Willamette national cemetery two phase design- build
Ended Definitive Contract Awarded Last action
- Contract number
- VA101F17C2881
- Awardee
-
Kiewit Infrastructure West CO. UEI YSNNL4FGAQ53 Part of Peter Kiewit Sons Inc.
- Awarding agency
-
VA Office of Construction and Facilities Management
Headquarters, Department of Veterans Affairs
- Obligated
- $37,687,510
Award facts
- Opportunity
-
- VA10116R0147 Solicitation number
- Willamette National Cemetery Design-Build Phase I - Pre-Proposal Conference/Site Visit Presentation and Attendees List Award Notice · Posted Jul 14, 2016
- Willamette National Cemetery - Two-Phase Design-Build Construction Award Award Notice · Posted Jun 30, 2016
- Contract value 100% obligated
- $37,687,510.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 4 offers Two Step
- Pricing
- Firm Fixed Price
- Place of performance
- Happy Valley, OR 97086, USA
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Additional Work (new agreement, FAR part 6 applies) | $45,652 | |
| Additional Work (new agreement, FAR part 6 applies) | $89,589 | |
| Additional Work (new agreement, FAR part 6 applies) | $25,388 | |
| Additional Work (new agreement, FAR part 6 applies) | $31,433 | |
| Additional Work (new agreement, FAR part 6 applies) | $30,179 | |
| Additional Work (new agreement, FAR part 6 applies) | $80,108 | |
| Supplemental Agreement for work within scope | $45,475 | |
| Supplemental Agreement for work within scope | $450,101 | |
| Supplemental Agreement for work within scope | $85,027 | |
| Supplemental Agreement for work within scope | $2,453 | |
| Supplemental Agreement for work within scope | $39,630 | |
| Supplemental Agreement for work within scope | $27,561 | |
| Supplemental Agreement for work within scope | $27,603 | |
| Supplemental Agreement for work within scope | $120,610 | |
| Supplemental Agreement for work within scope | $930,116 | |
| Supplemental Agreement for work within scope | $21,779 | |
| Supplemental Agreement for work within scope | $41,307 | |
| Supplemental Agreement for work within scope | $53,478 | |
| Change Order | $39,772 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $36,850 | |
| Supplemental Agreement for work within scope | $9,189 | |
| Supplemental Agreement for work within scope | $28,915 | |
| Supplemental Agreement for work within scope | $125,369 | |
| Supplemental Agreement for work within scope | $6,132 | |
| Supplemental Agreement for work within scope | $1,510 | |
| Supplemental Agreement for work within scope | $65,387 | |
| Supplemental Agreement for work within scope | $93,374 | |
| Supplemental Agreement for work within scope | $616,300 | |
| Supplemental Agreement for work within scope | $87,640 | |
| Other Administrative Action | $25,822 | |
| Other Administrative Action | $3,206,761 | |
| Other Administrative Action | $0 | |
| Original award | $31,197,000 |
Show all 36
About this award
This is a $37,687,510.00 firm fixed price definitive contract awarded by the U.S. Department of Veterans Affairs (VA) Office of Construction and Facilities Management to Kiewit Infrastructure West Co. for a two-phase design-build project at the Willamette National Cemetery in Portland, Oregon. The contract does not have a set-aside designation. Kiewit Infrastructure West Co. is a subsidiary of the larger construction and engineering firm Peter Kiewit Sons Inc., which regularly performs federal infrastructure and construction contracts as both a prime and subcontractor. The project scope involves the design and construction of improvements at the Willamette National Cemetery, a VA-operated facility. The contract has an ultimate completion date of April 1, 2022.
Quick answers
Who was awarded contract VA101F17C2881?
VA101F17C2881 was awarded to Kiewit Infrastructure West CO. by VA Office of Construction and Facilities Management (Headquarters) on March 6, 2017.
How much is contract VA101F17C2881 worth?
The government has obligated $37,687,510 on VA101F17C2881.
Was contract VA101F17C2881 competed?
The extent of competition for VA101F17C2881 was full and open competition. The government received 4 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award