,155
Supplemental Agreement for work within scope P00020 · Construct mechanical electrical bldg, modification no. P00020, change item no. 0028 (alternate certification of hemp filters) $32,910
Supplemental Agreement for work within scope P00019 · Construct mechanical electrical bldg, modification no. P00019, change item no. 0029 (shared partnering cost) $3,081
Supplemental Agreement for work within scope P00018 · Construct mechanical electrical bldg, modification P00018, change item no. 0025 (damper specification changes). $20,640
Supplemental Agreement for work within scope P00017 · Construct mechanical electrical bldg, modification no. P00017, change item no. 0024-2 (provide geofoam over utilidor 403-part 2) $32,652
Supplemental Agreement for work within scope P00016 · Construct mechanical electrical bldg, modification no. P00016 change item NOS. 0014 (lighting control & emergency egress) and 0023 (adjust steel reinforcement… $2,150
Change Order P00015 · Construct mechanical electrical bldg, modification no. P00015, change item no. 0024-1 (provide geofoam over utilidor 403-part 1) $5,000
Supplemental Agreement for work within scope P00014 · Construct mechanical electrical bldg, modification no. P00014, change item no. 0021 (HAT channel anchorage) $0
Supplemental Agreement for work within scope P00013 · Construct mechanical electrical bldg, modification no. P00013, change item no. 0012 (revised embeds and wall reinforcement) $53,482
Supplemental Agreement for work within scope P00011 · Construct mechanical electrical bldg, modification no. P00011, change item no. 0016 (utilidor hot water pipe mat'l. $21,944
Supplemental Agreement for work within scope P00012 · Construct mechanical electrical bldg, modification no. P00012, change item no. 0018 (SEQ of operation for chilled water valve) and 0020 (utilidor pipe embed… $5,222
Supplemental Agreement for work within scope P00010 · Construct mechanical electrical bldg, modification no. P00010, change item NOS. 0013 (revise SDB stub-out profile elevations), 0017 (SEQ of operations for demin… -$3,705
Supplemental Agreement for work within scope P00009 · Construct mechanical electrical bldg, modification no. P00009, change item no. 0009 (electrical and telecom revision/clarifca) $26,223
Supplemental Agreement for work within scope P00008 · Construct mechanical electrical bldg, modification no>P00008, change item NOS. 0010 (moist resist paint & revised waterproof and 0015 (seismic isrs for fan… $7,719
Supplemental Agreement for work within scope P00007 · Construct mechanical electrical bldg, modification no. P00007, change item no. 0011 (update transfer grill requirements) $4,805
Supplemental Agreement for work within scope P00006 · Construct mechanical electrical bldg, modification no. P00006, change item no. 0004 - sanitary sewer changes -$1,957
Supplemental Agreement for work within scope P00005 · Construct mechanical electrical bldg, modification no. P00005, CI #S 0005, 0007,&0008 $44,388
Supplemental Agreement for work within scope P00004 · Construct mechanical electrical bldg, modification no, P00004, change item no. 0002 - replace RMF specs $0
Supplemental Agreement for work within scope P00003 · Construct mechanical electrical bldg, modification no. P00003, change item NOS. 0001 (add scms panel, sump pump connect & relay) and 0003 (blast door emerg… $30,691
Change Order P00002 · Construct mechanical electrical bldg $0
Other Administrative Action P00001 · Construct mechanical electrical bldg - MOD to correct clause 52.211-10 to same language as RFP $0
Original award $28,785,000
Show all 44

About this award

This is a $33,746,100 firm-fixed-price definitive contract awarded by the U.S. Army Corps of Engineers, Alaska District to Watterson Construction Co for the construction of the Missile Field 4 Mechanical Electrical Building at Fort Greely, Alaska. The contract has a completion date of September 30, 2021 and did not utilize any set-aside designations. Major subcontractors include Central Environmental Inc., Heritage Rock And Services, LLC, Fullford Electric, Inc., Brice Civil Constructors, Inc., and several other small businesses providing specialized services such as electrical, mechanical, and environmental support. This contract is part of the Army's infrastructure modernization efforts at Fort Greely, a strategic missile defense site operated by the U.S. Army.

Quick answers

Who was awarded contract W911KB18C0030?

W911KB18C0030 was awarded to Watterson Construction Co by ENDIST Alaska (US Army Corps of Engineers) on July 20, 2018.

How much is contract W911KB18C0030 worth?

The government has obligated $33,724,100 on W911KB18C0030. Its potential value, with all options, is $33,746,100.

Was contract W911KB18C0030 competed?

The extent of competition for W911KB18C0030 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award