Willamette national cemetery two phase design- build

Ended Definitive Contract Awarded Last action

Contract number
VA101F17C2881
Awardee
Awarding agency
Obligated
$37,687,510

Award facts

Contract value 100% obligated
$37,687,510.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Happy Valley, OR 97086, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00005 · Willamette national cemetery two phase design-build contract closeout $0
Supplemental Agreement for work within scope P00034 · Willamette national cemetery two phase design-build. This MOD formalizes a minor change to the cost loaded schedule $0
Additional Work (new agreement, FAR part 6 applies) P00033 $45,652
Additional Work (new agreement, FAR part 6 applies) P00032 $89,589
Additional Work (new agreement, FAR part 6 applies) P00031 · Willamette national cemetery two phase design-build. This MOD is to provide fiber, permits and water line repairs. $25,388
Additional Work (new agreement, FAR part 6 applies) P00029 · Willamette national cemetery two phase design-build. This MOD is to install irrigation pumps to ensure a complete and usable facility. $31,433
Additional Work (new agreement, FAR part 6 applies) P00030 $30,179
Additional Work (new agreement, FAR part 6 applies) P00028 $80,108
Supplemental Agreement for work within scope P00027 · Willamette national cemetery two phase design-build. This MOD is to provide wireless routers and additional fiber backbone. $45,475
Supplemental Agreement for work within scope P00023 $450,101
Supplemental Agreement for work within scope P00025 · Willamette national cemetery two phase design- build. This contract modification was issued to provide a new fiberoptic backbone between buildig 1001 and the… $85,027
Supplemental Agreement for work within scope P00020 · Willamette national cemetery two phase design- build. 1. Provide all labor, equipment, and materials to place a laydown pad across the drive lane from the… $2,453
Supplemental Agreement for work within scope P00026 $39,630
Supplemental Agreement for work within scope P00024 · Willamette national cemetery two phase design- build. This contract modification was issued to remove trees that were impacting new improvements. $27,561
Supplemental Agreement for work within scope P00021 · Willamette national cemetery two phase design- build. This modification includes steel tariff costs, flashing detail for building 3005, and repairs to the… $27,603
Supplemental Agreement for work within scope P00022 $120,610
Supplemental Agreement for work within scope P00018 $930,116
Supplemental Agreement for work within scope P00019 · Willamette national cemetery two phase design- build. This contract modification was issued to provide window coverings for the renovated cemetery… $21,779
Supplemental Agreement for work within scope P00016 $41,307
Supplemental Agreement for work within scope P00017 $53,478
Change Order P00015 $39,772
Other Administrative Action P00014 $0
Supplemental Agreement for work within scope P00012 $36,850
Supplemental Agreement for work within scope P00010 $9,189
Supplemental Agreement for work within scope P00013 $28,915
Supplemental Agreement for work within scope P00008 $125,369
Supplemental Agreement for work within scope P00009 $6,132
Supplemental Agreement for work within scope P00011 $1,510
Supplemental Agreement for work within scope P00006 $65,387
Supplemental Agreement for work within scope P00007 $93,374
Supplemental Agreement for work within scope P00003 $616,300
Supplemental Agreement for work within scope P0005 $87,640
Other Administrative Action P0004 $25,822
Other Administrative Action P00002 $3,206,761
Other Administrative Action P00001 $0
Original award $31,197,000
Show all 36

About this award

This is a $37,687,510.00 firm fixed price definitive contract awarded by the U.S. Department of Veterans Affairs (VA) Office of Construction and Facilities Management to Kiewit Infrastructure West Co. for a two-phase design-build project at the Willamette National Cemetery in Portland, Oregon. The contract does not have a set-aside designation. Kiewit Infrastructure West Co. is a subsidiary of the larger construction and engineering firm Peter Kiewit Sons Inc., which regularly performs federal infrastructure and construction contracts as both a prime and subcontractor. The project scope involves the design and construction of improvements at the Willamette National Cemetery, a VA-operated facility. The contract has an ultimate completion date of April 1, 2022.

Quick answers

Who was awarded contract VA101F17C2881?

VA101F17C2881 was awarded to Kiewit Infrastructure West CO. by VA Office of Construction and Facilities Management (Headquarters) on March 6, 2017.

How much is contract VA101F17C2881 worth?

The government has obligated $37,687,510 on VA101F17C2881.

Was contract VA101F17C2881 competed?

The extent of competition for VA101F17C2881 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award